Hitachi Energy India Q4 FY26 earnings call

Tue 26 May 2026POWERINDIA

In brief

Hitachi Energy India Q4 FY26 revenue up 46.2% YoY at Rs 2,754.1 cr; board approves additional Rs 2,000 cr capex for greenfield transformer facility

Management's tone
Confident
What was said
Leaned positive
Guidance
None given
Analyst pushback
Medium
Stock, next session
+1.01% (Nifty 50 −0.49%)
  • Q4 FY26 revenue rose 46.2% YoY to Rs 2,754.1 cr; PAT Rs 330.5 cr, up ~80% YoY; PBT margin before exceptional 16.1% vs 13.1% YoY.
  • FY26 revenue Rs 8,147.7 cr (+27.6%); PAT Rs 987.8 cr (+157.3%); PBT margin before exceptional 16.9% vs 8.1% in FY25; operating cash flow Rs 1,746.3 cr.
  • Board approved additional Rs 2,000 cr capex for greenfield large power transformer facility at Karjan, Vadodara, taking cumulative capex to ~Rs 4,000 cr; production targeted by Q4 CY2028.
  • Order backlog at Rs 29,555.3 cr as of March 31, 2026, up 53.6% YoY, providing multi-quarter revenue visibility; FY26 orders Rs 18,456.5 cr (+1.6%).
  • Mumbai 1,000 MW VSC city infeed HVDC project commissioned, reinforcing execution track record; HVDC pipeline of 3-4 projects over next 2 years flagged.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q4 FY26

This quarterA year agoLast quarterMargin
Revenue₹2,754 cr+46.2%+32.3%
EBITDA (excl. other income)₹416 cr+74.9%+43.0%15.1% (12.6% a year ago)
Net profit₹330 cr+79.7%+26.4%12% (9.8% a year ago)
EPS (₹)₹74.14+71.8%+26.4%

From the company's filed results for the quarter ended 31 Mar 2026 (standalone), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Q4 FY26 operational EBITDA / margin: said Operational EBITDA Rs 452.3 cr, margin 16.4% (per CFO commentary); filed EBITDA excl. other income Rs 416.28 cr, margin 15.1%. Management labels it 'operational EBITDA' (16.4%) while filed EBITDA excludes other income; Rs 36 cr gap suggests broader operating definition.

What moved the numbers, as management explained it

  • Q4 revenue +46.2% YoY and PBT margin 16.1% (vs 13.1% YoY) driven by strong execution on base business and operating discipline, per CFO.
  • Other expenses as % of revenue fell to 14.3% in Q4 (FY25: ~20%), supporting margin expansion through operating leverage and cost control.
  • FY26 gross margin improved ~200 bps to ~40% vs ~38% in FY25, per CFO; sequential Q4 dip attributed solely to product mix change.
  • Q4 included Rs 31.5 cr unrealised exchange loss flagged by CFO as notional; (one-off)
  • HVDC contributed only ~Rs 1,100 cr of FY26 revenue (about 15% of FY26 base); margin uplift came mainly from base/services/exports, not HVDC mix.

The numbers management led with

  • Order backlog: Rs 29,555.3 crores as of March 31, 2026, up 53.6% YoY
  • Additional capex approved: Rs 2,000 crores for greenfield transformer facility in Karjan, Gujarat
  • Cumulative capex commitment: Approximately Rs 4,000 crores (including Rs 2,000 crores announced in October 2024)
  • Additional transformer capacity: 30-40 GVA of new large power transformer capacity

Guidance

Guidance on this call

WhatForWhat management said
Additional greenfield transformer facility capexFY27-FY29Additional Rs 2,000 cr capex approved in Q4 FY26 Board; facility at Karjan, Vadodara to produce large power transformers and HVDC converter transformers.
Cumulative capexFY26-FY29Total cumulative capex close to Rs 4,000 cr (Oct 2024 programme + new Rs 2,000 cr).
New transformer facility production commencement (Transformers)Q4 CY2028Greenfield Karjan facility to begin producing large power transformers and HVDC converter transformers by last quarter of calendar year 2028.
Incremental transformer capacity (Transformers)FY27-FY29New Karjan facility to add 30-40 GVA of transformer capacity, roughly doubling existing capacity.
Export revenue share bandMedium termMaintain 25-30% of revenue from exports (excluding large HVDC lumps); FY26 print ~25%.
HVDC project pipeline (next 2 years)FY27-FY28At least 3, if not 4, HVDC projects in the next 2 years; mix of LCC and VSC; capacity not a constraint.

What changed since the Thu 5 Feb 2026 call

WhatOn the Thu 5 Feb 2026 callOn this call
Mumbai 1,000 MW HVDC project (achieved)Mumbai HVDC pre-commissioning test complete; commissioning in 2-3 weeks; no LD/delay risk flaggedMumbai city infeed project (1,000 MW VSC) commissioned; site visited by Board the morning of the call
Capex plan (raised)FY26 plan Rs 700+ cr per QIP; FY27 additional Rs 700+ cr reiterated; capex deployment slow at Rs 155 crBoard approved additional Rs 2,000 cr for greenfield transformer facility; cumulative capex now ~Rs 4,000 cr
Order backlog level (restated)Order backlog at all-time high of Rs 29,872 cr as of Q3 FY26Order backlog Rs 29,555.3 cr as of March 31, 2026; still framed as record and up 53.6% YoY
Export revenue share target (held)Target 25-30% of revenue from exports (re-anchored higher vs prior 25%); currently 29-30%FY26 export revenue ~25%; average band 25-30% retained, excluding HVDC lumps
Data center contribution framing (restated)Data center contribution currently high single digit % of ordersData center framed as 15% of addressable capex per data center; India base <2 GW projected to 13-18 GW
Barmer 6,000 MW HVDC bid (restated)Biding for Barmer 6000 MW LCC HVDC project for TBCB customers; capacity not a constraint3-4 HVDC projects expected in next 2 years; one (Barmer 6 GW LCC) already out for bidding; combination of LCC and VSC

Guided on earlier calls, and what was filed

WhatForGuidedFiled
EBITDA marginFY26at least 10% (on the Q2 FY26 call)14.3%, within the range (standalone)

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

Balance sheet, capex and funding

  • FY26 operating cash flow Rs 1,746.3 cr; FY26 capex deployment under Rs 700+ cr QIP plan was lagging earlier in the year.; look at our strong operating cash this year of Rs. 1,746.3 Crores
  • New Rs 2,000 cr capex approved in Q4 Board; cumulative capex now ~Rs 4,000 cr (Oct 2024 plan + new greenfield).; our total cumulative capex stands close to Rs. 4,000 Crores
  • Q4 finance cost described as negligible; depreciation ~1% of revenue.; Depreciation, 1%, finance cost negligible
  • Greenfield Karjan, Vadodara facility groundbreaking set for June 12, 2026; production targeted by last quarter of CY2028.; we are doing the groundbreaking ceremony on 12th of June
  • New facility will add 30-40 GVA of large power transformer / HVDC converter transformer capacity, roughly doubling existing capacity.; We are going to create anywhere between 30 GVA to 40 GVA
  • Q4 personnel expenses 6.3% of revenue; FY26 full year 7.9% of revenue.; Personnel expenses as a % of revenue for this quarter was 6.3%

The industry, as management sees it

India's electricity demand is poised for strong sustained growth over the coming decade, driven by industrial expansion, renewable integration, EV adoption, and rapid scale-up of new-age load centers such as data centers. The grid is becoming more complex with higher load density, AI-led workloads, and increasing reliability requirements — leading to significant investments across transmission, distribution, and grid infrastructure. Battery energy storage pipeline is ~80 GW over 5-6 years, and data center capacity is expected to grow 6-9x from current <2 GW to 13-18 GW.

Risks management named

  • Geopolitical/Middle East supply chain pressure creating temporary industry slowdown
  • Commodity price volatility and elevated freight costs (Hormuz route impact)
  • Unrealized exchange loss of Rs 31.5 cr in Q4FY26
  • Product mix-driven sequential gross margin compression
  • Royalty obligations on technology sourced from parent for new product segments

Q&A

Q&A was dominated by export strategy (3-pronged approach covering allocated markets, global feeder factories and contract manufacturing), the HVDC margin and pipeline story, and the freshly announced Rs 2,000 cr capex for the Karjan transformer facility. Pushback was strongest on domestic non-HVDC order inflow ex-services/exports, with analysts flagging apparent weakness in FY26 base orders — management pushed back claiming growth, but with limited supporting numbers. Forward numbers were not provided (consistent with stated no-guidance policy). Other meaningful exchanges covered data center sizing (15% addressable, 6-9x growth from ~2 GW to 13-18 GW), HVDC capacity (no constraints for next 2 years, 3-4 projects in pipeline) and royalty/technology sourcing obligations from parent.

Not answered directly

  • Exact export order intake and revenue numbers for FY26
  • FY27 domestic non-HVDC order growth outlook (qualitative only)
  • Base orders ex-services and exports commentary
  • Transformer delivery timeline specifics for export market
  • Detailed HVDC mix impact on FY27 margins

Asked for a number, answered without one

  • Exact export order intake and revenue (FY26 and Q4): Management declined to share absolute numbers; gave only a 25-30% ballpark, noting exact figures are typically taken excluding large HVDC lumps.
  • HVDC order breakup across Marinus, Adani, PGCIL, Mumbai for FY26: CFO gave only a rough figure of Rs 1,100 cr or ~15% of FY26 base revenue; no project-wise split provided.
  • Number of products in feeder-factory / India-only category: MD said exports overall are ~30% of revenue and feeder factory is 'low risk and stable margin' but did not give a count or share.

Every question, with its answer

  1. 1. Exports strategy and 3-pronged approach

    Parikshit Kandpal, HDFC Securities

    Question. On exports: order inflow from exports looks robust at ~Rs 3,000 cr+ this year. How are you generating these inquiries across U.S., Europe and APAC, and do you compete with parent entities in these geographies?

    Answer, N Venu, Managing Director & CEO. Export strategy is 3-pronged: (1) allocated markets developed on a long-term basis together with local sales/marketing organizations — no two Hitachi Energy companies compete in any market; (2) global feeder factories where India exclusively manufactures certain products (e.g. 66 kV high circuit breakers, COMBIFLEX relays) sold globally, some directly and some through Hitachi Energy offices (becomes related party); (3) feeder factories supplying components to other Hitachi Energy factories in U.S., Germany, Sweden, Switzerland etc.

  2. 2. HVDC revenue mix and margin

    Parikshit Kandpal, HDFC Securities

    Question. On HVDC margin: peers are at 25%+ EBITDA while we are at 14-15% with high royalty burden. How much of FY26 revenue was HVDC across the 3 HVDCs (Marinus, Adani, Power Grid, Mumbai entry), and is there scope for further margin improvement given two-thirds of order book is HVDC?

    Answer, N Venu, Managing Director & CEO. HVDC is margin-accretive but was not very substantial in this quarter or this year. Whole-year HVDC revenue out of Rs 8,000 cr is around Rs 1,100 cr (~15%). Focus has been on base business, service, exports and other levers; HVDC is one of the growth levers, not the only one.

  3. 3. Services order geography

    Parikshit Kandpal, HDFC Securities

    Question. On services order in Q4: was the high services order from India (HVDC upgrade) or global? Is it part of the export order book?

    Answer, N Venu, Managing Director & CEO. The service upgrade is from India — for MSETCL customers, upgrade of control and protection. It is not part of exports.

  4. 4. Base orders ex-services and exports

    Parikshit Kandpal, HDFC Securities

    Question. Base orders look very weak this year — possibly even declining YoY if services and exports are removed. What is your commentary on base ordering?

    Answer, N Venu, Managing Director & CEO. We have seen our base orders also had strong growth for the whole of financial year.

    Not answered directly.

  5. 5. FY27 domestic order pipeline

    Mohit Kumar, ICICI Securities

    Question. On domestic order inflow ex-HVDC (domestic + exports ex-HVDC ~Rs 9,000 cr last year): how do you see this developing for FY27 and what is the inquiry pipeline ex-HVDC in domestic market?

    Answer, N Venu, Managing Director & CEO. We don't give forward-looking numbers. Ex-HVDC, pipeline is very strong in renewables and data centers; equally strong in transmission and other projects; industries showing intermittency but coming up. Transformer pipeline across segments also very strong; pipeline compared to a year ago and quarter ago is very good.

    Not answered directly.

  6. 6. HVDC transformer capacity and BHEL arrangement

    Mohit Kumar, ICICI Securities

    Question. On the new transformer capacity: does it mean Hitachi will produce HVDC transformers internally going forward, replacing the BHEL arrangement on the 2 HVDC packages?

    Answer, N Venu, Managing Director & CEO. Existing won projects will stay as they are — no change in those orders. New facility is for additional capacity to meet demand, not to replace any arrangement. In the new facility, we will manufacture not only large power transformers but also converter transformers (VSC and LCC) and large power transformers for data centers. We have done a complete 360 view before putting up this capacity and have a strong business case.

  7. 7. Sequential gross margin contraction

    Sumit Kishore, Axis Capital

    Question. Gross margins contracted significantly on a sequential QoQ basis. What was the mix change or factors that drove this outcome?

    Answer, Ajay Singh, Chief Financial Officer. Sequential QoQ gross margin contraction is only because of product mix. On full-year basis, gross margin improved by 200bps — from ~38% last year to ~40% this year. Margin accretion work is ongoing; product mix causes some sequential volatility.

  8. 8. Non-HVDC domestic order weakness

    Sumit Kishore, Axis Capital

    Question. Overall order inflow grew 1.6%, but excluding HVDC, the non-HVDC domestic order inflow appears to be falling in FY26 over FY25. What led to this and what's the outlook?

    Answer, N Venu, Managing Director & CEO. When we investigated, it is not the case with us. Some of the capacities required probably will be filled in with the HVDC portfolio — that's also why some orders which are required at the same time may not be possible. Otherwise, even excluding non-HVDC orders, there has been growth in domestic as well.

    Not answered directly.

  9. 9. Capex capacity in GVA

    Sumit Kishore, Axis Capital

    Question. On the Rs 2,000 cr capex: what kind of physical capacity for power transformers in GVA terms will this create?

    Answer, N Venu, Managing Director & CEO. We are going to create anywhere between 30 GVA to 40 GVA, exactly close to our existing factory. This is additional capacity — baseline 30 GVA, depending on product mix can go to 40 GVA, effectively doubling capacity.

  10. 10. Local content, capex drivers and royalty

    Amit Anwani, PL Capital

    Question. Clarification: after adding the new capacity, will total capacity be 30-40 GVA or is that the incremental addition? Also, on minimum local content — what's the status on the 2 HVDC projects, and is the capex also driven by the localization drive (30%+ now, going up over 5-7 years)? Will this also reduce royalty?

    Answer, N Venu, Managing Director & CEO. 30-40 GVA is additional capacity, doubling the existing. On local content, we are far ahead of the recent government circular requirements and have been consistently increasing local content. New capacity has nothing to do with local requirements — it's based on demand from renewables, transmission and data centers. On royalty: we manufacture locally but continue to get technology from principals; we need to pay royalty for new technologies and products in data centers, energy storage etc. to ensure those technologies are available at the same time as globally. CFO added that R&D spend is managed centrally — no R&D spend at India level.

  11. 11. Capex purpose and product gaps

    Puneet Gulati, HSBC

    Question. Can you talk about any big gaps in your portfolio that you would want to address with the Rs 2,000 cr capex?

    Answer, N Venu, Managing Director & CEO. Rs 2,000 cr is not about gaps. Majority is going into existing products: (1) new greenfield large power transformer facility in Karjan, Vadodara (additional capacity, in addition to existing Baroda/Maneja facility); (2) two additional power quality lines (7th and 8th) at Bangalore factory. Not addressing product gaps — addressing demand from electrification of more sectors.

  12. 12. Capex phasing and capitalization timeline

    Puneet Gulati, HSBC

    Question. How should one think about phasing the Rs 4,000 cr cumulative capacity over the next 2-3 years? When should we expect different phases of capitalization?

    Answer, N Venu, Managing Director & CEO. Of the Rs 4,000 cr, Rs 2,000 cr announced in October 2024 is largely on ground; many of those projects take 3-4 years to complete. Additional Rs 2,000 cr — groundbreaking ceremony on 12th June; transformer manufacturing from this new facility by last quarter of calendar year 2028. Investigation was for a multiyear growth story, not 1-3 year spike.

  13. 13. Renewables and data center share in order book

    Subhadip Mitra, Nuvama

    Question. On renewables and data center: how much of these are part of current revenues and order book, and what is the growth trajectory going ahead?

    Answer, N Venu, Managing Director & CEO. All segments are part of the order book. Transmission is highest, followed by renewable, then industry/service/exports. Data centers in India are at less than 2 GW today but going multifold in next 4-5 years. Even on a small base, the growth rate percentage is much higher. Battery energy storage is also significant — almost 80 GW of battery storage for the next 5-6 years per CEA report.

  14. 14. Manufacturing localization for new segments

    Subhadip Mitra, Nuvama

    Question. For data center and battery energy products, are these products already being manufactured in India or would they need to be imported from parent and then supplied?

    Answer, N Venu, Managing Director & CEO. Combination of both: some products already being manufactured in India and we are going to expand our product basket; some are available in parent and we will localize them. Localization is important to meet the price point required by Indian customers — importing alone won't allow sustainable growth.

  15. 15. Exports order intake and revenue numbers

    Jason Soans, IDBI Capital

    Question. Can you share the export order intake and export revenue for FY26 as exact numbers?

    Answer, Ajay Singh, Chief Financial Officer. Export revenue at year-end is around 25%; orders will be on similar lines. Currently looks a bit lower because we have booked large domestic orders; average exports are 25-30%. Venu added: when discussing percentages, always exclude large lumpy items like HVDC orders.

    Not answered directly.

  16. 16. HVDC pipeline and capacity availability

    Jason Soans, IDBI Capital

    Question. On near-term HVDC pipeline for next 2 years: is it more LCC or VSC? Given the company has already won 2 mega 6 GW projects, do you have the capacity to take on more for the next couple of years?

    Answer, N Venu, Managing Director & CEO. Pipeline is very robust. One project has already come up for bidding for TBCB customers; several others in the pipeline. In the next 2 years, we are talking about 3-4 projects. Capacity will be consistent — it's a combination of LCC and VSC, doesn't matter which, since we have global leadership in both. We have no limitation as of now to take more HVDC projects now and next year or year after; we have been building capacity since 2022 (HVDC and control production factory in Chennai) and are now setting up additional transformer factory for converter transformers in anticipation of demand.

  17. 17. Exports market composition and data center exposure

    Shirom Kapur, Jefferies

    Question. On exports: which markets are you getting demand from, and is it largely third-party or driven by orders from parents? Specifically, are you catering to the data center market in U.S. or other global parts?

    Answer, N Venu, Managing Director & CEO. Three categories: (1) allocated markets developed on a long-term sustainable basis — Indian subcontinent (Bangladesh, Sri Lanka, Nepal, Bhutan), Southeast Asian countries; sell directly to third-party customers (e.g. GIS sold to Southeast Asian and some European customers); (2) global feeder factory — sell to our organization/Hitachi Energy offices worldwide (sometimes becomes related party); (3) feeder factory manufacturing components as contract manufacturing for Hitachi Energy factories worldwide (through parent organizations).

  18. 18. Q4 industry slowdown and transmission delays

    Shirom Kapur, Jefferies

    Question. You mentioned a temporary industry slowdown in Q4 and delays in some transmission projects that caused a small dip in transmission orders. What are these delays, how long will they go on, and is it already behind us?

    Answer, N Venu, Managing Director & CEO. In my view, it is behind us. Transmission projects are in the pipeline. Industrial capex shows good momentum in steel and other industries. Investments are coming in transmission, renewable, fossil power plants, data center, semiconductor, batteries to industries, and automobile expansions.

    Partly answered.

  19. 19. Exports: SAARC and Southeast Asia allocation

    Rahul Gajare, Macquarie Capital

    Question. On exports to SAARC and Southeast Asia: is it all necessarily catered by Hitachi India itself, or do you compete with other Hitachi entities in Southeast Asia?

    Answer, N Venu, Managing Director & CEO. Some allocated markets will be catered by Hitachi Energy India only. Indian subcontinent (Bangladesh, Sri Lanka, Nepal, Bhutan) and Southeast Asian countries are allocated — entire portfolio in Southeast Asian countries is part of our portfolio here.

  20. 20. Feeder factory revenue contribution

    Rahul Gajare, Macquarie Capital

    Question. On the feeder factory: how many of these products are there, and how much of your revenue do they make up? Will this be continuous regardless of export volumes?

    Answer, N Venu, Managing Director & CEO. It's more like a contract with our companies — pass-through, low risk and stable margin kind of thing. It is growing. Whole of exports is in the range of 30% or so.

    Partly answered.

  21. 21. Transformer delivery timeline

    Rahul Gajare, Macquarie Capital

    Question. On timeline of transformer supply for the export market — and is the timeline different for 765 kV vs 400 kV?

    Answer, N Venu, Managing Director & CEO. We have so much demand for transformers from the domestic market that our focus continues to maintain our domestic market. One of the reasons for increasing capacity is to cater to domestic demand and new segments like data centers. Timeline is highly dynamic — we deliver in 15 months for some, 12 months for some. Always tell customers to order as early as they can so we can plan better.

    Not answered directly.

  22. 22. Data center opportunity size

    Randy Lau, Goldman Sachs

    Question. How should we think about the data center opportunity for Hitachi Energy, particularly with respect to domestic and global competitors over the next 5 years?

    Answer, N Venu, Managing Director & CEO. Data center market in India is currently less than 2 GW; projections are 13-18 GW depending on data source — 6-9x capacity growth. For every data center, 15% of capex is Hitachi Energy addressable. The addressable market is expanding 6-8x.

  23. 23. Price escalation and inflation pass-through

    Randy Lau, Goldman Sachs

    Question. In the current inflationary commodity price environment, how effective has the price escalation process been in protecting margins of your HVDC and transformer contracts?

    Answer, N Venu, Managing Director & CEO. Geopolitical challenges are causing elevated inflation, elevated metal prices and elevated transport charges (Hormuz affected). Most of our portfolio has commodity price pass-through with a price variation clause built into contracts — we do that openly and transparently. Things we cannot pass through are inflated freight, which we are looking at how to manage. We have several mitigation initiatives actively.

What was said

Topic by topic, in the order it was spoken

Safety and License to Operate · N Venu (MD & CEO)

  • Zero fatalities during FY26 across factories, project sites and offices
  • Conducted more than 1,700 life-saving rule inspections during the year
  • Annual health checkups and ongoing safety awareness sessions for employees and subcontractors
  • Recognized by leading third-party agencies and customers for enhancing safety culture at project sites

Sustainability and ESG Progress · N Venu (MD & CEO)

  • 100% renewable energy in operations via rooftop solar and long-term PPAs with solar developers
  • 11% water reduction from 2019 baseline through recycling and efficient fixtures
  • Halol (Gujarat) facility earned Water Positive Index certification; both Halol and Mysore facilities certified platinum for zero waste to landfill
  • Substantial increase in gender diversity; zero integrity incidents in FY26
  • ESG ratings improved: Crisil 61 (strong) and NSE 62 (adequate)

Market Context and Demand Drivers · N Venu (MD & CEO)

  • Middle East geopolitical situation creating temporary supply chain pressure across the industry; mitigation measures in place
  • Structural transformation in India's energy landscape: energy security, policy support, localization and accelerating electrification
  • Demand drivers: industrial expansion, renewable integration, EV adoption, data center scale-up, AI-led workloads, DISCOM health improvement
  • Multi-year growth opportunity across transmission, distribution and grid infrastructure; Hitachi Energy well-positioned via market presence, execution and technology

Q4 FY26 Financial Performance · N Venu (MD & CEO) and Ajay Singh (CFO)

  • Q4 orders Rs 2,422.5 cr (+10.6% YoY); revenue Rs 2,754.1 cr (+46.2% YoY)
  • Q4 PBT Rs 443.4 cr (PBT margin 16.1% vs 13.1%); PAT Rs 330.5 cr (+80% YoY) at 12% margin
  • Q4 operational EBITDA Rs 452.3 cr at 16.4% margin (+33.7% sequentially)
  • Full year FY26 orders Rs 18,456.5 cr (+1.6%); revenue Rs 8,147.7 cr (+27.6%)
  • FY26 PBT Rs 1,375.2 cr (+166.3%); PAT Rs 987.8 cr (+157.3%); operational EBITDA Rs 1,252.5 cr at 15.4% margin (vs 9.3%)
  • Order backlog of Rs 29,555.3 cr as of March 31, 2026 (+53.6% YoY); operating cash flow Rs 1,746.3 cr

Project Commissioning Highlights · N Venu (MD & CEO)

  • Successfully commissioned India's first 1,000 MW VSC-based city infeed project in Mumbai (Aarey and Kudus HVDC converter stations)
  • Commissioned Barmer renewable substation; supplied transformers to leading utilities; delivered AIA substation in Rajasthan
  • End-to-end scope: design, engineering, manufacturing, supply, erection, testing and commissioning
  • Reinforces execution capabilities for diverse segments and geographies

Order Intake Composition FY26 · N Venu (MD & CEO)

  • Growth across industry, data centers, railways and renewables segments
  • Small dip in transmission segment attributed to mismatch vs large orders booked in FY25
  • Product segment leads the order mix; utilities and direct end customers emerge as clear winners by sector and channel

Capex and Capacity Expansion · N Venu (MD & CEO)

  • Board approved additional Rs 2,000 cr capex for greenfield large power transformer facility in Karjan, Vadodara (Gujarat)
  • Facility will produce large power transformers and HVDC converter transformers (both VSC and LCC technologies)
  • Targeted commissioning by Q4 CY2028; this is over and above the Rs 2,000 cr program announced in October 2024
  • Cumulative capex commitment now stands close to Rs 4,000 cr; 30-40 GVA of additional capacity to be created
  • Additionally adding 7th and 8th power quality lines at Bangalore factory in response to demand

Detailed Financial Performance (CFO Walk) · Ajay Singh (CFO)

  • Q4 personnel expenses at 6.3% of revenue; other expenses pulled down to 14.3% of revenue
  • Q4 exchange loss of Rs 31.5 cr (unrealized/notional); depreciation ~1%; finance cost negligible
  • FY26 gross margin improved by ~200bps to ~40% (vs ~38% prior year)
  • FY26 personnel expenses at 7.9% of revenue; other expenses at 16.9% (vs 20% prior year)
  • FY26 PBT margin 16.2% (vs 8.1%); PAT margin 12.1% (vs 6%) — significant operating leverage on volume growth

Strategic Outlook and Priorities · N Venu (MD & CEO)

  • Two clear priorities: sustain growth momentum and improve operational efficiency across all areas
  • Expand into high-growth areas: energy storage, services, exports, digital innovation (AI Nexus program)
  • Maintain leadership in utilities, HVDC, industries and data centers; strengthen service business in India as a key pillar
  • Drive productivity and operational excellence with emphasis on quality and scalability
  • Continue investment in people, technology and capacity expansion to support sustainable multi-year growth

In their words

A key highlight is our record order backlog of Rs 29,555 crores as of March 31, 2026, which provides a strong revenue visibility for several quarters going forward.
N Venu (MD & CEO, Hitachi Energy India Limited)
We don't have any limitation as of now to take more HVDC projects now and the next year or year after and we are creating those capacities.
N Venu (MD & CEO, Hitachi Energy India Limited)
Every data center, 15% of data center capex is Hitachi Energy. And if you look at the addressable market is expanding by anywhere 6 to 8x depending upon the data from the various officials, So it's quite substantial.
N Venu (MD & CEO, Hitachi Energy India Limited)

To check next time

What management committed to on this call, or the dates they gave.

  • Groundbreaking ceremony at Karjan, Vadodara on June 12, 2026; track land/site progress against CY2028 production target.
  • FY27 capex deployment pace against revised ~Rs 4,000 cr cumulative programme.
  • Outcome of Barmer 6,000 MW LCC HVDC TBCB bid and other HVDC pipeline awards (3-4 projects expected over 2 years).
  • Sustainability of Q4 PBT margin 16.1% and FY26 EBITDA margin 15.4% as product mix evolves.
  • Export order momentum vs 25-30% revenue share band; watch for parent-vs-third-party split.
  • Trajectory of non-HVDC domestic base orders following Q4 commentary that they are growing.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Tue 26 May 2026₹35,995.00+1.01%−0.49%
5 sessions Tue 2 Jun 2026₹35,105.00−1.49%−2.28%
20 sessions Tue 23 Jun 2026₹36,090.00+1.28%−0.86%

From the close of Mon 25 May 2026, ₹35,635.00: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Hitachi Energy India's other calls

  • Q2 FY27Wed 18 Nov 2026Not read
  • Q2 FY27Thu 12 Nov 2026Tone: Confident
  • Q3 FY26Thu 5 Feb 2026Tone: Confident
  • Q2 FY26Fri 7 Nov 2025Tone: Confident
  • Q1 FY26Wed 30 Jul 2025Tone: Confident
  • Q4 FY25Thu 15 May 2025Tone: Confident
  • Q3 FY25Thu 30 Jan 2025Tone: Confident
  • Q2 FY25Tue 29 Oct 2024Tone: Confident
  • Q1 FY25Thu 25 Jul 2024Tone: Mixed
  • Q4 FY24Wed 22 May 2024Tone: Confident