Jindal Drilling Ind. Q2 FY25 earnings call

Wed 30 Oct 2024JINDRILL

In brief

Management's tone
Confident
What was said
Leaned positive
Guidance
None given
Analyst pushback
Low
Stock, next session
+8.47% (Nifty 50 −0.51%)
  • Jindal Supreme deployed with ONGC on 15 Oct 2024 — ahead of November timeline — at $88,859/day vs prior $40,700, full flow-through to EBITDA as company-owned rig
  • Jindal Pioneer acquisition from JV pending statutory approval; filed April 2024, expected shortly — would move rig from 49% JV economics to 100% in JDIL
  • Net cash position improved to ₹69 cr (Sep 2024) from ₹51 cr (March 2024); debt to fall from ₹173 cr to ₹132 cr by March 2025
  • Jindal Explorer renewal tender expected Nov/Dec 2024; current ONGC benchmark rate ~$64,000, MD expects to 'maintain if not improve' given tighter rig market
  • Management working on simplifying group structure to consolidate assets into JDIL — flagged as valuation-accretive

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY25

This quarterA year agoLast quarterMargin
Revenue₹173 cr+21.4%+0.9%
EBITDA (excl. other income)₹31.2 cr−41.2%−18.9%18.1% (37.4% a year ago)
Net profit₹0 cr——0% (0% a year ago)
EPS (₹)₹11.90+56.0%−21.4%

From the company's filed results for the quarter ended 30 Sept 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

The numbers management led with

  • Jindal Supreme new day rate: USD 88,859/day (vs prior USD 40,700/day)
  • Refurbishment capex on Jindal Supreme: More than ₹130 crore, driven by MODU standard change
  • Total debt repayment schedule: ₹173 cr → ₹132 cr by 31 Mar 2025; ₹66 cr in FY26 and ₹66 cr in FY27

Guidance

Guidance on this call

WhatForWhat management saidOn the Q1 FY25 call
Rig day rate (Jindal Supreme)Oct 2024 - Oct 2027Deployed 15 Oct 2024 at $88,859/day on a 3-year fixed contract with ONGC (raised)Operating day rate of $88,859/day from Q3 FY25
Total debtFY25-FY27₹173 cr to reduce to ₹132 cr by 31 March 2025, with ₹66 cr repayment each in FY26 and FY27—
Net cash positionFY25-FY27Currently ₹69 cr; expected to improve rapidly on internal accruals and JV cash generation—
Jindal Explorer contractQ4 FY25Current contract ends May 2025; ONGC tender expected Nov/Dec 2024, likely extended to Aug/Sep 2025 for refurbishment—
Jindal Pioneer acquisitionnear-termApplication filed April 2024; statutory approval expected shortly, which would move Pioneer from 49% JV economics to 100% in JDIL—
Said on the Q1 FY25 call, not repeated on this one (3)
  • EBITDA margin: 30-35% when all rigs are operational; current blend is 2 owned and 3 rented rigs
  • Gross debt reduction: Gross debt will reduce rapidly over next 12 months as all rigs now contracted on new ONGC contracts at higher rates
  • Q2 FY25 standalone earnings: Earnings will decline sequentially in Q2 FY25 on account of Jindal Supreme refurbishment

The business

The industry, as management sees it

International rig market firming on continued geopolitical tensions and Aramco rig shelving, which is helping pricing. ONGC is short of rigs (less than 7 available) and continues tendering activity, though has cancelled two recent tenders where bidder rates were too high or rigs were too old to deliver on time.

Risks management named

  • ONGC has cancelled/postponed two tenders in 2024 due to rate pressure
  • Jindal Explorer contract expires May 2025; rig may be off-hire Aug-Oct 2025 for refurbishment
  • Pioneer acquisition awaiting statutory approval; outcome timing uncertain
  • International rig market remains exposed to geopolitical and Aramco decisions

Q&A

The Q&A was constructive and information-rich, with analysts testing the drivers of the QoQ EBITDA decline, the quantum of Supreme refurbishment amortisation, and the value unlock from acquiring Pioneer. Management declined to share specific refurbishment numbers (deflected) but was forthcoming on the day-rate uplift on Supreme ($40,700 → $88,859), the debt schedule, and the ONGC tender outlook. Pushback was minimal; the only meaningful analyst friction was on the quantum of one-off costs going forward, which management was clear on.

Not answered directly

  • Jindal Supreme quarterly refurbishment amortisation
  • Specific EBITDA impact of Pioneer acquisition

Every question, with its answer

  1. 1. Jindal Supreme refurbishment cost

    Swapnil Kabra, SK Enterprises

    Question. What was the total cost of refurbishment of Jindal Supreme and how was it spread over the quarters? Can you quantify the impact per quarter?

    Answer, Kaushal Bengani, DGM, IR & Finance. Management does not share rig-wise refurbishment numbers. Cost was significant due to a change in MODU safety standard. The expenditure is being amortised over three years (the contract duration) — consistent with how other rig refurbishments have been treated.

    Not answered directly.

  2. 2. Contract renewal risk / international markets

    Swapnil Kabra, SK Enterprises

    Question. If ONGC does not renew contracts after they end, do you have backup plans to deploy rigs internationally?

    Answer, Raghav Jindal, Managing Director. Jindal Supreme is on a fixed 3-year contract, locked in. For other rigs coming off contract, MD sees continuing ONGC contracts. If not, the company is in touch with international markets, particularly the Far East, and sees strong global demand supported by geopolitical tensions lifting day rates.

    Follow-up. So you do not see any risk there, right?

    Answer. No risk — strong global demand and prices rising again with the war; 'great market to be in'.

  3. 3. Jindal Supreme day rate economics

    Pritesh, Lucky Securities

    Question. What is the incremental day rate on Jindal Supreme versus the original and how much should flow to EBITDA?

    Answer, Kaushal Bengani, DGM, IR & Finance. Original deployment at $40,700 (contract ended March 2024); new contract from 15 Oct 2024 at $88,859. As a company-owned rig, margins are higher than a rented rig. Since the rig was profitable at $40,700, incremental rate flows to EBITDA.

    Follow-up. Should I say bulk of it will flow down to EBITDA?

    Answer. Yes.

  4. 4. QoQ EBITDA bridge

    Pritesh, Lucky Securities

    Question. Standalone EBITDA fell ~₹10 cr QoQ though both quarters were without Jindal Supreme — what is normalised EBITDA without Supreme?

    Answer, Kaushal Bengani, DGM, IR & Finance. Higher operational refurbishment expenses on Jindal Supreme were booked in Q2 (larger component near deployment) plus depreciation. Q1 also had some of these expenses. Refurbishment costs tend to rise as the deployment date nears.

    Partly answered.

  5. 5. Pioneer acquisition EBITDA impact

    Pritesh, Lucky Securities

    Question. On the Pioneer acquisition, when it comes through and Supreme starts at the revised rate, are we looking at 3-4x type improvement in quarterly EBITDA?

    Answer, Kaushal Bengani, DGM, IR & Finance. Did not give a specific multiple. Maximum profit comes from company-owned rigs — two of which (Discovery I, and now Supreme) will be in the fleet. Earnings improvement will be visible next quarter and step up further if Pioneer is acquired (moving from 49% JV economics to 100%).

    Not answered directly.

  6. 6. Debt and net cash trajectory

    Pritesh, Lucky Securities

    Question. In absence of any acquisition or asset creation, what should the debt/net cash position look like in 2025 and 2026?

    Answer, Kaushal Bengani, DGM, IR & Finance. Debt of ₹173 cr to fall to ₹132 cr by 31 March 2025; ₹66 cr repayments each in FY26 and FY27. With internal cash generation and JV cash flows, net cash position (currently ₹69 cr) will improve rapidly.

  7. 7. Rig renewal pipeline

    Pritesh, Lucky Securities

    Question. Do you have a rig renewal and repricing lined up in the next 4-6 quarters, or are you done?

    Answer, Raghav Jindal, Managing Director. Jindal Explorer (rented rig) is up for renewal. ONGC is in talks for two new tenders before year-end; Antique expects to participate and win. Contract ends May 2025; rig will likely extend to Aug/Sep 2025, then a couple of months for refurbishment before the next contract.

    Follow-up. Since it's a lease asset, do you have to incur the refurbishment or the owner?

    Answer. Depends on how the new contract is negotiated between owner and operator; will update when completed.

    Partly answered.

  8. 8. Supreme refurbishment cost quantum

    Nirvana Laha, Badrinath Holdings

    Question. Jindal Supreme refurbishment accounting — is it the same treatment as other refurbished assets? Estimated total ₹115-120 cr, quarterly amortisation ~₹10 cr — are these broadly correct?

    Answer, Kaushal Bengani, DGM, IR & Finance. Confirmed accounting treatment is consistent. Total refurbishment is actually more than ₹130 cr due to MODU standard change. Would not give the quarterly amortisation figure.

    Follow-up. Is the quarterly amortisation closer to ₹20 cr or ₹10 cr?

    Answer. We are not giving that out for any rig.

    Not answered directly.

  9. 9. Jindal Supreme P&L waterfall

    Nirvana Laha, Badrinath Holdings

    Question. Is there any cost below EBITDA on Jindal Supreme, or does EBITDA flow straight to PBT?

    Answer, Kaushal Bengani, DGM, IR & Finance. There is interest cost on the ₹173 cr debt secured against Supreme, but that debt is for refurbishment across multiple rigs over past quarters — not solely for Supreme.

  10. 10. Forward one-offs

    Nirvana Laha, Badrinath Holdings

    Question. Are there any one-off costs expected in the next 4 quarters (excluding acquisitions)?

    Answer, Kaushal Bengani, DGM, IR & Finance. Recent one-offs were Virtue I deployment expenses (Oct 2023) and the JV rig markdown to $75 million (March 2024). No significant one-offs expected going forward — though by nature one-offs are unpredictable.

  11. 11. ONGC tender cancellations / Explorer

    Nirvana Laha, Badrinath Holdings

    Question. ONGC has cancelled two tenders in June and September — your read on the situation, and are you in talks on the Explorer contract?

    Answer, Raghav Jindal, Managing Director. Cancellations were due to rates being higher than ONGC expected — the international market had softened at that point on Aramco shelving rigs. Now with the war continuing, international prices are firming which supports Explorer. ONGC is short of rigs and Antique will participate in the next two tenders. Rates should hold or improve; any decline would not be sharp.

    Follow-up. From ONGC's strategic point of view, can it afford to let Indian operators move rigs out of Indian waters?

    Answer. ONGC does not want rigs deployed outside India. When Pioneer (built for ONGC) went abroad, ONGC lost a new rig and has been following up on when Pioneer returns. ONGC has dependence on efficient operators.

  12. 12. Rig relocation logistics

    Nirvana Laha, Badrinath Holdings

    Question. If a rig had to be moved out of India, what costs are required to dismantle, move and reassemble?

    Answer, Raghav Jindal, Managing Director. No dismantling needed. Far moves use a dry tow; nearby moves use a wet tow. Only additional equipment or certification required by a new contract would be needed.

  13. 13. Explorer tender timeline

    Udit Sehgal, Tradewalk Research, LLP

    Question. When can we expect the Explorer renewal tender from ONGC and by when do you have to take a call?

    Answer, Raghav Jindal, Managing Director. Tender not yet out; expected in November or December. Award typically takes about 30 days.

  14. 14. Pioneer deployment plans

    Udit Sehgal, Tradewalk Research, LLP

    Question. Once Pioneer is on your books, do you intend to charter it out to ONGC?

    Answer, Raghav Jindal, Managing Director. Pioneer is contracted in Mexico till its term ends. After that, it is open — likely to come back to ONGC, which has expressed interest. MD says the aim is to bring it into ONGC.

  15. 15. ONGC rate environment

    Udit Sehgal, Tradewalk Research, LLP

    Question. Macro: why does ONGC keep cancelling tenders — is it rate pressure?

    Answer, Raghav Jindal, Managing Director. It's about rates. Some bidders quoted very old rigs needing huge investment and could not deliver on time. ONGC negotiates hard. Last benchmark was ~$64,000. International market is now firmer; ONGC should maintain or marginally improve rates — range could be $65,000 to $85,000 depending on conditions.

    Follow-up. Any plan to buy the rig with Maharashtra Seamless?

    Answer. Nothing decided as of now.

  16. 16. IR visibility and structure simplification

    Udit Sehgal, Tradewalk Research, LLP

    Question. Suggestion: Jindal Drilling has great cash flows ahead but limited public visibility — could you have an IR team / broker coverage?

    Answer, Kaushal Bengani, DGM, IR & Finance. Started earnings calls and presentations a few quarters ago; visibility takes time. Main reason for low visibility is absence of direct institutional broker coverage, which is not in management's control. What is in control — improving operations, presentations, earnings calls and shareholder engagement — is being done. Additional year-wise revenue split added this time. Management is also working on simplifying the structure so rig assets are consolidated into Jindal Drilling, which will immediately impact valuation and earnings.

What was said

Topic by topic, in the order it was spoken

Q2 FY25 Financial Performance and Drag from Supreme Refurbishment · Kaushal Bengani (DGM, IR & Finance)

  • Q2 FY25 revenue largely flat QoQ but EBITDA down 21% and PAT/EPS down ~30%; the decline was pre-communicated and reflects Jindal Supreme refurbishment and depreciation
  • Year-on-year profitability dip is structural: only one company-owned rig (Discovery I) operated in Q2 FY25 vs two (Discovery I and Jindal Supreme) in Q2 FY24
  • Refurbishment expenditure on Jindal Supreme exceeded ₹130 cr, primarily driven by a change in MODU safety standard required by ONGC
  • Rig segment contributes ~90% of total EBITDA — the area of focus for further growth

Jindal Supreme Deployment with ONGC · Kaushal Bengani (DGM, IR & Finance)

  • Jindal Supreme commenced operations with ONGC on 15 October 2024, ahead of the November 2024 timeline previously communicated
  • Deployed at a day rate of $88,859 on a 3-year fixed contract — versus the previous contract day rate of $40,700 that ended in March 2024
  • Being a company-owned rig, incremental revenue will flow through to EBITDA with margins higher than rented rigs
  • Larger component of refurbishment operational expenses hit Q2 as deployment date neared; amortised over the 3-year contract duration

Jindal Pioneer Acquisition from JV · Kaushal Bengani (DGM, IR & Finance)

  • Acquisition of Jindal Pioneer from the joint venture is in the final stage; application filed with statutory authority in April 2024
  • Currently only 49% of JV profit accrues to Jindal Drilling; full consolidation expected to materially step up earnings once approval lands
  • Authority engagement is ongoing and management is 'hopeful' the matter will be approved shortly
  • No decision yet on the rig held with Maharashtra Seamless

Balance Sheet Strength and Debt Schedule · Kaushal Bengani (DGM, IR & Finance)

  • Net cash position improved to ₹69 cr as of September 2024 from ₹51 cr at March 2024
  • Total debt of ₹173 cr (secured against Jindal Supreme) to reduce to ₹132 cr by 31 March 2025
  • Repayment schedule thereafter: ₹66 cr each in FY26 and FY27
  • Fully paid one loan against Discovery I in FY25 from internal accruals, demonstrating cash generation capability

Order Book, Business Overview and Fleet · Kaushal Bengani (DGM, IR & Finance)

  • Over 35 years of experience as leading offshore drilling services contractor in India's oil and gas sector
  • Five offshore jack-up rigs currently deployed with ONGC; also provide mud logging and directional drilling services
  • Over 30 years of service to ONGC, with long-standing operational and management team
  • Order book presentation now bifurcated rig-wise and year-wise on shareholder request; usually fresh tender on contract conclusion

Jindal Explorer Renewal and ONGC Tender Outlook · Raghav Jindal (MD)

  • Jindal Explorer contract ends May 2025; likely to extend to August/September 2025 for routine refurbishment and monsoon
  • Two ONGC tenders expected before end-FY25; Antique expects to participate and win
  • Latest ONGC benchmark day rate was ~$64,000; MD expects to 'maintain if not get a little better' given tightening international market
  • ONGC currently operates with fewer than 7 rigs and wants Pioneer back in India

In their words

There is a lot of demand worldwide, especially with the war and everything, the prices are going up again, and hopefully it is a great market to be in.
Raghav Jindal (Managing Director, Jindal Drilling & Industries Limited)
Jindal Supreme is a company-owned rig. So, margins will be higher than rented rig. If we were profitable when the rig was deployed at $40,700, then any additional rate will go down into EBITDA.
Kaushal Bengani (DGM IR & Finance, Jindal Drilling & Industries Limited)
ONGC has been pressurizing. That's why they did negotiate a lot. And that's why some of those contracts were cancelled. Like I said, the last was around USD 64,000. Our situation from that time to now has improved internationally. And hopefully, we should be able to maintain, if not get a little better than that.
Raghav Jindal (Managing Director, Jindal Drilling & Industries Limited)

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Wed 30 Oct 2024₹671.40+8.47%−0.51%
5 sessions Tue 5 Nov 2024₹732.95+18.42%−1.04%
20 sessions Thu 28 Nov 2024₹794.05+28.29%−2.26%

From the close of Tue 29 Oct 2024, ₹618.95: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Jindal Drilling Ind.'s other calls

  • Q2 FY27Mon 16 Nov 2026Tone: Confident
  • Q1 FY27Mon 10 Aug 2026Tone: Mixed
  • Q3 FY26Fri 30 Jan 2026Tone: Mixed
  • Q2 FY26Thu 6 Nov 2025Tone: Mixed
  • Q1 FY26Fri 1 Aug 2025Tone: Confident
  • Q4 FY25Wed 28 May 2025Tone: Confident
  • Q3 FY25Wed 29 Jan 2025Tone: Confident
  • Q1 FY25Wed 31 Jul 2024Tone: Mixed
  • Q4 FY24Thu 23 May 2024Tone: Confident