Jindal Drilling Ind. Q3 FY25 earnings call
In brief
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- None given
- Analyst pushback
- Medium
- Stock, next session
- +7.53% (Nifty 50 +0.90%)
- Q3 FY25 revenue up 39% QoQ to INR254 cr; PAT jumps to INR49 cr from INR16 cr on Jindal Supreme deployment at $88,000/day
- Jindal Pioneer acquisition ($75 mn, no debt) targeted for completion within Q4 FY25; rig built March 2015
- Management flags Dec-24 EBITDA run rate as base for next 4-5 quarters; margins to improve further post-Pioneer consolidation
- Net cash position doubles to INR101 cr (gross debt INR156 cr, cash INR257 cr); INR17 cr JV profit booked in Q3
- Order book of INR1,636 cr provides visibility; ONGC-BP press release and US policy shift cited as sector tailwinds
An AI read of the company's transcript · the filing
The numbers
The quarter, Q3 FY25
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹239 cr | +30.8% | +38.8% | |
| EBITDA (excl. other income) | ₹80.7 cr | +46.6% | +158.2% | 33.7% (30.1% a year ago) |
| Net profit | ₹0 cr | — | — | 0% (0% a year ago) |
| EPS (₹) | ₹22.76 | +106.5% | +91.3% |
From the company's filed results for the quarter ended 31 Dec 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
The numbers management led with
- Q3 FY25 revenue (QoQ growth): INR254 crores, up 39% QoQ
- Q3 FY25 EBITDA: INR81 crores (vs INR31 cr in Q2 FY25)
- Total order book: INR1,636 crores
- Net cash position: INR101 crores (vs INR51 crores 9 months ago); gross debt INR156 cr, cash INR257 cr
- Jindal Pioneer purchase price: $75 million (no debt; rig manufactured March 2015)
Guidance
Guidance on this call
| What | For | What management said | On the Q2 FY25 call |
|---|---|---|---|
| EBITDA run rate | next 4-5 quarters | Stand-alone EBITDA run rate achieved in Dec 2024 should be taken as base for next 4-5 quarters; all additional developments will only add further to earnings | — |
| Jindal Pioneer acquisition | Q4 FY25 | Targeted to conclude within Q4 FY25 (March 2025 quarter); Board has discussed and team is working to ensure closure | Application filed April 2024; statutory approval expected shortly, which would move Pioneer from 49% JV economics to 100% in JDIL |
| Operating margin | Q4 FY25 onwards | Margins to normalise at 34% level and improve further once Pioneer is consolidated into JDIL | — |
| Jindal Supreme operational days | Q4 FY25 | Supreme will work 90 days in Q4 FY25 (vs 75 days in Q3 FY25) — implicit revenue uplift | — |
| Jindal Explorer contract | by March 2025 | Decision on de-hire (May or September 2025) or extension expected by mid-to-end of March 2025 | Current contract ends May 2025; ONGC tender expected Nov/Dec 2024, likely extended to Aug/Sep 2025 for refurbishment |
Said on the Q2 FY25 call, not repeated on this one (3)
- Rig day rate (Jindal Supreme): Deployed 15 Oct 2024 at $88,859/day on a 3-year fixed contract with ONGC
- Total debt: ₹173 cr to reduce to ₹132 cr by 31 March 2025, with ₹66 cr repayment each in FY26 and FY27
- Net cash position: Currently ₹69 cr; expected to improve rapidly on internal accruals and JV cash generation
The business
The industry, as management sees it
Management is bullish on a multi-year oil & gas upcycle that started after the Russia-Ukraine war in Feb 2022 and is expected to extend longer than prior cycles due to the new US administration's drilling agenda. ONGC's 9 Jan 2025 press release hiring BP Exploration as a technical advisor signals fresh Indian E&P capex, with a lag to ground-level expenditure. New-build rig supply remains muted due to >10-year payback economics at current day rates, protecting incumbent contractors like JDIL.
Risks management named
- Single-customer dependency: ONGC contract award is the only material risk that cannot be mitigated
- Pioneer acquisition pending regulatory opinion and consent from current Mexico-based customer
- Refurbishment cost (4-6 months) and timing risk if Explorer contract is not renewed
- Long payback (>10 years) for new-build rigs discourages fresh supply, capping rate ceiling upside
Q&A
Q&A was dominated by three themes: (1) the pace and certainty of the Jindal Pioneer acquisition closing in Q4 FY25 after a multi-year wait — management deflected on the regulatory mechanics but reaffirmed the targeted timeline; (2) the day-rate outlook for the upcoming Explorer contract renewal, where management refused to specify numbers but pointed to tender outcomes by mid-March 2025; and (3) sector-level tailwinds (ONGC-BP press release, Trump policy) versus the capex barrier to new-build rigs. Pushback was strongest from individual investors probing the Pioneer delay and refurbishment cost disclosure; analysts probing JV profit split, refurbishment quantum and Pioneer-specific day rates were deflected.
Not answered directly
- Jindal Pioneer-specific JV profit breakdown
- Day rate for Jindal Explorer renewal contract
- Refurbishment cost quantum for upcoming rig
- Specific Pioneer EBITDA/PAT contribution at current rates
Every question, with its answer
1. Q3 operational metrics and forward outlook
Nirvana Laha, Badrinath Holdings
Question. How many days did Jindal Supreme operate in Q3 (was it 75 days)? Will the full impact be seen in Q4? Is Pioneer acquisition expected to complete this quarter? At current run rate, will Pioneer add INR8-10 cr to quarterly PAT (since only 49% is consolidated)? Will the current PAT run rate of INR65 cr+ hold for the next 6 quarters with Supreme and Virtue tied up? When will Explorer extension/monsoon continuation be communicated? Does the recent ONGC-BP Exploration press release on Bombay High production enhancement imply a tailwind for JDIL?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Confirmed 75 days of Supreme operation from 15 Oct 2024; full impact will be visible in March 2025 quarter. Pioneer acquisition is in final stage and the company wants to conclude it within this quarter (Board has discussed); 100% confirmation only after transaction closes. On JV profits, the 49% consolidation captures two JVs — one owns Pioneer and the other owns Virtue-I — but JDIL did not break out the Pioneer-specific contribution. Stand-alone EBITDA run rate achieved in Dec '24 should be taken as base for next 4-5 quarters; revenue run rate may not hold because Explorer could be de-hired in May or September. Explorer renewal communication expected by mid-to-end of March 2025 (3-year contract anniversary in May 2022). On the ONGC-BP press release of 9 Jan 2025: clear indication ONGC wants to increase exploration activities and more capex is expected — a strong tailwind for all oil & gas players, though fructification requires actual expenditure.
Partly answered.
2. JV profit breakdown, depreciation outlook, Explorer renewal
Diwakar Rana, Prudent Equity Private Limited
Question. Of the INR17 cr JV profit reported this quarter, how much came from Jindal Pioneer? Should we expect the INR26 cr depreciation to continue? Are there talks for a new contract for Jindal Explorer? What day rate can be expected for Explorer renewal?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Bengani declined to break out Pioneer-specific JV profit: 'We are not giving that out specifically.' Two JVs are consolidated at 49% — one owns Pioneer, the other owns Virtue-I — and rates are publicly known. On depreciation: if Pioneer is not purchased, INR26 cr stays flat; if acquired, depreciation will rise from the date the asset comes into JDIL. On Explorer: 'We are' in talks for a new contract, but did not comment on day rate; referred analyst to the presentation where day rates and duration are disclosed.
Follow-up. Will the new Explorer day rate be around $55,000-58,000?
Answer. Bengani: 'That, I don't know.'
Not answered directly.
3. Rented rig economics
Dixit Doshi, Whitestone Financial Advisors Private Limited
Question. How is the upside shared on the three rented rigs going forward — is it fixed or variable over the next 3-5 years?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. It is variable; when rig rates increase, renegotiation with the rig owner takes place.
4. Day rate benchmarks, margins, debt
Manikanth, Unknown (Investor)
Question. Virtue-I and Discovery-I contracts end May 2026 and Explorer in May 2025. Should the $88,000 Supreme rate be the base for new deployments? Can margins normalise at the current 34% level? Where do borrowings stand vs INR200 cr in Sep 2024?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. On day rates: cannot say Supreme's $88,000 is the base — rates are a function of international market and Indian competition; last contracted rate is not always an indicator. On margins: yes, margins will normalise at 34% and improve further post-Pioneer acquisition. On borrowings: per Slide 11, gross debt on 31 Dec 2024 is INR156 cr, cash INR257 cr, giving net cash INR101 cr — JDIL has been net cash for quite some time.
Partly answered.
5. Trump impact, rig rates, Q4 order book
Piyush Kumar, Dhunseri Investments
Question. With Trump in power and his drilling agenda, how do we see rig rates going ahead for Pioneer and Explorer? On Page 6 of the presentation, Q4 FY25 order book is shown at INR220 cr — does FY24 revenue line up with that?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Difficult to comment on Trump factor alone; more rigs in operation globally would increase demand and rental rates, with the effect spilling into India. Specifying a number is not possible. Bengani re-emphasised the 9 Jan 2025 ONGC press release as a positive indicator. On the order book: the INR220 cr Q4 figure is a bifurcation given as a guide — conservative by 5% — and Q4 revenue will be higher than Q3's INR239 cr because Supreme will work 90 days vs 75 in Q3. Disclaimer on the slide makes the order book only indicative.
Partly answered.
6. Capital return, contract tenure
Amit Agicha, HG Hawa & Company
Question. Is the company considering any share buyback to enhance shareholder value? Can you provide insights into contract tenure and renegotiation frequency and pricing trends for upcoming renewals? Do you expect current contracts to continue till 2027-28?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. No share buyback or other corporate action being considered right now. On tenure/renewal: Bengani referred to Slides 5 and 6 for day-rate and contract-duration bifurcation. Confirmed existing contracts are firm and will continue for the contracted duration.
Partly answered.
7. Explorer tender, consolidation roadmap, deepwater
Udit Sehgal, Tradewalk Research
Question. What is the status of the new ONGC tender for Explorer — has there been a delay? Is ONGC negotiating for lower rates? Is the indicative range of $65,000-85,000/day still relevant? Are there plans to bring the rented rigs into JDIL's books? What is the medium-term strategy — should we expect acquisitions of rented rigs or a brand-new rig (rigs going from 6 to 7-8)? Is deepwater a medium-term consideration given high global rates?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Tender has been submitted; awaiting outcome — cannot comment on day-rate range till tender is decided. On consolidation: there is general consensus to consolidate rented rigs gradually into JDIL where economics make sense; Pioneer is the immediate focus. History of two prior acquisitions (2019, 2021) validates the consolidation playbook. Most likely next step is acquiring rented rigs that JDIL already operates; if a suitable rig becomes available within budget, that will also be considered. Material earnings upside also expected when Explorer, Star and Discovery-I are renegotiated at higher rates. On deepwater: not actively pursued — capex is significantly higher (~$300 mn, 3-year build, 10-15 year payback at current day rates), which is itself a barrier that protects JDIL's market leadership.
Partly answered.
8. Refurbishment, Explorer geography, sector tailwind
Saket Kapoor, Kapoor & Company
Question. Is the broader thesis to consolidate all rigs under JDIL to unlock NAV and annuity run rate? What should be an ideal refurbishment spend percentage, and does refurbishment enhance efficiency or merely maintain the rig? Is Explorer refurbishment cost disclosed? Where is Explorer geographically deployed — is it in Bombay High?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Clarified the rationale is value creation within JDIL: JDIL already operates the rented rigs and has the financial resources to acquire them. Refurbishment is driven by (a) unique ONGC contract requirements and (b) recertification/safety; takes 4-6 months; analogies to car servicing. Refurbishment cost quantum not disclosed — depends on tender criteria and well locations; 'We are not disclosing that.' All five rigs are deployed in Bombay High. On the 9 Jan 2025 press release: it will take some time for capex to actually increase, but when it does, 100% all oil & gas sector-related industries (including pipes) will benefit.
Not answered directly.
9. Global day rates, supply, hedging
Rahul Agarwal, Bandhan Mutual Fund
Question. Globally (Borr Drilling, Valaris) some contracts have been signed at $180,000/day — is that the new normal vs $120,000-130,000 earlier? How many rigs are operational in India? Any movement on the supply side — new rig builds? Are we finding distressed rig acquisition opportunities globally? What is JDIL's hedging policy and what % is naturally hedged?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. On global rates: need to check rig technical specs (e.g., 350-ft jack-up), Indian vs international cost structures, and whether the benefit of firm long-term ONGC contracts is replicated abroad. Generally bullish on oil & gas — reason for significant Supreme refurbishment. India: more than 30 rigs operational (latest data not at hand; suggested Petrodata). Supply: new builds have not started — at $250-300 mn capex over 3 years and $100,000/day theoretical rate, payback exceeds 10 years and could be 15 years at 7-7% interest, deterring fresh supply. Acquisitions: 'We are not getting opportunities' — they dry up in upcycles. Hedging: full natural hedge on rented rigs since receivable USD > payable USD; for owned rigs, open exposure partly booked via forwards; FX gain of ~INR9 cr booked in Dec quarter; if rupee remains at current levels, similar gains expected in March quarter. JDIL has no diversification plans beyond the rig segment.
Partly answered.
10. Risk framework
Siddhartha Mathew, Unknown (Investor)
Question. Beyond sustained oil prices and ONGC cancelling/renegotiating, what other risks should investors think about?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. The only industry risk that cannot be addressed is securing a contract from ONGC. Once a contract is in place, it is firm — not renegotiated or cancelled. All other risks (refurbishment, day rates, etc.) are addressable.
11. Diversification into technical services
Abhi, Unknown (Investor)
Question. Given ONGC's 9 Jan press release on hiring international technical service providers, shouldn't JDIL consider building in-house technical exploration services for higher growth non-linearity alongside rig rentals?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Acknowledged the logic but stated advisory/technical services is not JDIL's positioning — JDIL is an operator paid to run rigs, with 35 years of track record. Mud logging and directional drilling are existing small divisions that are not scalable. Current business delivers 30-35% EBITDA margins that will improve post-Pioneer; preferred to play to strengths in market-leading segments rather than diversify. Requested patience for one more quarter to close Pioneer first.
12. Pioneer delay reason, Explorer tender, cash deployment
Manikant, Unknown (Individual Investor)
Question. What is the main reason Pioneer acquisition has been pending for over a year — is there a real problem? With Explorer de-hiring in 4 months and the tender already submitted, can we expect the new contract to be completed in this window, or will there be idle time? Is JDIL looking to acquire other rented rigs given the strong net cash position, and how much cash will go for Pioneer — $75 mn?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. No real problem — only regulatory navigation. Shareholder approval obtained March 2024. Time gap between execution and physical delivery of the rig into India exceeded regulatory limits, so approval was applied for in April 2024. With ~a year elapsed, the application has become infructuous (per JDIL's reading — taking legal opinion). Once opinion is clear, will need consent of the current Mexico-based customer for change of ownership. On Explorer: confirmation of new contract will come before conclusion of existing contract; if lost, 6-month refurbishment gap before next tender — 'no risk right now'. Cash is being conserved to fund Pioneer. Confirmed $75 mn is the purchase price.
13. Cycle position, duration, capex outlook
Dikshant, DB Wealth
Question. Where are we in the oil & gas cycle — starting, mid, or well into the up cycle? How long will this cycle last — 5-7 years or potentially a decade? With strong cash and max-efficiency operations, can JDIL now look at aggressive capex or another expansion? Are we at the peak of the cycle given crude is not at all-time highs?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. Up cycle started after Russia-Ukraine war in Feb 2022. Expects a longer cycle than prior ones due to US policy change favouring drilling. Humorous deflection on length prediction. The only acquisition on cards is Pioneer this quarter; reassessment after that. On cycle peak: 'No, because crude is not at an all-time high for an extended period.'
Partly answered.
14. Pioneer EV, deployment, vintage
Saket Kapoor, Kapoor & Company
Question. Is the $75 mn for Pioneer the total cash outgo or enterprise value including debt? Will the rig be deployed in Mexico or brought into India? What is the year of manufacture of Pioneer?
Answer, Kaushal Bengani, Deputy General Manager, Investor Relations and Finance. $75 mn is the enterprise value; there is no debt on the rig. JDIL wants to bring the rig into India where rates are good and the asset remains within control — unless a really high rate like $180,000/day materialises internationally, India is the preferred deployment. Jindal Pioneer was manufactured in March 2015.
What was said
Topic by topic, in the order it was spoken
Q3 FY25 Operational Milestone — Jindal Supreme Deployment · Kaushal Bengani (DGM IR & Finance)
- Jindal Supreme rig deployed with ONGC on 15 October 2024 — the key Q3 development
- Office and rig teams worked relentlessly to ensure successful deployment
- Earnings improvement was expected and had been communicated in the prior 3 earnings calls since contract award
Q3 FY25 Financial Performance Snapshot · Kaushal Bengani (DGM IR & Finance)
- Revenue improved 39% QoQ to INR254 crores (vs Q2 FY25)
- EBITDA increased from INR31 cr to INR81 cr
- PAT jumped from INR16 cr to INR49 cr
- EPS rose from INR5 to INR17 per share
- Earnings jump primarily attributed to Jindal Supreme deployment in Q3
Company Overview & Service Portfolio · Kaushal Bengani (DGM IR & Finance)
- Leading offshore drilling services contractor in India's oil & gas sector with 35+ years experience
- Supported by efficient operational and management team with highest safety standards
- Serving ONGC for over 30 years; currently 5 offshore jack-up rigs deployed with ONGC
- Also provides mud logging and directional drilling services to the oil & gas sector
Order Book Visibility · Kaushal Bengani (DGM IR & Finance)
- Total order book of INR1,636 crores with rig-wise day rate and contract duration breakup
- Year-wise, rig-wise order book realisation path provided to stakeholders
- EBITDA mix remains consistent — more than 90% of EBITDA from offshore drilling rig segment
Balance Sheet Strength — Net Cash Position · Kaushal Bengani (DGM IR & Finance)
- Net cash position doubled in the last 9 months from INR51 crores to INR101 crores
- Cash position expected to improve further as all rigs are deployed at higher rates on new ONGC contracts
- Earnings will additionally improve post-Jindal Pioneer acquisition (final stage)
In their words
The stand-alone EBITDA run rate, which we have achieved in December '24 quarter should be taken as a base for the next 4, 5 quarters, because all additional developments that will happen will only add further to the earnings of Jindal Drilling.
That will happen for the first time in March 2025 quarter. First time after a very long duration, maybe 7, 8, 9 years.
It is a barrier to the industry, and that's why we enjoy the market leadership position.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Wed 29 Jan 2025 | ₹829.70 | +7.53% | +0.90% |
| 5 sessions Mon 3 Feb 2025 | ₹944.50 | +22.41% | +1.76% |
| 20 sessions Mon 24 Feb 2025 | ₹764.60 | −0.91% | −1.76% |
From the close of Tue 28 Jan 2025, ₹771.60: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
Jindal Drilling Ind.'s other calls
- Q2 FY27Mon 16 Nov 2026Tone: Confident
- Q1 FY27Mon 10 Aug 2026Tone: Mixed
- Q3 FY26Fri 30 Jan 2026Tone: Mixed
- Q2 FY26Thu 6 Nov 2025Tone: Mixed
- Q1 FY26Fri 1 Aug 2025Tone: Confident
- Q4 FY25Wed 28 May 2025Tone: Confident
- Q2 FY25Wed 30 Oct 2024Tone: Confident
- Q1 FY25Wed 31 Jul 2024Tone: Mixed
- Q4 FY24Thu 23 May 2024Tone: Confident