KNR Constru Q4 FY25 earnings call

Fri 30 May 2025KNRCON

In brief

KNR Q4 standalone EBITDA ₹118 cr at 13.8% margin; targets ₹8,000-10,000 cr order inflow by FY26 end

Management's tone
Cautious
What was said
Mixed
Guidance
None given
Analyst pushback
Medium
Stock, next session
−4.53% (Nifty 50 −0.33%)
  • Q4 standalone revenue was ₹851 cr; EBITDA ₹118 cr at 13.8% margin versus ₹214 cr a year ago.
  • Consolidated FY25 revenue rose 7% YoY to ₹4,753 cr; EBITDA jumped 55% to ₹1,625 cr at 34.2% margin.
  • Order book stood at ₹5,052 cr (HAM 40%, irrigation 28%, pipeline 21%, other roads 11%); firm targets ₹8,000-10,000 cr inflow.
  • HAM equity of ₹651 cr already invested out of revised ₹990 cr; ₹339 cr remaining split ₹210 cr FY26 and ₹130 cr FY27.
  • Q4 consolidated PAT collapsed to ₹8 cr on a consolidation adjustment from sale of stepdown subsidiary KNR Muzaffarpur Holdings.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q4 FY25

This quarterA year agoLast quarterMargin
Revenue₹975 cr−31.0%+15.0%
EBITDA (excl. other income)₹95.9 cr−74.4%−62.5%9.8% (26.5% a year ago)
Net profit₹139 cr−60.6%−43.9%14.3% (25% a year ago)
EPS (₹)₹4.95−60.6%−44.0%

From the company's filed results for the quarter ended 31 Mar 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Q4 FY25 consolidated EBITDA: said ₹221 cr, margin 22.7%; filed ₹95.88 cr (excl other income), margin 9.8%. Filed definition excludes other income ₹25.30 cr; adding other income gives ~₹121 cr, still a wide gap from ₹221 cr.
  • Q4 FY25 consolidated PAT: said ₹8 cr; filed ₹139.24 cr (margin 14.3%). Management attributed low PAT to consolidation adjustment on sale of stepdown subsidiary KNR Muzaffarpur Holdings.
  • Q4 FY25 consolidated EBITDA margin: said 22.7%; filed 9.8% (EBITDA excl other income). Filed margin uses EBITDA excluding other income; management's 22.7% includes other items/gains from subsidiary transfer.

What moved the numbers, as management explained it

  • Q4 standalone revenue declined as most existing road/HAM projects at 90-95% complete (frag-end), limiting revenue recognition.
  • Q4 standalone EBITDA margin fell to 13.8% versus 15-16% earlier as fixed overheads spread over lower turnover.
  • Q4 consolidated PAT collapsed to ₹8 cr due to one-off consolidation adjustment on sale of stepdown subsidiary KNR Muzaffarpur Holdings. (one-off)
  • Consolidated FY25 EBITDA margin at 34.2% likely benefits from gain on subsidiary step-down sale; readers should not extrapolate. (one-off)
  • Consolidated debt rose to ₹1,847 cr (vs ₹1,258 cr) and net D/E to 0.41x (vs 0.34x) on HAM equity infusion and working capital build-up.

Guidance

Guidance on this call

WhatForWhat management said
Order inflow targetFY26order inflow of approximately at least INR8,000 crores to INR10,000 crores by the end of '26
Standalone revenue from existing order bookFY26we can execute this year between INR2,500 to INR3,000 with existing order book only
HAM equity infusion (HAM projects)FY26INR210 crores in FY26 and around INR130 crores in FY27
HAM equity infusion (HAM projects)FY27around INR130 crores in FY27
Standalone EBITDA margin guidanceFY26around 13%-14% it is possible
Capex for new projects (New projects (MSRDC, mining))FY27FY '27 can see maybe a INR100 crores, INR200 crores kind of a capex

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY25 EBITDA marginFY2515–16% (on the Q4 FY24 call)31.2%, above the range
Standalone turnoverFY25₹3,500–3,600 cr (on the Q2 FY25 call)₹4,753 cr, above the range
Standalone EBITDA margin guidanceFY2513–14% (on the Q2 FY25 call)31.2%, above the range
Revenue targetFY26₹4,500 cr (on the Q2 FY25 call)₹2,698 cr, below the figure guided

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Roads / HAM

Order book share 40% HAM and 11% other roads; Q4 revenue mix 46% HAM and 30% road EPC; multiple HAM projects at 89-95% physical progress.

Order book HAM share 40% · Order book other roads 11% · Q4 revenue share HAM 46% · Q4 revenue share road EPC 30%

Outlook: Targets ₹8,000-10,000 cr order inflow by end of FY26; pursuing NHAI bids ₹30,000-40,000 cr and state ₹10,000-15,000 cr pipeline.

Irrigation

Q4 revenue mix 19%; receivables ~₹790 cr and unbilled ~₹500 cr outstanding; Telangana government collections dragging.

Q4 revenue share 19% · Receivables ₹790 cr · Unbilled ~₹500 cr · Q4 execution ₹152 cr

Outlook: Telangana department said settlement in 1-1.5 months; incremental ₹900 cr revenue possible; pursuing AP, Bihar, MP, Rajasthan bids.

Pipeline

Order book share 21%; Q4 back-to-back 4% revenue mix; Amrit scheme with 25% central and 75% state funding.

Order book share 21% · Q4 back-to-back share 4% · Q4 revenue ₹30 cr

Outlook: Targets ₹300-400 cr FY26 execution (~35-40%); no funding constraints seen from state so far.

Mining (new)

New diversification thrust; bids placed in NTPC, Singareni, Western Coalfield; JVs with Sushee and Harsha pursued.

Bid pipeline INR2,000-5,000 cr over 2-5 years

Outlook: Pursuing EPC and MDO opportunities; bid results awaited, expects orders in 2-3 months.

Balance sheet, capex and funding

  • Standalone working capital days at 93 versus 89 as of March 2024.
  • Consolidated debt ₹1,847 cr as of March 31, 2025 versus ₹1,258 cr as of March 31, 2024.
  • Consolidated net debt to equity 0.41x versus 0.34x as of March 2024.
  • HAM equity infused so far ₹651 cr of revised ₹990 cr; ₹339 cr remaining split ₹210 cr FY26 and ₹130 cr FY27.
  • Capex FY25 ₹22 cr; FY26 similar; FY27 could see ₹100-200 cr for new MSRDC/mining projects.
  • Mobilization advance ~₹20 cr; retention money ₹846 cr as of March 2025.

The industry, as management sees it

Management is constructive on the road sector medium term, citing MoRTH's 25,000-30,000 km two-to-four lane upgrade with INR8-10 lakh cr outlay, FY26 target of 10,000 km construction and the 5,800 km high-speed corridor rollout. However, they flagged that near-term NHAI bid flow is constrained by the policy of not bidding projects until clearances are in place, and that election-related decision-making delays have temporarily slowed the pipeline.

Risks management named

  • NHAI show cause notice on Kerala BOT (KNR Ramatheertham) - management says it is not at fault but potential 1-year debarment is being contested
  • Telangana irrigation receivables of INR1,200 crores remain stuck; arbitration being prepared as fallback
  • Arunachal Pradesh arbitration award of INR319 crores now in court; resolution likely 4-5 years away
  • Working capital days expanded to 93 from 89 and net debt/equity rose to 0.41x from 0.34x
  • Kerala project subsoil damage estimated at INR25-30 crores for viaduct remediation; insurance recovery uncertain
  • Aggressive bidding environment in road sector forcing KNR to look at JVs and adjacent sectors

Q&A

Analysts drove the discussion around three core themes: (i) FY26 revenue execution capability and the absence of a quantitative guidance, with management repeatedly deferring until the MSRDC LOA; (ii) margin trajectory, with management acknowledging a downgrade to 13-14% standalone EBITDA on the 'frag end' of legacy HAM projects; and (iii) the NHAI show cause notice on the Kerala BOT, where multiple analysts (Vasudev, Parikshit, Vaibhav Shah) probed the ban duration, parent-vs-subsidiary impact and the INR25-30 cr viaduct remediation cost. Pushback was moderate and concentrated on the show cause notice and irrigation receivables, with management largely redirecting to 'wait for LOA' style answers rather than committing to numbers.

Not answered directly

  • FY26 consolidated revenue guidance (deferred to post-MSRDC LOA)
  • Consideration value of HAM asset monetisation (deferred as negotiation ongoing)
  • Whether parent company NHAI bidding is impacted by Kerala show cause (deferred as interpretation pending)
  • MSRDC revenue contribution to FY26 (deferred until LOA)

Asked for a number, answered without one

  • FY26 consolidated revenue guidance: Said existing book supports ₹2,500-3,000 cr standalone plus ₹400-500 cr consolidated; declined total guidance pending MSRDC and other LOAs.
  • HAM asset monetization consideration: Said final negotiations in advanced stage, expects to sign by mid-July; declined to disclose consideration or multiple.
  • FY26-27 arbitration claim quantum: Said Arunachal Pradesh award of ~₹319 cr challenged in court; declined to project any near-term recovery, citing 4-5 year timeline.
  • Capex quantum for new mining/MSRDC projects in FY26: Said capex requirement for new projects will not be in FY26, may be in FY27 at ₹100-200 cr level; deferred specifics.

Every question, with its answer

  1. 1. Order book and revenue execution

    Shravan Shah, Dolat Capital

    Question. What is the unbilled revenue as of March 2025, and given the INR5,052 cr order book, how much of the residual ~INR4,000 cr can be executed in FY26?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Unbilled revenue is INR968 cr. Out of INR5,000 cr order book, after removing ~INR1,000 cr, INR4,000 cr is executable. Management expects INR2,500-3,000 cr execution in FY26 from this existing book; further upside depends on receipt of new orders (MSRDC, mining, NHAI) by Q3/Q4.

    Follow-up. Break-up of FY26 bid pipeline by NHAI, state and MSRDC? Value of MSRDC? EBITDA margin guidance? Status of Telangana irrigation receivables of INR1,200-1,300 cr?

    Answer. MSRDC: cabinet approval due in a month, LOA 1-2 months thereafter, with value around INR2,400 cr gross / INR2,200 cr net. Mining bids pursued at NTPC, Singareni, WCL; state government tenders in 2-3 months. Total NHAI bid pipeline INR30,000-40,000 cr, state highways INR10,000-15,000 cr, mining INR2,000-5,000 cr. EBITDA margin guide now 13-14% (slightly lower than 15-16% prior). Irrigation receivables: met Minister last week, expecting settlement in ~1.5 months; arbitration filing ready as backup.

  2. 2. Irrigation backlog and FY26 guidance

    Vaibhav Shah, JM Financial

    Question. Unbilled portion of irrigation backlog? Revenue guidance for FY26 from backlog plus possible MSRDC? Pipeline execution pace in FY26? Backlog at Valanchery-Kappirikkad, Ramanattukara-Valanchery and Chittoor-Thatchur? Status of new irrigation projects? Opportunity at Amravati development? Are both parent and subsidiary banned from NHAI bidding for a month?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Irrigation unbilled ~INR500 cr (similar to last quarter); incremental irrigation revenue ~INR900 cr from INR1,400 cr book. Revenue guidance deferred until MSRDC LOA; only standalone existing book execution of INR2,500-3,000 cr confirmed. Water pipeline execution targeted at INR300-400 cr in FY26. Project backlogs: Valanchery-Kappirikkad INR108 cr, Ramanattukara-Valanchery INR98 cr, Chittoor-Thatchur INR122 cr. Two new irrigation projects received appointed date last month. On Amravati, KNR placed some bids but is preparing for upcoming large bunch. On show cause notice: only the concessionaire (KNR Ramatheertham SPV) appears barred; management's interpretation is the parent company is not impacted and they are clarifying with the department.

    Partly answered.

  3. 3. Order book additions

    Niteen Dharmawat, Aurum Capital

    Question. Order book grew from INR3,800 cr to INR5,000 cr - which projects got added and is any appointed date still pending?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Two projects received appointed date: Mysore-Kushalnagara Package IV and V (~INR1,200 cr) plus ~INR400 cr irrigation project and some COS additions - totalling ~INR2,000 cr added in the year. No appointed dates pending on existing projects.

  4. 4. Standalone vs consolidated guidance and dividend policy

    Saket Kapoor, Kapoor and Company

    Question. Is the INR2,500-3,000 cr execution target on standalone or consolidated basis? Has KNR bid for the Ken Betwa interlinking project? Jal Jeevan exposure and dividend payout rationale at INR0.25/share for 4 years?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. INR2,500-3,000 cr is on a standalone basis; consolidated could be INR400-500 cr higher. On Ken Betwa: not yet participated but interested in central government-backed interlinking projects in south. Pipeline project is funded 25% by central government and 75% by state under Amrit scheme; no delays and no funding constraints observed. Dividend policy: company wants to retain cash for mining projects, BOT toll assets and diversification; will revisit based on performance and cash flow.

    Partly answered.

  5. 5. Margin guidance and bid pipeline

    Jainam Jain, ICICI Securities

    Question. Why was Q4 margin lower and what margin range to expect going forward? What is the bid pipeline for FY26 and order inflow target?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Q4 EBITDA reduction explained by projects being in 'frag end' (90-95% complete), so revenue generation lower but overheads continue. Maintain 13-14% standalone EBITDA guidance. New projects (MSRDC, mining, irrigation) should improve margin mix; irrigation has better margin. FY26 order inflow target INR8,000-10,000 cr. NHAI pipeline INR30,000-40,000 cr and state pipeline INR10,000-15,000 cr.

  6. 6. Revenue mix, asset monetisation and diversification

    Bhavin Modi, Anand Rathi Financial Services

    Question. Q4 revenue mix between HAM, irrigation, EPC? Status of HAM asset monetisation - what consideration? Plans for partnership/JV for railways, airports, river interlinking or complex projects like tunneling?

    Answer, K. Jalandhar Reddy, Executive Director. Q4 mix: HAM ~46%, irrigation 19%, road EPC 30%, back-to-back 4%. On monetisation: in advanced stage with 1-2 sittings remaining; expects to sign SOP by mid-July. On diversification: JVs already formed with NCC for certain projects and with Sushee-Harsha and Patel Engineering for mining and tunneling. Open to metros, flyovers, irrigation, pump houses, powerhouses and mining tenders - expects meaningful orders in 2-3 months.

  7. 7. Balance sheet reclassification and mining bid structure

    Mudit Bhandari, IIFL Capital

    Question. Why have other current assets and other financial assets expanded on standalone balance sheet - any reclassification? On NTPC, Singareni, WCL mining projects - is it pure EPC or MDO?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Other financial assets expansion is mainly unbilled revenue rising from INR497 cr to INR968 cr; trade receivables actually fell from INR1,364 cr to INR1,244 cr. Mining projects: combination of EPC and MDO (mining development and operations) - pursuing both where margins are attractive.

  8. 8. Kerala ban duration and capex

    Vasudev, Nuvama Wealth

    Question. On the Kerala project show cause notice - how long can the ban extend, is it 1 year as per media or 1 month per intimation, and could it extend to the parent? FY25 capex, irrigation execution value and Telangana receivables?

    Answer, K. Jalandhar Reddy, Executive Director. Show cause notice gives 15 days to respond and proposes 1-year debarment plus 0.5% penalty. Management is confident there is no mistake - subsoil water logging caused the settlement, road was not open to traffic, all designs and approvals were in order. Will also pursue legal option. FY25 capex INR22 cr; Q4 irrigation execution INR152 cr (19% of revenue); pipeline project INR30 cr quarterly; Telangana receivables including unbilled INR1,200 cr.

  9. 9. Adjusted FY25 financials

    Dheeraj, Avendus Spark

    Question. Adjusted revenue, EBITDA margin and PAT for FY25 excluding arbitration claim and other one-offs?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Adjusted FY25 revenue INR3,234 cr; adjusted PAT INR339 cr; adjusted EBITDA margin 15.94%. No one-offs in the current quarter.

  10. 10. Receivables aging, HAM delays and budget impact

    Balasubramaniam, Arihant Capital

    Question. What percentage of receivables is over 180 days and how is counterparty risk from state government being mitigated? Reason for delay in HAM projects like Sriranganatha and Kaveri Infra? Impact of union budget on EPC tendering volumes in irrigation and highways?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Most receivables are from irrigation (INR500 cr) and HAM SPVs which can draw funds anytime. HAM delays attributable to authority ROW issues and late appointed dates; no execution delay. On budget: significant opportunities exist but NHAI is not bidding projects until clearances are in place, causing postponement; expects pickup this fiscal; two-to-four lane upgrade of ~30,000 km and INR8-10 lakh cr outlay supports strong pipeline.

    Partly answered.

  11. 11. Irrigation receivables and HAM monetisation

    Parth Thakkar, JM Financial

    Question. Current outstanding irrigation revenue? Plans to monetise HAM assets and at what multiple?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Outstanding irrigation receivables ~INR790 cr. Four HAM assets are in SPA negotiation; targeted to close by mid-June (later pushed to mid-July on follow-up); multiple not disclosed at this stage.

    Partly answered.

  12. 12. Mobilization, retention and arbitration

    Jainam Jain, ICICI Securities

    Question. Mobilization advance and retention money as of March 2025? Total executable order book out of INR4,000 cr; any slow moving orders? Arbitration claims expected in FY26-27?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. Mobilization advance ~INR20 cr; retention money INR846 cr. INR4,000 cr is the net executable order book; no slow moving orders. On arbitration: received award on an Arunachal Pradesh project of ~INR319 cr but counterparty went to court; will take 4-5 years to close.

  13. 13. Kerala impact, insurance and ban

    Parikshit, HDFC Securities

    Question. Kerala bridge damage - impact, insurance coverage and exact ban period (1 month or 1 year)? MSRDC revenue guidance for FY26?

    Answer, K. Jalandhar Reddy, Executive Director. Damage may not be covered by insurance; main cause is poor subsoil below foundation. Viaduct is the proposed solution at ~INR25-30 cr cost. Design was approved by all authorities and the failure is treated as an accident. On ban: management disputes 1-year debarment and is preparing a viaduct proposal to NHAI; could be treated as change of scope or pursued via arbitration. On MSRDC revenue: cannot quantify until LOA; will comment only on receipt of definitive LOA.

    Not answered directly.

  14. 14. Capex outlook and bonus

    Shravan Shah, Dolat Capital

    Question. Capex outlook for FY26 and FY27 if INR8,000-10,000 cr orders come in? How much early-completion bonus will be booked in FY26? In which quarter will the Chittoor-Thatchur bonus be booked?

    Answer, K. Venkatram Rao, General Manager, Finance and Accounts. FY26 capex similar to current INR20-30 cr; FY27 may see INR100-200 cr capex for new projects (MSRDC, mining, etc.). Chittoor-Thatchur bonus of INR3.26 cr will be booked in Q1 FY26 subject to NOC.

What was said

Topic by topic, in the order it was spoken

Road Sector Outlook and MoRTH Reforms · K. Venkatram Rao (GM, Finance and Accounts)

  • Road infrastructure sector saw slowdown in FY25 but Q4 showed promising recovery with improved awarding and execution.
  • MoRTH enforcing fixed timeline for land acquisition and statutory clearances (forest/wildlife) to expedite execution.
  • Revised policy imposes additional performance security on aggressive bids to encourage financially sound bidding.
  • MoRTH plans to upgrade 25,000-30,000 km of two-lane highways to four-lane corridors with INR8-10 lakh cr outlay.
  • FY26 target: 10,000 km of highway construction prioritising modernisation and northeast connectivity.
  • Planned rollout of 5,800 km high-speed corridor network to drive national connectivity.

HAM Project Status and Equity · K. Venkatram Rao (GM, Finance and Accounts)

  • Physical progress at March 31, 2025: Ramanattukara-Valanchery 95%, Valanchery-Kappirikkad 93%, Chittoor-Thatchur 91%, Magadi-Somwarpet 89%, Marripudi-Somvarappadu 37%.
  • INR651 cr of INR990 cr revised HAM equity requirement already invested.
  • Balance equity of INR339 cr to be infused: INR210 cr in FY26 and INR130 cr in FY27.
  • Subsidiary KNR Holding completed transfer of KNR Muzaffarpur Holdings for INR1 lakh; KNR transferred 0.65% in KNR Muzaffarpur Barauni Tollway for INR45.90 lakhs.

Project Updates, Bonus and Kerala Show Cause · K. Venkatram Rao (GM, Finance and Accounts)

  • April 2025: Appointed date received for Mysore-Kushalnagara Package IV and V.
  • May 2025: Provisional completion certificate received for Chittoor-Thatchur Package III, 40 days ahead of schedule, eligible for INR3.26 cr bonus.
  • May 21, 2025: NHAI show cause notice to KNR Construction and subsidiary KNR Ramatheertham for partial damage of under-construction BOT in Kerala.
  • Damage attributed to indeterminate subsoil conditions and high water table; one VUP approach ramp with RE wall yielded causing settlement of service road.
  • Financial impact still under evaluation.

Order Book and FY26 Inflow Aspiration · K. Venkatram Rao (GM, Finance and Accounts)

  • Order book at March 31, 2025: INR5,052 cr, split HAM 40%, irrigation 28%, pipeline 21%, other roads 11% (errata issued).
  • Current order book executable over 1.5-2 years.
  • FY26 order inflow aspiration of INR8,000-10,000 cr on back of government infrastructure push.

FY25 Stand-alone and Consolidated Financial Performance · K. Venkatram Rao (GM, Finance and Accounts)

  • Q4 standalone revenue INR851 cr; EBITDA INR118 cr (vs INR214 cr YoY) at 13.8% margin; net profit INR75 cr (vs INR198 cr).
  • FY25 standalone revenue INR3,359 cr; EBITDA INR626 cr (vs INR701 cr) at 18.6% margin; net profit INR726 cr, +47% YoY.
  • Q4 consolidated revenue INR975 cr; EBITDA INR221 cr at 22.7% margin; PAT INR8 cr due to consolidation adjustment on stepdown subsidiary sale.
  • FY25 consolidated revenue INR4,753 cr (+7% YoY); EBITDA INR1,625 cr (+55%); PAT INR1,002 cr (+33%).

Balance Sheet and Capital Structure · K. Venkatram Rao (GM, Finance and Accounts)

  • Working capital days stood at 93 vs 89 in March 2024.
  • Consolidated debt INR1,847 cr at March 31, 2025 vs INR1,258 cr at March 31, 2024.
  • Net debt to equity on consolidated basis at 0.41x vs 0.34x in March 2024.

In their words

Now that road sector is a bit heated up. So, we would like to go other sectors and recoup our order book and then once the road sector becomes okay, then we would probably even go in the roads also.
K. Jalandhar Reddy (Executive Director, KNR Constructions)
We are very confident that we have not done any mistake in there. It's a complete waterlogged area where the technically, because of the water loggedness somewhere in between the beneath the foundation, that particular area has been submerged.
K. Jalandhar Reddy (Executive Director, KNR Constructions)
That is why once we receive the LOA of that project, after that we can really give the correct guidelines to you. So far, we have not received the LOA. That's why we could not really predict it.
K. Venkatram Rao (General Manager, Finance and Accounts, KNR Constructions)

To check next time

What management committed to on this call, or the dates they gave.

  • MSRDC LOA receipt for ~₹2,200 cr project expected within 1-2 months.
  • Q1 FY26 booking of ₹3.26 cr bonus from Chittoor-Thatchur early completion (40 days ahead).
  • Resolution of irrigation receivables ₹1,200 cr Telangana, expected in 1-1.5 months per department.
  • Closure of HAM asset monetization with SPA signing targeted by mid-July 2025.
  • Progress on ₹8,000-10,000 cr FY26 order inflow target, including mining and NHAI bids.
  • Outcome of NHAI show cause notice on Kerala BOT project; financial impact assessment of ~₹25-30 cr.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Fri 30 May 2025₹210.80−4.53%−0.33%
5 sessions Thu 5 Jun 2025₹209.47−5.14%−0.33%
20 sessions Thu 26 Jun 2025₹226.35+2.51%+2.88%

From the close of Thu 29 May 2025, ₹220.81: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

KNR Constru's other calls