KNR Constru Q1 FY26 earnings call
In brief
KNR Q1 FY26 consolidated revenue ₹613 cr (-38% YoY); cuts standalone FY26 guide to ₹2,000-2,500 cr; targets ₹10,000-12,000 cr order inflow.
- Management's tone
- Mixed
- What was said
- Mixed
- Guidance
- Guidance cut
- Analyst pushback
- Medium
- Stock, next session
- −4.00% (Nifty 50 −0.40%)
- Standalone FY26 revenue guide cut to ₹2,000-2,500 cr from ₹2,500-3,000 cr as most legacy projects are 90%+ complete and new order wins slipped.
- Order inflow target for FY26 raised to ₹10,000-12,000 cr (excluding ₹3,500 cr mining project) on top of ₹8,305 cr opening order book.
- HAM SPV share purchase agreement expected within a month as four-asset monetization enters advanced stage; would cut consolidated debt of ₹2,018 cr.
- JV with Harsha Constructions received LOA from NTPC for Banhardih coal mine block at ₹4,800 cr ex-GST with KNR's 74% share, marking entry into mining.
- Standalone working capital days spiked to 169 from 93 in March on ₹1,300 cr Telangana irrigation receivables; ₹1,200 cr inflows expected by March 2026.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q1 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹613 cr | −37.8% | −37.2% | |
| EBITDA (excl. other income) | ₹183 cr | −34.3% | +90.8% | 29.9% (28.3% a year ago) |
| Net profit | ₹123 cr | −28.5% | −11.4% | 20.1% (17.5% a year ago) |
| EPS (₹) | ₹4.39 | −28.5% | −11.3% |
From the company's filed results for the quarter ended 30 Jun 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
What moved the numbers, as management explained it
- Q1 FY26 consolidated revenue fell to ₹613 cr from ₹985 cr YoY because most legacy projects 90%+ complete; new HAM/EPC orders just started with low Q1 run rate.
- Standalone EBITDA margin at 13.6% (₹66 cr) versus ₹192 cr in Q1 FY25 reflects revenue deleverage and legacy HAM projects at 'frag end'.
- Consolidated EBITDA margin of 29.9% (₹183 cr) reflects HAM SPV annuity income in consolidated entities; standalone is only 13.6%.
- Working capital days surged to 169 from 93 in March on ₹1,300 cr Telangana irrigation receivables; only ₹14 cr collected in Q1 — a base-distortion to not extrapolate. (one-off)
- Net profit ₹51 cr standalone, ₹123 cr consolidated; consolidated PAT margin 20.1% on SPV annuity contribution and lower revenue base.
The numbers management led with
- Order book: INR8,305 cr (43% mining, 27% roads, 17% irrigation, 13% pipeline)
- Coal mining contract value: INR4,800 cr (excl. GST), 74% share, 5-year operation + 360-day development, ~34.5 mt coal
- FY26 order inflow target: INR10,000-12,000 cr (excluding mining)
- Working capital days: 169 days (vs 93 days as of March 31, 2025)
- Telangana irrigation receivables: INR1,300 cr pending (INR800 cr certified, INR500 cr unbilled); INR1,000 cr targeted for recovery by March
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| Standalone revenue | FY26 | Standalone revenue FY26 guided to INR2,000-2,500 cr. |
| Order inflow excluding mining | FY26 | Aim at order inflow of approximately INR10,000-12,000 cr by end of FY26 excluding mining. |
| Standalone EBITDA margin | FY26 | EBITDA will be somewhere around 13% to 13.5% for FY26 standalone. |
| HAM SPV SPA signing (HAM Roads) | — | Share purchase agreement with prospective investor for four HAM SPVs expected within one month. |
| Pipeline project revenue (Water Pipeline) | FY26 | Pipeline project revenue target of INR500 cr for FY26 with billing on milestone completion. |
| Mining project revenue year 1 | FY26 | Banhardih coal mine year 1 (development phase) revenue of INR90-100 cr. |
| FY26 capex | FY26 | Maximum INR100 cr capex for entire company in FY26. |
What changed since the Fri 30 May 2025 call
| What | On the Fri 30 May 2025 call | On this call |
|---|---|---|
| FY26 standalone revenue guide (cut) | INR2,500-3,000 cr for FY26 | INR2,000-2,500 cr for FY26 |
| FY26 standalone EBITDA margin guide (restated) | 13-14% standalone for FY26 | 13-13.5% standalone for FY26 |
| FY26 order inflow target (raised) | INR8,000-10,000 cr | INR10,000-12,000 cr (excluding mining) |
| MSRDC project timing and FY26 revenue (delayed) | Cabinet approval and LOA awaited; could add INR300-400 cr to FY26 revenue | Final CM approval pending, 2 months more; INR200 cr FY26 revenue possible if LOA in 2 months |
| HAM SPV monetization SPA timing (delayed) | Share purchase agreement targeted for mid-July 2025 | SPA expected within one month from this call (mid-September 2025) |
| NHAI debarment risk on Kerala BOT (achieved) | 1-year debarment possible on NHAI show cause notice, INR25-30 cr remediation cost | Delhi HC ruled suspension order has 'lived its life', no longer treated as disqualification |
| Mining diversification (achieved) | Target to bid NTPC, Singareni, WCL mining projects | NTPC Banhardih coal mine LOA received at INR4,800 cr with 74% share |
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| FY25 EBITDA margin | FY25 | 15–16% (on the Q4 FY24 call) | 31.2%, above the range |
| Standalone turnover | FY25 | ₹3,500–3,600 cr (on the Q2 FY25 call) | ₹4,753 cr, above the range |
| Standalone EBITDA margin guidance | FY25 | 13–14% (on the Q2 FY25 call) | 31.2%, above the range |
| Revenue target | FY26 | ₹4,500 cr (on the Q2 FY25 call) | ₹2,698 cr, below the figure guided |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
HAM Roads
58% of Q1 standalone revenue; ₹676 cr of ₹990 cr revised HAM equity infused; four SPVs in advanced monetisation; Delhi HC quashed NHAI one-month debarment on Kerala BOT.
58% of Q1 standalone revenue · HAM equity infused ₹676 cr of ₹990 cr · FY26 HAM equity to infuse ₹185 cr · FY27 HAM equity to infuse ₹129 cr
Outlook: SPA signing within one month to monetise four HAM SPVs and reduce consolidated debt; balance ₹314 cr equity across FY26-FY27.
EPC Roads
31% of Q1 standalone revenue; Mysuru EPC ₹1,200 cr to complete by November; Mangaluru and Chittur-Thatchur also under execution.
31% of Q1 standalone revenue · Mysuru EPC value ₹1,200 cr · 27% of order book
Outlook: ₹80 cr per month from two projects in dry season; ₹10-15 cr in rainy months; bonus targeted by year-end.
Irrigation
6% of Q1 standalone revenue; ₹1,300 cr receivables pending including ₹800 cr certified bills; ₹1,400 cr order book of which ₹500 cr already built.
6% of Q1 standalone revenue · Irrigation receivables ₹1,300 cr · Certified bills ₹800 cr · Order book ₹1,400 cr
Outlook: ₹1,200 cr expected by March 2026 from Telangana after ministerial assurance; ₹300-400 cr execution targeted in FY26.
Water Pipeline
₹1,073 cr order book; Q1 work done (₹200 cr by subcontractor) not yet billed as milestone not achieved; ~₹500 cr unbilled pipeline revenue.
Order book ₹1,073 cr · Q1 subcontractor work ₹200 cr (unbilled) · Unbilled pipeline ₹500 cr
Outlook: ₹500 cr revenue target for FY26 with billing tied to milestone completion; balance to be completed by November FY27.
Mining (New)
Banhardih coal mine LOA received in JV with Harsha Constructions (KNR 74%); contract value ₹4,800 cr ex-GST; 5-year operation + 360 days development; 34.5 million tons coal.
Contract value ₹4,800 cr ex-GST · KNR share 74% · Coal quantity 34.5 million tons · 5-year operation + 360 days development
Outlook: ₹90-100 cr revenue in year 1 (development), then ~₹700 cr per annum; OB removal with existing assets in FY26, mining capex ₹300-400 cr likely in FY27.
Balance sheet, capex and funding
- Consolidated debt ₹2,018 cr as of 30 June 2025 (vs ₹1,847 cr on 31 March 2025); net debt/equity 0.43x (vs 0.41x).
- Standalone cash positive with gross debt ₹5.5 cr and cash ₹81 cr; consolidated cash ₹280 cr.
- Working capital days 169 vs 93 in March; debtors ₹1,228 cr, unbilled ₹996 cr, creditors ₹286 cr.
- HAM equity: ₹676 cr of ₹990 cr revised requirement infused; ₹185 cr to be infused in FY26 and ₹129 cr in FY27.
- Q1 FY26 capex ₹2 cr; FY26 capex guidance up to ₹100 cr; FY27 mining capex could be ₹300-400 cr.
- Retention money receivable ₹338 cr; mobilization advance received ₹48 cr; retention payable ₹150 cr.
The industry, as management sees it
NHAI ordering activity is muted due to the 90% land acquisition gating policy, with only 166 km awarded in Q1 FY26 vs INR3.4 trillion pipeline. FASTag toll collection and traffic growth remain strong (16-19% YoY). Government is tightening bidding norms and rolling out smart construction technology. Industry may see backlog clearing over 9-10 months once land acquisition is sorted, with HAM as the dominant model (INR2 lakh cr+).
Risks management named
- Delayed NHAI awards pending cabinet approval and 90% land acquisition completion
- Telangana irrigation receivables of INR1,300 cr dependent on state bank funding resolving
- No L1 wins in recent bidding round due to aggressive market pricing
- Working capital days spiked to 169 from 93 driven by irrigation debtors
- Standalone EBITDA fell to INR66 cr from INR192 cr YoY on project exhaustion
- Mining project margins could dilute blended EBITDA by 1-2%
Q&A
Execution and order inflow dominated discussion. Analysts pressed hard on the muted Q1 run-rate and the INR500-1,000 cr cut to FY26 revenue guidance, with management citing project exhaustion and delayed order inflow. Detailed questions on Telangana irrigation receivables (INR1,300 cr pending, INR800 cr certified), HAM asset monetization timeline, and the Banhardih coal mining project economics. Pushback was strongest on the FY26 revenue number, where management accepted they could not defend the prior INR2,500-3,000 cr range; on the consolidated 30% EBITDA print, management attributed it to finance-cost accounting rather than underlying performance.
Not answered directly
- NHAI order inflow kilometers for FY25
- Proceeds expected from HAM monetization
- Capital return policy (buyback/dividend)
- FY27 revenue guidance
Asked for a number, answered without one
- NHAI order inflow kilometers in FY25: Actually, the number is there. We'll let you know separately.
- FY27 mining capex number: It could be. It could be. (Later indicated INR300-400 cr for the entire mining project life, not tied to a specific year.)
- FY27 revenue range: It is an assumption kind of that. So definitely, we are focusing on this around INR12,000 crore order intake.
- HAM monetization proceeds value: we are discussing with that on forum, we'll let you know.
Every question, with its answer
1. Execution and FY26 revenue guidance
Alok Deora, Motilal Oswal
Question. Execution has been very muted this quarter. What led to the low execution? How are we seeing the coming quarter? Last call you guided INR2,500-3,000 cr revenue for FY26, any update?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. Existing order book is exhausted - all projects except four are over 90% complete. The four remaining are two HAM projects (appointed in April), Mangalore, and one from last year. Irrigation revenue was just 6% of total as project achieved near completion. Quarter is muted turnover.
Follow-up. What's the outlook now since we got appointed date for a project in April? What is full year guidance? Is it INR2,000-2,500 cr for stand-alone company? That's a big range.
Answer. Mysuru EPC project of INR1,200 cr is being focused for completion by October-November. Dry season revenue will be INR40 cr per project per month, INR80 cr combined. FY26 guidance now stands at INR2,000-2,500 cr; any new orders will add to this. Director K. Jalandhar Reddy added: market has been very aggressive and we could not achieve L1 status in any of the recent bids. INR700 cr of Telangana flyover projects are L1 and MSRDC INR2,200 cr expected in 1-2 months.
Partly answered.
2. Segment-wise revenue ramp and Telangana receivables
Shravan Shah, Dolat Capital
Question. On execution and order inflow (two pain points): how much revenue will the INR3,500 cr mining order generate this year and next? On the INR1,073 cr water pipeline, how much revenue this year and next? Will Marripudi-Somavarappadu HAM complete this year? On Telangana irrigation, INR1,300 cr pending - how much can we receive by March? Two new Telangana irrigation projects of INR430 cr - how much revenue this year?
Answer, K. Jalandhar Reddy, Executive Director. Mining: ~INR90 cr revenue in year 1, then INR700 cr per annum. Water pipeline: INR500 cr by March, balance by November next year. Marripudi-Somavarappadu HAM to be completed mostly this year. On Telangana irrigation: MD had progressive meeting with state government last month, strong assurance on payment; once bank funding issue is sorted, INR800 cr (certified bills) will be released immediately, plus balance INR400-500 cr (unbilled) targeted. New Telangana irrigation projects to be completed by March except the canal project awaiting land acquisition.
3. FY26 guidance reduction and Telangana receivables
Niteen, Aurum Capital
Question. What is the revenue and EBITDA guidance for the year given order book is getting built? Will there be negative growth? Last call guided INR2,500-3,000 cr - is there a reduction? And the status of the court case against Telangana government for INR977 cr payment delay?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. Order book is INR8,300 cr with INR3,500 cr from mining. Mining will contribute only INR90-100 cr this year. FY26 revenue target now INR2,000-2,500 cr (reduced from INR2,500-3,000 cr). Last call assumed order wins which have not materialized. EBITDA margin guided at 13-13.5%. On Telangana: progressive meeting with state government, bank funding issue being addressed, INR800 cr certified bills expected by March plus INR400-500 cr unbilled. Interest claim filed alongside principal recovery.
4. NHAI award pipeline and cabinet approval process
Hiten Jain, Avendus Spark
Question. On order inflow, slowdown due to land acquisition and NHAI has pipeline of INR3.4 lakh cr for FY26. Is there also a delay because projects need cabinet approval? When can we expect Vision 2047-type long-term road plan?
Answer, K. Jalandhar Reddy, Executive Director. NHAI must get cabinet approval and link to land acquisition status. Projects below INR1,000 cr may not require cabinet approval. HAM projects worth INR2 lakh cr+ could be the focus. Land acquisition can happen in phases; if NHAI has confidence to complete in 6 months, tendering takes 45 days, LOA another month, agreement 9-10 months. They may dilute timing to push the program. Cabinet approval is filed with current land status and assurance of completion date.
Partly answered.
5. Diversification into metro and railway
Rehan Saiyyed, Trinetra Asset Managers
Question. On diversification, you mentioned an ambition to enter metro and railway. What tangible steps have been taken so that you can bid in advance stage?
Answer, K. Jalandhar Reddy, Executive Director. We have already discussed with NCC to quote in metros; earlier also quoted and will continue in future. Once the bids in the expected size come up, we will be there. (Call had audio echo issues; analyst could not complete follow-up on timing of metro contribution.)
Partly answered.
6. HAM monetization, consolidated EBITDA mechanics, capital allocation
Faizal Hawa, H.G. Hawa
Question. Once money comes in from HAM equity and profits, will the company be net cash positive? Will interest cost drop below INR10 cr post-Q2? Why did consolidated EBITDA come in at 30% this quarter when guidance is 13-14%? Will the company consider buyback or more aggressive dividends given the cash inflow?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. Standalone is already cash positive - INR5.5 cr debt, INR81 cr cash. HAM monetization will further improve liquidity and transfer debt to incoming investors. 30% consol EBITDA is mainly because consolidated PBT is 23% and PAT 20%; finance cost sits below EBITDA in consol. The 30% margin is essentially a finance-cost accounting effect. On capital return: cash will be used for diversification (BOT toll, metro, solar, mining), not buyback/dividend. Interest cost reduction: INR2,000 cr debt in existing four HAM assets will be wiped off on monetization, but new projects will add debt.
Partly answered.
7. Q1 segment revenue mix and unbilled revenue
Bhavin Modi, Anand Rathi
Question. Can you give the revenue breakup by segment for this quarter? What is the unbilled revenue standing today? Does the INR8,000 cr order book include the INR996 cr unbilled?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. Q1 segment revenue mix: 58% HAM road, 6% irrigation, 31% EPC road, 5% back-to-back. Unbilled revenue is INR996 cr and must be excluded from order book. Net order book is therefore ~INR7,000 cr. Unbilled is split across irrigation and roads (not separately broken out in call - taken offline).
8. Mining project economics, capex, and bid pipeline
Shrey Mehta, Nuvama Wealth Management
Question. For the coal mining block, how much capex and depreciation should we factor? What is the working capital cycle? What is the capex incurred in Q1 FY26 for the entire company? How much capex for the full year? What is the bid pipeline?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. Mining: year 1 is development stage, no significant capex this year. Overburden removal will use existing assets. From next year, heavy mining machinery required - total project capex INR300-400 cr. Depreciation spread across 5-year operation. Working capital for mining to be assessed post mining plan. Q1 FY26 company capex was INR2 cr only; full year capex max INR100 cr. Bid pipeline INR3,500 cr (MSRDC INR2,200 cr + Telangana flyover L1 INR700 cr + balance).
9. FY27 outlook, water and irrigation execution, MSRDC
Vaibhav Shah, JM Financial
Question. FY26 revenue will be impacted, but can we see sharp growth in FY27 from HAM, water and mining? Revenue of INR3,000-3,500 cr possible? What was water project execution in Q1 and full year target? Out of INR996 cr unbilled, is irrigation INR500 cr? What execution from irrigation in FY26 and FY27? MSRDC LOA timing and FY26 execution?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. FY27 outlook is assumption-based. If INR12,000 cr order intake achieved, FY27 will be full execution year returning to normal turnover. Water project: minimal Q1 execution (INR200 cr done by subcontractor but not billable until milestone); targeting INR500 cr this year. Unbilled split: INR500 cr irrigation + INR500 cr roads. Irrigation order book INR1,400 cr (INR500 cr already built), net INR900 cr; FY26 execution INR300-400 cr. MSRDC LOA expected in 2 months pending CM approval; if order in hand by then, INR200 cr execution possible in FY26 via earthworks.
10. Bid pipeline composition and consolidated cash
Shravan Shah, Dolat Capital
Question. Clarification on the INR3,500 cr bid pipeline - this is INR2,200 cr MSRDC and INR700 cr Telangana where we are L1? How much value of projects will we bid by March end across sectors? What is consolidated cash?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. Confirmed: bid pipeline INR3,500 cr comprises INR2,200 cr MSRDC (awaiting approval) and INR700 cr Telangana flyover L1 status. For the full year, we have identified ~45 projects in road sector worth INR80,000-90,000 cr that we will try to bid. Consolidated cash is INR280 cr. On Oddanchatram HAM: equity infused INR64 cr against INR80 cr original requirement - lower because project completed ahead.
11. NHAI order inflow FY25
Hiten Jain, Avendus Spark
Question. How much was the NHAI/road ministry order inflow in FY25? Was it similar to FY24 at around 8,500 km?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. NHAI order inflow has been muted for the last two years (FY24 and FY25). Specific FY25 kilometer number not provided; company to share separately.
Not answered directly.
12. Stand-alone working capital items and mining economics
Bhavin Modi, Anand Rathi
Question. Working capital items on stand-alone basis: debtor billed revenue, creditor amount, mobilization advance and retention money? What is the HAM monetization expected proceeds? Will mining project get any mobilization advance? Will the 7.76% stripping ratio impact EBITDA margin? What is the mining fee quoted?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. Stand-alone working capital: debtors INR1,228 cr (certified bills, excludes unbilled INR996 cr); creditors INR286 cr; retention money receivables INR338 cr; mobilization advance received INR48 cr; retention payable INR150 cr. HAM monetization proceeds to be communicated later. Mining has no mobilization advance - only 10% against overburden removal quantity. Stripping ratio is based on quantity, quoted rate is healthy. Mining fee quoted: INR1,365 per ton (excl. GST); village development and Nala works paid separately at ~INR90 cr.
13. Pipeline project execution and stand-alone balance sheet
Vasudev, Nuvama
Question. Status of the pipeline project - revenue clocked this quarter and full year target? Stand-alone gross debt and cash level?
Answer, K. Venkata Ram Rao, General Manager, Finance and Accounts. Pipeline project: minimal Q1 work; FY26 target INR500 cr (INR200 cr work done by subcontractor but not billable until milestone). Stand-alone gross debt INR6 cr; cash INR81 cr.
What was said
Topic by topic, in the order it was spoken
Industry & Road Sector Overview · K. Venkata Ram Rao (GM, Finance & Accounts)
- NHAI awarded only 166 km of highway projects in Q1 FY26; constructed 1,092 km, slightly ahead of Q1 FY25 levels.
- Slowdown attributed to NHAI policy of initiating bidding only after 90% land acquisition is secured to minimize delays.
- Robust pipeline: INR3.4 trillion across 124 highway/expressway projects spanning 6,376 km (84 HAM, 28 EPC, 12 BOT).
- FASTag toll collection grew 16% YoY in volume and 19% in collection during Q1 FY26.
- Government tightening bidding norms: additional performance security and stricter DPR consultant eligibility criteria.
HAM Project Execution Update · K. Venkata Ram Rao (GM, Finance & Accounts)
- Physical progress as of June 30, 2025: Ramanattukara-Valanchery 99%, Valanchery-Kappirikkad 98%, Chittor-Thatchur 94%, Magadi-Somwarpet 89%, Marripudi-Somavarappadu 43%.
- Equity invested of INR676 cr against revised equity requirement of INR990 cr for HAM projects.
- Balance INR314 cr to be infused: INR185 cr in FY26 and INR129 cr in FY27.
- Detail on each HAM project available in slide 23 of investor presentation.
NHAI Show-Cause Notice Resolution · K. Venkata Ram Rao (GM, Finance & Accounts)
- On May 21, 2025, NHAI issued show-cause notice to KNR Ramanattukara Infra Pvt Ltd (WOS) and parent company on main carriageway/service road concerns.
- Notice led to a one-month suspension from future NHAI bidding.
- Company approached Delhi High Court; on July 21, 2025, court ruled the suspension order had lived its life and bar on bidding was a drastic measure.
- Court observed one-month period is complete and suspension should not be treated as disqualification; department free to take further action per extant policy.
Banhardih Coal Mining LoA · K. Venkata Ram Rao (GM, Finance & Accounts)
- JV with Harsha Constructions received Letter of Acceptance from NTPC for Banhardih coal mine block in Jharkhand.
- KNR share 74%, partner 26%; contract value INR4,800 cr (excluding GST).
- 5-year operation period plus 360-day initial development period; total coal quantity ~34.5 million tons.
- Strategic entry into new business segment, expanding presence beyond core infrastructure.
Order Book & Inflow Guidance · K. Venkata Ram Rao (GM, Finance & Accounts)
- Total order book at INR8,305 cr as of June 30, 2025: 43% mining, 27% roads, 17% irrigation, 13% pipeline.
- Client mix: 79% third-party (74% state government, 4% central government, 1% private) and 21% captive HAM.
- Current order book to be executed in 1.5-2 years (excluding mining).
- FY26 order inflow target: INR10,000-12,000 cr across NHAI, irrigation, mining and state government projects.
Q1 FY26 Standalone Financials · K. Venkata Ram Rao (GM, Finance & Accounts)
- Standalone revenue INR483 cr in Q1 FY26 (muted due to project completions).
- Standalone EBITDA INR66 cr vs INR192 cr in Q1 FY25; EBITDA margin 13.6%.
- Standalone PAT INR51 cr vs INR134 cr in Q1 FY25.
Q1 FY26 Consolidated Financials · K. Venkata Ram Rao (GM, Finance & Accounts)
- Consolidated revenue INR613 cr in Q1 FY26 vs INR985 cr in Q1 FY25.
- Consolidated EBITDA INR183 cr (29.9% margin) vs INR279 cr in Q1 FY25.
- Consolidated PAT INR123 cr in Q1 FY26.
Balance Sheet & Working Capital · K. Venkata Ram Rao (GM, Finance & Accounts)
- Working capital days stood at 169 as of June 30, 2025 vs 93 as of March 31, 2025.
- Consolidated debt INR2,018 cr as of June 30, 2025 vs INR1,847 cr as of March 31, 2025.
- Consolidated net debt to equity at 0.43x as of June 30, 2025 vs 0.41x as of March 31, 2025.
In their words
INR2,000 to INR2,500 crore we are taking on it. But however, any new orders which are coming up and their commitments are happening those will add to that actually.
due to the market being very, very aggressive, so we couldn't achieve the L1 status in any of the projects.
this time, we have a strong assurance to get paid from the dues. So that is one good news, sir.
To check next time
What management committed to on this call, or the dates they gave.
- HAM SPV SPA signing targeted within one month from Aug 12, 2025.
- MSRDC LOA targeted within 2 months (CM final approval pending).
- Telangana irrigation ₹800 cr certified bill release promised within a month.
- Order inflow progress against ₹10,000-12,000 cr FY26 target.
- Mining project overburden removal progress at Banhardih coal mine.
- Telangana flyover L1 projects (₹700 cr) LOA timing.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Tue 12 Aug 2025 | ₹201.89 | −4.00% | −0.40% |
| 5 sessions Tue 19 Aug 2025 | ₹202.88 | −3.53% | +1.61% |
| 20 sessions Wed 10 Sept 2025 | ₹194.96 | −7.29% | +1.58% |
From the close of Mon 11 Aug 2025, ₹210.30: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
KNR Constru's other calls
- Q2 FY27Mon 16 Nov 2026Tone: Mixed
- Q1 FY27Fri 14 Aug 2026Tone: Mixed
- Q4 FY26Mon 1 Jun 2026Tone: Mixed
- Q3 FY26Wed 11 Feb 2026Not read
- CallFri 6 Feb 2026Not read
- Q2 FY26Thu 13 Nov 2025Tone: Cautious
- Q4 FY25Fri 30 May 2025Tone: Cautious
- Q3 FY25Fri 14 Feb 2025Tone: Mixed
- Q2 FY25Wed 13 Nov 2024Tone: Mixed
- Q1 FY25Fri 16 Aug 2024Tone: Mixed
- Q4 FY24Thu 30 May 2024Tone: Cautious