Shriram Properties Q2 FY26 earnings call
In brief
Shriram Properties Q2 FY26 hit by BBMP split, defers INR 420 cr handovers; H2 pipeline of INR 1,000+ cr remains intact
- Management's tone
- Mixed
- What was said
- Even-handed
- Guidance
- Guidance held
- Analyst pushback
- Medium
- Stock, next session
- −3.14% (Nifty 50 +0.70%)
- Q2 sales value reached INR 685 cr (+55% QoQ, +21% YoY) on 1.14 mn sqft sold, even as the BBMP split into 5 corporations from Sept 2, 2025 froze approvals and eKhatas.
- Over 650 units with INR 420 cr of revenue recognition potential were deferred from Q2 to H2; H2 pipeline of ~2,800 units carries INR 1,000+ cr revenue potential.
- 5 new projects added in FY26 so far (2.3 mn sqft, GDV INR 2,350 cr); another 5-6 projects with 6+ mn sqft at advanced diligence stage for closure in coming months.
- Net debt at INR 407 cr with D/E at 0.29x and cost of debt at 11.1%; cash balance INR 286 cr and net free cash flow of INR 99 cr generated in Q2.
- H1 PAT was INR 29 cr (vs INR 17 cr in H1 FY25); H1 gross margin stable at 32% with H1 EBITDA ~INR 70 cr, broadly in line with last year.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q2 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹205 cr | +46.1% | −15.3% | |
| EBITDA (excl. other income) | ₹-5 cr | — | — | -2.5% (-0.9% a year ago) |
| Net profit | ₹8.6 cr | — | −58.4% | 4.2% (-0.7% a year ago) |
| EPS (₹) | ₹0.50 | — | −58.7% |
From the company's filed results for the quarter ended 30 Sept 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
Where management's figures differ from the filing
- Revenue (Q2 FY26, consolidated): said Operating revenue INR 220.5 cr (+49% YoY); total revenue INR 229 cr (+48% YoY); filed Revenue ₹205.31 cr (+46.1% YoY). Gap of ~7% vs filed; management cited total revenue of INR 229 cr vs filed ₹205.31 cr without reconciling the difference on the call
- EBITDA (Q2 FY26, consolidated): said EBITDA INR 23.3 cr (+73% YoY), described as 'healthy'; filed EBITDA excluding other income: ₹-5.04 cr (margin -2.5%). Definition differs: filed figure is EBITDA excluding other income (PBT+fin+depn minus other income); stated INR 23.3 cr appears to include other income of ₹23.7 cr
What moved the numbers, as management explained it
- BBMP restructuring into 5 municipal corporations effective 2 Sept 2025 froze approvals, OCs and eKhatas in Bangalore, deferring 650+ units (INR 420 cr revenue potential) out of Q2. (one-off)
- YoY growth rates benefited from a low Q2 FY25 base that was itself hit by the prior eKhata rollout in Bangalore; absolute Q2 revenues and profits remained modest despite strong 48-73% YoY growth.
- Higher relative overhead absorption from the deferred revenue base pressured EBITDA; management flagged non-recurring one-time settlement costs on the Ashiana land parcel in Kolkata and Pune ground-building costs.
- Finance costs down 19% YoY in Q2 and 18% YoY in H1, supporting the move from a loss in Q2 FY25 to PAT of INR 8.6 cr this quarter.
- Pune expansion (Code Name Superstar, second Hinjewadi project) drove incremental launch and brand-building spend in H1.
The numbers management led with
- Q2 sales volume: 1.14 million sq ft (39% QoQ, 10% YoY)
- Q2 sales value: INR 685 crores (55% QoQ, 21% YoY)
- Q2 deferred revenue recognition: 650+ units with INR 420 crores revenue potential deferred due to BBMP bifurcation
- Pending revenue recognition (Mission 1234): 9.8 mn sq ft with INR 5,000+ crores revenue potential over 3 years
- Hindustan Motor land (Kolkata): 313 acres fully paid freehold; ~130 acres developable; market value INR 3.5-6 cr/acre per public records
Guidance
Guidance on this call
| What | For | What management said | Filed |
|---|---|---|---|
| FY26 unit handovers | FY26 | FY26 handover target 3,000-3,500 units, with ~2,800 units planned in H2 | — |
| FY26 revenue | FY26 | Most likely upwards of INR 1,250-1,300 cr for FY26 | ₹1,267 cr, within the range |
| Annualised EBITDA margin | FY26 | Aspire to ~25% EBITDA margin on annualised basis | 6.9%, below the figure guided |
| PBT margin | FY26 | PBT margin 8-11% | — |
| Gross margin (annualised) | FY26 | Aspire to ~30% gross margin on annualised basis (H1 actual 32%) | — |
| Net debt | FY26 | No significant jump in net debt expected; current net debt INR 407 cr; growth capital to be repaid from project cash flows | — |
| Cost of debt | FY26 | Cost of debt 11.1%; blended to hover around 11% +/- 5-10 bps near term | — |
| BD project additions (next few months) | H2 FY26 | On track to add another 5-6 new projects with 6+ mn sqft potential in next few months | — |
| ROCE/ROE | FY28 | Mid-teen ROCE/ROE by FY28 under Mission 1-2-3-4 | — |
| Mission 1-2-3-4 supply target | FY26-FY28 | Need 30-35 mn sqft over the next 3 years; 22.4 mn sqft visible today, adding 15-20 mn sqft in 12-18 months | — |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
What changed since the Tue 12 Aug 2025 call
| What | On the Tue 12 Aug 2025 call | On this call |
|---|---|---|
| FY26 unit handover target (cut) | 3,300-3,600 units (1,400 Kolkata, 1,800 Bangalore, rest Chennai) | 3,000-3,500 units for the full year; H2 alone carries 2,500+ unit pipeline |
| Net debt (raised) | INR 380 cr (Q1 FY26); no significant jump expected | INR 407 cr; management reiterates no significant jump expected |
| Net D/E ratio (raised) | 0.28x at end-Q1 FY26 | 0.29x; still well within comfort range |
| Code Name Superstar (Pune) sell-through (achieved) | 150 units / 36% of open supply sold within 4 weeks of launch | 48% sold in Phase 1 of 0.44 mn sqft (project area 0.89 mn sqft) |
| FY26 revenue target (restated) | Most likely upwards of INR 1,250-1,300 cr for FY26 | Confident of crossing INR 1,000-1,200 cr; H1 already at INR 450+ cr, H2 potential ~INR 1,000 cr |
| Project pipeline additions in FY26 (achieved) | 6 projects (~3 mn sqft) nearing closure plus 5 at advanced commercial stage; target to double pipeline in 18-24 months | 5 projects already added (2.3 mn sqft, GDV INR 2,350 cr), with 5-6 more at advanced diligence for closure in next few months |
| Mission 1-2-3-4 (FY28 targets) (held) | Mid-teen ROCE/ROE by FY28 under Mission 1-2-3-4 framework | Mission 1-2-3-4 remains fully intact; FY28 revenue/PAT mission numbers reconfirmed |
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| Deferred revenue recognition | Q3 FY25 | at least ₹150 cr (on the Q2 FY25 call) | ₹121 cr, below the range |
| FY25 sales value growth | FY25 | at least 27% (on the Q4 FY24 call) | -69.7%, below the range |
| FY25 PAT margin | FY25 | 9–10% (on the Q4 FY24 call) | 9.4%, within the range |
| Sales value | FY25 | at least ₹2,700 cr (on the Q2 FY25 call) | ₹823 cr, below the range |
| Revenue recognition | FY25 | at least ₹1,200 cr (on the Q2 FY25 call) | ₹823 cr, below the range |
| PAT | FY25 | ₹100 cr (on the Q2 FY25 call) | ₹77 cr, below the figure guided |
| Full-year revenue | FY25 | ₹1,100 cr (on the Q2 FY25 call) | ₹823 cr, below the figure guided |
| Revenue growth (range) | FY26 | 25–35% (on the Q4 FY25 call) | 53.9%, above the range |
| EBITDA margin (target) | FY26 | 22–25% (on the Q4 FY25 call) | 6.9%, below the range |
| PAT margin (target) | FY26 | 8–10% (on the Q4 FY25 call) | 8%, within the range |
| FY26 revenue | FY26 | ₹1,250–1,300 cr (on the Q1 FY26 call) | ₹1,267 cr, within the range |
| FY26 EBITDA margin | FY26 | 22–25% (on the Q1 FY26 call) | 6.9%, below the range |
| FY26 PAT margin | FY26 | 8–10% (on the Q1 FY26 call) | 8%, within the range |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
Residential real estate (Bangalore, Chennai, Kolkata, Pune)
Q2 operations ran on the strength of pre-Sept 2 momentum; H1 sales value INR 1,126 cr (+19% YoY), collections INR 725 cr, 1,504 units handed over. Q2 financials muted by BBMP-driven handover deferrals, not by demand.
Q2 sales volume 1.14 mn sqft · Q2 sales value INR 685 cr · Q2 collections INR 388 cr · Q2 handovers 764 units · H1 sales value INR 1,126 cr · H1 collections INR 725 cr · H1 handovers 1,504 units · Q2 revenue INR 229 cr · Q2 EBITDA INR 23.3 cr · Q2 PAT INR 8.6 cr · H1 PAT INR 29 cr
Outlook: Confident of recouping lost ground in H2 FY26; H2 pipeline of ~2,800 handovers with INR 1,000+ cr revenue potential materialising; FY26 handover target of 3,000-3,500 units intact
Balance sheet, capex and funding
- Net debt INR 407 cr (vs INR 380 cr at end-Q1 FY26); net D/E 0.29x
- Cost of debt 11.1%; CRISIL A- positive rating reaffirmed
- Cash balance INR 286 cr at end-Q2 FY26
- Q2 operating cash flow INR 52 cr; net free cash flow INR 99 cr after INR 68 cr invested in new BD projects
- H1 BD investment INR 143 cr across 5 new projects; INR 68 cr of Q2 deployment was growth capital for project lock-ins, not construction finance
- No significant jump in net debt expected; growth capital to be repaid from project cash flows as completions occur
The industry, as management sees it
Bengaluru residential market has structurally grown from 45,000-55,000 homes annually to 75,000-80,000+ units and continues to grow. Mid-market segment has a 3-4 year runway driven by post-COVID demand for larger homes. Industry is consolidating post-RERA - top 10 players now account for >55-56% of organised residential sector. Pricing is in a steady-state mature environment with 5-8% annual increases covering construction inflation. No supply-driven price pressure expected given consolidation discipline.
Risks management named
- Quarterly revenue and margin volatility from regulatory events in core Bengaluru market
- eKhata issuance pace remains a gating factor for handover acceleration in H2
- Pending litigation on Kolkata land parcel could affect monetisation timeline
- Q4 revenue concentration risk if H2 handovers and recognition slip into FY27
Q&A
Q&A was dominated by three themes: regulatory disruption and recurring events in core markets, the INR 259 cr Calcutta contingent liability and H2 revenue recognition timing. CEO Gopalakrishnan handled most questions, becoming mildly defensive when challenged on the recurring nature of regulatory hurdles and on the historical 10% PAT margin guidance - explicitly correcting the analyst's framing on revenue delays. Pushback was strongest from Divakar (Prudent Equity) on PAT trajectory, from Nitin Jain on recurring regulatory events, and from Saumil Shah on the unrecognised value of the Kolkata land parcel. Management was most forthcoming on operational KPIs and H2 recovery visibility, but deferred the year-wise split of the INR 5,000 cr FY28 revenue target to offline conversations via SGA.
Not answered directly
- FY28 revenue year-wise split (deferred to offline conversation)
- Next hearing date for West Bengal High Court case
- Detailed split of H2 collection by geography
Asked for a number, answered without one
- Year-wise split of INR 5,000+ cr pending revenue recognition across FY26, FY27 and FY28: Declined to give on a group call; offered to take the analyst offline to walk through the modeling inputs
- Projected cumulative PAT for FY26-FY28: Confirmed cumulative could be possible but declined to put a number on annual profit
- Next hearing date for West Bengal High Court case on the Kolkata contingent liability: Said 'You will hear from us very soon on this' without giving a date
Every question, with its answer
1. Calcutta contingent liability
Divakar, Prudent Equity
Question. What is the total amount of contingent liability pertaining to the Calcutta projects?
Answer, Gopalakrishnan J, Executive Director & CEO. The contingent liability (provision) on the books is INR 259 crores, substantial part of which is already provided for. Historically provision was ~INR 5 cr per quarter; Q2 FY26 we provided INR 1.71 cr. On H1 basis INR 3.2 cr provided vs INR 16 cr last year. We are at the fag end of the process and expect resolution fairly soon; the provision should disappear in the coming quarters, hopefully during this year itself.
Follow-up. This case is pending in the High Court of West Bengal, right? When will be the next hearing?
Answer. Confirmed the matter is in West Bengal High Court. On the next hearing date: 'You will hear from us very soon on this.'
Not answered directly.
2. Recurring revenue delays
Divakar, Prudent Equity
Question. Three to four years ago the company used to give 10% PAT margin / ~INR 100 cr PAT guidance but has not touched even INR 80-85 cr. How do you plan to reach INR 100 cr PAT / INR 1,000 cr revenue / 10% PAT margin?
Answer, Gopalakrishnan J, Executive Director & CEO. CFO clarified guidance has been mid-20s EBITDA margin and 9-11% PBT consistently. FY25 PAT margin was ~8% (INR 77 cr on INR 816 cr revenue). 'We are on the path. Hopefully this year we will reach the 1,000 odd crore revenue mark... and that should translate into the profitability level that you alluded to.' Cited trajectory from INR 18-19 cr PAT in 2022 to INR 77-78 cr now with margin moving from 7-8% towards ~10% PAT target.
Follow-up. Revenue delays appear to be a recurring issue - similar pattern seen last year. Continuously happens for Shriram Properties.
Answer. 'Facts are incorrect.' Cited last year Q4 was a bumper quarter; Q2 last year had similar eKhata issue. BBMP bifurcation on 2 Sep is macro/sector-wide. 'Every company's revenue recognition, earnings, and margins would have gone through difficulty during Q2.' Quarterly volatility is normal; over 3-4 years the company has progressed consistently.
Not answered directly.
3. Inventory composition
Divakar, Prudent Equity
Question. In inventory of ~INR 2,600 cr, what is the split between finished goods and work-in-progress?
Answer, Gopalakrishnan J, Executive Director & CEO. 'Very insignificant part of finished goods inventory in our books.' Of ~19-20 mn sq ft ongoing, unsold inventory is ~3 mn sq ft and 85% of inventory is sold. Projects with OC received or pending OC as of 30 Sep are ~INR 300 cr (per Slide #15 first four rows) - this is the finished goods value. Completed project inventories are insignificant in SPL's portfolio.
4. Recurring regulatory hurdles
Nitin Jain, Fairvalue Advisors
Question. BBMP restructuring must have been known earlier - surprised there was no mention in the last call that this was upcoming.
Answer, Gopalakrishnan J, Executive Director & CEO. 'Restructuring was known but timing of implementation was not known.' Karnataka Assembly passed the act around May-June 2025; effective date of 2/3 Sep was a surprise. BBMP stopped taking decisions, new corporation took time to stabilise with officers appointed later and unfamiliar with jurisdiction. 'Couple of months of delay is not something that would be worried about from BBMP perspective.' For listed companies quarter-to-quarter matters but on full fiscal year basis no significant difference.
Follow-up. It keeps happening - regulatory issues in Maharashtra last year, Karnataka now. Are we falling short on planning?
Answer. 'It is an incorrect impression.' Every company has learning curve in new markets; took 6 months for approvals in Maharashtra. eKhata in Bangalore last year and BBMP bifurcation this year happen in any business. Despite eKhata issues last year delivered 3,300 homes. 'Temporary aberrations in volumes... will get caught up in subsequent quarters.'
5. OC delays vs handover growth
Nitin Jain, Fairvalue Advisors
Question. OCs were delayed and collection growth was slow, but handover growth was pretty good. How do you reconcile the two?
Answer, Gopalakrishnan J, Executive Director & CEO. Handover growth 'not that robust - should have been much higher.' Customers paid full money but registration couldn't happen due to eKhata issues. Mix of units matters - Bangalore suffered so majority of H1 handovers were in Kolkata with smaller ticket sizes (~INR 45 lakh, ~INR 4-5 lakh balance). H1 collections INR 725 cr (+6%); confident of reaching INR 1,800 cr collection target. Two factors will help: new launches bringing new collections, and ~INR 460 cr pending pent-up handovers with 5-10% balance receivable at handover stage.
6. Borrowing increase rationale
Nitin Jain, Fairvalue Advisors
Question. Borrowing increase in this quarter - were these lined up to make sure launches happen on time?
Answer, Gopalakrishnan J, Executive Director & CEO. 'Nothing to do with launches.' Borrowings were primarily growth capital for locking in new BD projects. 5 projects locked this year (3 in Oct) required capital raise. Debt-equity will be kept in check (0.3-0.5x range). As new projects complete and profit share unlocks as operating cash flow, these debts will be repaid. Net basis will remain under control; 'these were raised for growth funding.'
7. FY28 revenue flow timing
Vidhi Shah, CRK
Question. You said INR 450 cr is deferred revenue and 4.6 mn sq ft is pending revenue recognition. Is this INR 450 cr part of pending revenue recognition?
Answer, Gopalakrishnan J, Executive Director & CEO. Confirmed. Slide #6 lists projects that didn't get OC in Q2 (INR 420 cr worth to be handed to customers). Slide #15 shows INR 1,128 cr worth of stock for full year handover. Substantial part of that is sold - potential H2 revenue recognition. Already at ~40% of annual number; balance from INR 1,128 cr pipeline which includes the INR 460 cr number. Should cross INR 1,100-1,200 cr revenue that has been guided.
Follow-up. Slide #26 says INR 5,000 cr by FY28. Out of pending revenue recognition, INR 1,100 cr will be recognised in H2 - correct?
Answer. 'Might not be possible because if you get the OC during Q4, all of them may not be possible. Substantial part could be recognised, balance will spill over to Q1 and Q2 next year.'
Partly answered.
8. H2 FY26 recognition timeline
Vidhi Shah, CRK
Question. Can you give a rough year-wise split of how INR 5,000 cr will flow in FY26 / FY27 / FY28?
Answer, Gopalakrishnan J, Executive Director & CEO. 'Very difficult to explain on a large audience group. Maybe you can get in touch with one of us offline. We will probably walk you through.' IR team (SGA) will organise a conversation. 'Modeling has to be done by you. We can only broadly guide.'
Follow-up. INR 1,100 cr will be spread in next four quarters (H2 of FY26) - correct?
Answer. 'INR 1,100 cr will get spread mostly in second half (Q3 and Q4). Some part will spill over to Q1 next year. Q2 next year will be very small number.'
Not answered directly.
9. Land value per acre
Saumil Shah, Paras Investments
Question. On Hindustan Motor land in Kolkata - what is the size and is it 100% freehold?
Answer, Gopalakrishnan J, Executive Director & CEO. 'Over 313 acres of land, and it is freehold. Fully paid and in books for many years. Owned by Shriram Properties Limited through subsidiary (PE player Walton Street was original partner, merged into company). Out of 313-315 acres, ~40 acres utilised for development (Shriram Grand One, Shriram Sunshine). Discussions with West Bengal government hopefully to be heard soon. Strategy: develop 10 mn sq ft by themselves, rest to be monetised.
Follow-up. What could be the price per acre?
Answer. 'Very difficult to comment. Per sub registrar records anywhere between INR 3.5-4 cr to INR 6 cr.'
Partly answered.
10. FY28 project GDV
Saumil Shah, Paras Investments
Question. Approximate value would be INR 1,200-1,500 cr for this land? Do we have any dues to pay? And is the developable area ~125-130 acres?
Answer, Gopalakrishnan J, Executive Director & CEO. Large parcel - water bodies need to be maintained. Developable area ~130 acres. Doing some settlement to overcome ongoing litigation; at end of process. 'A large chunk, large value is residing there as simple acreage value, which market does not appreciate.' 'Fully paid freehold land' - no dues. ~125-130 acres to be developed - confirmed.
Follow-up. What is the total GDV for next 2.5-3 years (till FY28) across own and JV/JDA projects?
Answer. Per Slide #11, upcoming projects GDV is INR 11,470 cr; nearly half (INR 5,000 cr) is own. Substantial part of this will be launched before FY28 since 'we do not have a land bank. Other than Kolkata, we do not have any land bank in the balance sheet.' Lands acquired are launched within FY28.
11. Cumulative profit forecast
Saumil Shah, Paras Investments
Question. Cumulative profit for FY26-FY28 (2.5 years) of INR 550-600 cr - is that possible?
Answer, Gopalakrishnan J, Executive Director & CEO. 'Cumulative would be possible, but not annual profit.' Cumulative INR 550-600 cr confirmed as plausible.
12. Growth strategy and partnerships
Raj Mehta, Raj Mehta and Associates
Question. How is the sector in Bengaluru performing post the regulatory hurdles? Any challenges with construction or demand? Can margins be maintained?
Answer, Gopalakrishnan J, Executive Director & CEO. Comprehensive market view: market doing very well, strong demand, faster customer decision-making. Cited Codename The One at 80% sell-through in <3 months. Pricing in steady state with 5-8% annual hike covering construction inflation - no margin pressure. Bangalore has grown from 45,000-55,000 homes market to 75,000-80,000+. Industry consolidating - top 10 players now >55-56% of organised market. Mid-market segment has longer runway for 3-4 years; post-COVID theme of larger homes continues. 'Industry is benefiting from consolidation which has been going on for last 3-5 years since RERA came in.'
Follow-up. Smaller players/regional players in Pune tied up with PE funds and growing. Could we bring a bigger player so we can expand aggressively without leveraging balance sheet?
Answer. 'Market views us as bigger players. We are not looking for a bigger player.' In Pune, several local players called them; SPL has painted the city in blue. Sold 250+ units in Undri in 4 months (micro-market annual velocity was 400 units). Within 6 months of entry signed another project in Hinjewadi. Growing within prudent debt-equity norms (never crossed 0.3-0.5x). 'We should be able to show the aggression and consolidate a smaller player in us, either as an investor or as a DM partner.'
13. Investor outreach and roadshows
Raj Mehta, Raj Mehta and Associates
Question. Are you looking at Hyderabad or other markets to diversify from Bangalore, Chennai and Kolkata and reduce state-specific risk?
Answer, Gopalakrishnan J, Executive Director & CEO. 'Rome was not built in one day.' Focus first on Pune as new growth engine; need 4-5 projects running on ground to establish strong presence. Once Pune stabilises over next year, will think about Hyderabad or Mumbai/MMR. 'Enough opportunities for a credible, large brand with a proven track record irrespective of which market you want to go.'
Follow-up. Are we taking steps towards building investor confidence via roadshows or conferences?
Answer. 'Accelerated the effort, helped by IR teams and external IR consultants.' Engaged with analysts, fund managers and family offices. 'Over the last two quarters, both our CFOs and the IR team have been on the road after every result trying to go and meet the large investors consistently.' Requested analysts on the call to start coverage for institutionalisation.
14. H2 revenue potential
Nitin Jain, Fairvalue Advisors
Question. On Slide #15, is H2 revenue potential approximately INR 1,100 cr given H1 was INR 450 cr?
Answer, Gopalakrishnan J, Executive Director & CEO. 'Substantial part of INR 1,100 cr is a potential. It may not be all.' Same data in project-by-project slide. Some projects due for OC in Q3 and Q4 (Kolkata and Bangalore); may not be possible to consummate entire revenue in Q3/Q4 alone. 'Substantial part will come through in H2. The rest will come through in Q1.' 'Working towards it. Very confident that it will happen.'
15. Mission 1234 interpretation
Vidhi Shah, CRK
Question. In last call you mentioned INR 250-280 cr PAT and INR 3,000 cr revenue. Is this for FY28 alone or cumulative for FY26-FY28?
Answer, Gopalakrishnan J, Executive Director & CEO. 'The numbers are for FY28.' Confirmed standalone FY28 target, not cumulative. Numbers (INR 2,500-3,000 cr revenue and INR 250-280 cr PAT) are target/aspirational/mission numbers for FY28 alone.
What was said
Topic by topic, in the order it was spoken
CMD Opening: Operational Resilience Despite Regulatory Headwinds · Murali M. (Chairman and Managing Director)
- Q2 was another encouraging quarter with strong operational performance and sequential growth across key metrics
- Temporary financial headwinds from Bangalore regulatory transitions; fundamentals remain robust
- Sales volume of ~1.1 mn sq ft in Q2 (+39% QoQ), valued at INR 685 cr (+55% QoQ); H1 sales ~2 mn sq ft / INR 1,126 cr (+19% YoY)
- 5 new projects added in FY26 with 2.3 mn sq ft development potential and GDV INR 2,350 cr
- Advanced stages of finalising additional projects with 6+ mn sq ft potential in H2, providing growth visibility
- Strong rebound expected in H2 driven by project completions and revenue recognition
Company Overview and Positioning · Ravindra Kumar Pandey (Chief Financial Officer)
- 25+ years of leadership with presence in Bangalore, Chennai, Kolkata and Pune
- 48 completed projects and over 29 mn sq ft delivered; 31,000+ happy customers with ~25% referral-driven sales
- One of the most disciplined developers with debt/equity of 0.3x and CRISIL A+ positive rating
- Mid-market and mid-premium residential brand built on legacy, performance and trust
BBMP Bifurcation and Q2 Impact · Ravindra Kumar Pandey (Chief Financial Officer)
- BBMP split into 5 municipal corporations effective 2 Sep 2025; once-in-a-lifetime event
- Paralysed approvals, completion certificates and eKhata issuance impacting entire Bengaluru real estate sector
- 650+ units across 5 projects with INR 420 cr revenue recognition potential deferred to H2
- Normalcy returning from end-October; new corporations functional, OCs flowing, eKhata issuance resumed
Q2 Operational and Financial KPIs · Ravindra Kumar Pandey (Chief Financial Officer)
- Q2 sales volume 1.14 mn sq ft (+39% QoQ, +10% YoY); sales value INR 685 cr (+55% QoQ, +21% YoY)
- Q2 collections INR 388 cr (+15% QoQ, +7% YoY) despite registration delays; 764 units handed over (+3% QoQ, +30% YoY) with 56% from JV projects
- Q2 operating revenue INR 220.5 cr (+49% YoY); total revenue INR 229 cr (+48% YoY); EBITDA INR 23.3 cr (+73%); PAT INR 8.6 cr vs loss last year
- H1 operating revenue INR 475 cr (+33% YoY); gross profit INR 143 cr (+53%); gross margin stable at 32%; H1 PAT INR 29 cr vs INR 17 cr last year
- Gross margin stable at 30%+; muted absolute numbers solely due to deferred revenue recognition
Business Development and Pipeline · Ravindra Kumar Pandey (Chief Financial Officer)
- 5 new projects added in FY26 with ~2.3 mn sq ft potential and GDV INR 2,350 cr; 3 closed in Oct alone
- On track to add 5-6 more projects with 6+ mn sq ft potential over next few months
- BD funnel strong with 20+ mn sq ft under active evaluation across Bangalore, Chennai and Pune
- Targeted pipeline addition supported for next 12-18 months
Project Pipeline, Launches and Handover Outlook · Ravindra Kumar Pandey (Chief Financial Officer)
- Upcoming project pipeline GDV over INR 11,400 cr; on track to nearly double upcoming pipeline in 18-24 months
- 3 H1 launches: Code Name Superstar (Pune, 48% sold), Code Name The One (Bangalore, 80% sell-through), Springfield Phase 2 (Kolkata, 43% sold)
- H2 launch pipeline of ~2.7 mn sq ft with GDV ~INR 2,200 cr across Bangalore, Chennai and Kolkata
- H2 handover of ~2,800 units / 2.5+ mn sq ft with INR 1,000+ cr revenue recognition potential; full-year target 3,000-3,500 units
Cash Flow and Balance Sheet Strength · Ravindra Kumar Pandey (Chief Financial Officer)
- Q2 operating inflows INR 264 cr; H1 INR 485 cr despite registration delays
- Positive operating cash flow of INR 52 cr in Q2 and net free cash flow of INR 99 cr even after INR 68 cr invested in BD
- H1 invested INR 143 cr in new positions; closing cash balance INR 286 cr
- Net debt INR 407 cr; net D/E 0.29x; cost of debt reduced to 11.1%; CRISIL A+ positive rating maintained
Mission 1234 and Business Outlook · Ravindra Kumar Pandey (Chief Financial Officer)
- Mission 1234 (FY28) fully intact: ~9.8 mn sq ft pending revenue recognition worth INR 5,000+ cr over next 3 years
- Need 30-35 mn sq ft over 3 years to deliver mission; 22.4 mn sq ft visible today, adding 15-20 mn sq ft in next 12-18 months
- GBA transition stabilising; eKhata issues largely behind us; entering H2 on solid footing
- Confident of delivering strong H2 rebound and staying on course for FY28 growth mission
In their words
Be assured, these are temporary aberrations in volumes and they will get caught up in subsequent quarters like we did last year.
This transition nearly paralyzed the real estate sector in approvals, completion certificates and issue of eKhatas that are mandatory for unit registration ahead of handover and income recognition.
A large chunk, large value is residing there as a simple acreage value, which market does not appreciate.
To check next time
What management committed to on this call, or the dates they gave.
- Execution of the H2 FY26 handover pipeline of ~2,800 units (vs Q2's 764 units) and materialisation of the INR 1,000+ cr revenue potential
- Closure of the 5-6 new projects (6+ mn sqft) currently in advanced diligence
- Update on the West Bengal contingent liability and Hindustan Motor Kolkata land settlement (management promised an update soon)
- Launch execution of the 2.7 mn sqft / INR 2,200 cr GDV launch pipeline lined up for H2
- eKhata and OC normalisation pace in Bangalore post-October
- Confirmation of FY26 revenue crossing INR 1,250-1,300 cr guidance
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Wed 12 Nov 2025 | ₹90.58 | −3.14% | +0.70% |
| 5 sessions Tue 18 Nov 2025 | ₹89.02 | −4.81% | +0.84% |
| 20 sessions Tue 9 Dec 2025 | ₹84.59 | −9.55% | +0.56% |
From the close of Tue 11 Nov 2025, ₹93.52: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
Shriram Properties's other calls
- Q2 FY27Fri 20 Nov 2026Not read
- H1 FY27Fri 13 Nov 2026Not read
- Q1 FY27Thu 13 Aug 2026Tone: Confident
- Q4 FY26Mon 25 May 2026Tone: Cautious
- Q3 FY26Sat 14 Feb 2026Tone: Confident
- Q1 FY26Tue 12 Aug 2025Tone: Confident
- Q4 FY25Tue 27 May 2025Tone: Confident
- Q3 FY25Wed 12 Feb 2025Tone: Mixed
- Q2 FY25Thu 14 Nov 2024Tone: Confident
- Q1 FY25Wed 14 Aug 2024Tone: Mixed
- Q4 FY24Thu 30 May 2024Tone: Confident