Solex reported H1 FY25 income of ₹2,742 million, up 192%, and targets 4 GW of module capacity by June 2025.

Management's tone
Confident
What was said
Leaned positive
Guidance
First guidance issued
Analyst pushback
Low
Stock, next session
−5.00% (Nifty 50 −1.36%)
  • H1 FY25 income was ₹2,742 million, up 192% from ₹930 million in H1 FY24.
  • Management retained a June 2025 target for 4 GW of module capacity, while noting international shipping could delay it by one or two months.
  • FY25 revenue was targeted at ₹800 Cr, comprising ₹650 Cr from modules and ₹150 Cr from EPC.
  • Management guided to FY26 revenue of ₹2,400-2,500 Cr and FY27 revenue of ₹3,400-3,600 Cr.
  • Management said EBITDA margin would vary between 9% and 11%, with PAT margin around 5%.

An AI read of the company's transcript · the filing

The numbers

What moved the numbers, as management explained it

  • H1 FY25 was seasonally light: management said projects are typically commissioned in January-March and an extended monsoon delayed readiness; modules are delivered last.
  • PAT's 1,697% growth was against a low H1 FY24 base: PAT was almost 17x higher and margin rose from 0.8% to 4.8%.
  • The H1 FY25 module mix was almost 50% Solex brand and 50% OEM, versus 30% Solex and 70% OEM in H2 FY24.
  • H1 FY25 module revenue was ₹240 crore and EPC revenue ₹32 crore; exports were not a focus while capacity was booked.
  • H1 FY25 module revenue was ₹240 crore; aluminium-frame anti-dumping duty had affected pricing, while solar-glass impact remained unquantified.

The numbers management led with

  • Module capacity expansion capex: ₹280 crore project cost for 4 GW module expansion (building/land not included)
  • Capacity expansion funding mix: ₹210 crore debt + ₹70 crore equity for 4 GW expansion; existing term debt ~₹60 crore
  • Vision 2030 investment commitment: ~$1 billion cumulative investment to achieve 15 GW module + 5 GW cell capacity
  • H1 FY25 revenue growth: Revenue ₹274 crore in H1 FY25 vs ₹93 crore in H1 FY24 — 192% YoY growth

The company's filed results for this quarter are not on file with us yet; these are management's own figures from the call.

Guidance

Guidance on this call

WhatForWhat management said
Consolidated revenueFY25FY25 consolidated revenue target was ₹800 Cr, including ₹650 Cr from modules and ₹150 Cr from EPC.
Consolidated revenueFY26FY26 revenue target was around ₹2,400-2,500 Cr.
Consolidated revenueFY27FY27 revenue target was around ₹3,400-3,600 Cr.
EBITDA marginFY25-FY27EBITDA margin was expected to vary between 9% and 11% and improve each year.
PAT marginFY25-FY27PAT margin was expected to be around 5%.
Module manufacturing capacityQ1 FY261.5 GW was due by December/January, 2.5 GW line orders by 15-30 December, and full 4 GW operational by June 2025.
Manufacturing investmentFY26-FY30Manufacturing investment was planned at almost $1 billion by 2030.
Module manufacturingFY26-FY30Module manufacturing capacity was targeted at 15 GW by 2030.
Cell manufacturingFY26-FY30Cell manufacturing capacity was targeted at 5 GW by 2030; the process for a 2 GW line was initiated.
Tapi-R N-Type TOPcon launch (Module Manufacturing)Q4 FY25Tapi-R was planned for mid-January or early-February 2025.
Module production capacity (Module Manufacturing)FY25Capacity with the expanded line was described as 1,25,000 modules per month.
Full-year module turnover (Module Manufacturing)—The full-year turnover from modules was described as about ₹3,200 crore.
Working capital cycle—Management's working-capital cycle target was 45 days.
Solex brand share of module revenue (Module Manufacturing)H2 FY25-H2 FY26H2 FY25 and H2 FY26 were expected at 80% Solex brand and 20% OEM.
Export revenue (Module Manufacturing)FY26Next year, management expected a good number of revenue from exports.

The business

By business

Module Manufacturing

Module sales were ₹240 crore in H1 FY25, against ₹32 crore from EPC. The mix was almost 50% Solex brand and 50% OEM; current output was around 50,000 modules per month.

Module revenue ₹240 crore · EPC revenue ₹32 crore · Current production around 50,000 modules per month · Output also reached 60,000 modules per month · Solex brand mix 50% · OEM mix 50%

Outlook: The 1.5 GW line was expected to contribute from January/February 2025; 4 GW was targeted for June 2025, with FY25 module revenue of ₹650 Cr and Tapi-R planned for mid-January/early-February.

EPC Solutions

EPC contributed ₹32 crore of H1 FY25 revenue. Solex Green Energy offers rooftop, street-lighting and ground-mounted solutions, including utility-scale projects.

EPC revenue ₹32 crore

Outlook: FY25 EPC revenue was targeted at ₹150 Cr.

Cell Manufacturing

No H1 cell revenue was stated. Management said it had initiated the process for a 2 GW cell line within its Vision 2030 roadmap.

Cell-line process 2 GW · Cell capacity target 5 GW

Outlook: Management targeted 5 GW of cell manufacturing by 2030; the technology for the remaining 3 GW was undecided.

Balance sheet, capex and funding

  • The expansion project cost was about ₹280 crore, covering plant and infrastructure but excluding building and land.
  • Planned expansion funding was ₹210 crore of debt and ₹70 crore of equity; management said advances were available to place equipment orders.
  • Existing term debt was around ₹300 crore.
  • Management's working-capital target was a 45-day cycle, supported by customer advances and domestic and international creditor credit.
  • Vision 2030 manufacturing investment was about $1 billion.
  • Fixed assets were around ₹54 crore; additions of ₹80-85 crore and about ₹280 crore were cited, with overall assets of ₹415-420 crore.

The industry, as management sees it

Management believes India is moving from 500 GW RE target to 750 GW and eventually 1 TW, with solar contributing over 60% share. Electricity consumption growth has stepped up from historical 3% to 9% and likely to touch 12%. Industry capacity (70 GW current, 100 GW by March 2025) is required not just for India but also for US and Europe exports and repowering demand — they reject the overcapacity narrative.

Risks management named

  • International shipping/vessel availability could delay 4 GW June 2025 commissioning by 1–2 months
  • Anti-dumping duty on solar glass/aluminium frames could pressure raw-material costs; mitigated via change-in-law clauses
  • N-Type TOPcon initially showed higher UV/degradation vulnerability; Indian developers remain conservative
  • U.S. policy inconsistency under Trump administration on solar manufacturing incentives
  • Industry overcapacity narrative disputed — relies on 750 GW–1 TW target revision materialising

Q&A

Q&A was orderly and largely informational — analysts probed capacity ramp execution, capex funding mix, brand-mix trajectory and US opportunity. The deepest engagement came from Udit Sehgal on the FY26/FY27 revenue glidepath and from Aman Madrecha on debt/ALCM/TOPcon reliability; both got detailed, multi-part answers. Management showed no visible defensiveness, deflected very little, and used the call to formally anchor the three-year revenue targets (₹800 Cr → ₹2,400–2,500 Cr → ₹3,400–3,600 Cr) for the first time. The only mild surprise was the candid dismissal of US manufacturing and the explicit framing of Trump-era policy risk as positive for Indian exporters.

Not answered directly

  • Cell-line fundraising specifics (Vipul said 'still at initial level, will share once finalised')
  • Exact monthly revenue figure post 1.5 GW ramp (Chetan redirected to annual guidance)

Asked for a number, answered without one

  • Monthly revenue run rate: Management cited 1,25,000 modules per month and an FY25 annual revenue target of ₹800 Cr, not a monthly revenue figure.
  • Quarterly module volumes: Management agreed to quarterly revenue, EBITDA and PAT reporting from the first quarter of 2025 but gave no module-volume disclosure.
  • Tapi-R pricing and capacity share: Management said pricing would differ little and production lines were compatible, but gave no premium or capacity-share percentage.
  • Export share of current revenue: Management said capacity was already booked and exports were not a focus, without quantifying the revenue share.
  • Rupee working-capital requirement: Management gave a 45-day working-capital cycle target rather than a rupee requirement.
  • P-Type to N-Type cost variance: Management said the two technologies cost almost the same and saw no major cost difference.

Every question, with its answer

  1. 1. Quarterly reporting & Tapi-R product economics

    Agastya Dave, Independent/Unknown

    Question. Requested quarterly results disclosure and module volume numbers. Asked about Tapi-R product — pricing premium, manufacturing cost delta, cell configuration changes, and share of expanded capacity addressable.

    Answer, Chetan Shah, Chairman & Managing Director. Confirmed quarterly reporting will start once main-board listing happens (likely Q1 CY25). On Tapi-R, said realisations will not differ materially because developers save via lower module count per MW (~1,450 vs ~1,750), BOS and land (2.25–2.5 acres vs 2.75 acres/MW). Width same as current modules, just taller by 100 mm; all upcoming lines are G12R-compatible with minimal upgrade to back-contact/HJT. Production lines can flex between M10 and G12R as customer demand dictates.

  2. 2. Capacity expansion, capex funding and revenue glidepath

    Udit Sehgal, Unknown

    Question. Where is the 4 GW expansion — building, equipment, funds, timeline? Sources of funds? Will exchange disclosure be made once orders placed? Monthly run rate from Jan/Feb with 800 MW line up? FY26 and FY27 revenue guidance?

    Answer, Chetan Shah, Chairman & Managing Director. 1.5 GW building ready since two years; commercial production by Dec/Jan. 2.5 GW building under construction; equipment negotiations advanced, vendors in office today; orders to be placed 15–30 Dec. Equipment shipping challenges may push commissioning by 1–2 months beyond June 2025. Vipul Shah added project cost ₹280 Cr — ₹210 Cr debt + ₹70 Cr equity, with building/land not in cost. Chetan guided ₹800 Cr FY25 (₹650 Cr modules + ₹150 Cr EPC), ₹2,400–2,500 Cr FY26 (1.5 GW full year + 2.5 GW half year) and ₹3,400–3,600 Cr FY27 at 4 GW full run. Disclosure to exchange promised once orders placed.

  3. 3. Asset turnover and Trump/US market impact

    Isha Shah, Unknown

    Question. Asset turnover for Greenfield capex vs Brownfield 4 GW expansion? And any challenges in the US market post Trump's election given his 'Make in US' stance?

    Answer, Chetan Shah, Chairman & Managing Director. Vipul Shah: asset block currently ~₹54 Cr, adding ₹80–85 Cr for 700–800 MW line and ₹280 Cr for 2.5 GW — total asset block ~₹415–420 Cr yielding ~₹3,200 Cr module turnover at full operation. Chetan on US: dismissed Trump effect, said US targets are so large that even halving leaves massive demand-supply gap; US lacks ecosystem/supply chain, is consumer market; India best-positioned non-China supplier — saw it as net positive.

  4. 4. Anti-dumping duties and funding mix

    Pranjal Soni, Unknown

    Question. Impact of anti-dumping duty on solar glass imports from China on raw material costs? And how will further expansion be financed?

    Answer, Chetan Shah, Chairman & Managing Director. Acknowledged impact — aluminium frame AD duty imposed last month already hit prices. Glass AD investigation just initiated; long cycle before any decision. Mitigated by inserting 'change in law' clauses in all future orders to pass through any duty. On funding: mix of debt and equity, good banker relationships, multiple options on table. Vipul added discussions ongoing with a couple of investors for cell-line expansion; will disclose publicly once finalised.

    Partly answered.

  5. 5. Production run-rate, exports and main-board listing

    Kewal Shah, Unknown

    Question. Current monthly module manufacturing rate? Will it double by Dec? Export share? Geographies beyond US/Germany? Any US manufacturing plans? Main-board listing timeline?

    Answer, Chetan Shah, Chairman & Managing Director. Current ~50,000 modules/month, to scale to 1,25,000/month by Dec (75,000 new + 50,000 existing); already touched 60,000 on existing line. Exports negligible currently due to limited capacity; will ramp next year with US/Europe focus. No US manufacturing facility planned currently. Main-board listing: process underway, compliance complete, expected January 2025 — minor buffer for exchange-side approvals.

  6. 6. Revenue recognition timing and EPC mix

    Manish S, Unknown (chat)

    Question. From which month will new capacity reflect in revenue? Expected EPC share of revenue for FY25?

    Answer, Vipul Shah, Director. Second line (1.5 GW) contributing late Jan/early Feb; 2.5 GW line targeted for June, but conservative guidance assumes only six months revenue from 2.5 GW. FY25 mix: ₹650 Cr modules + ₹150 Cr EPC out of ~₹800 Cr total.

  7. 7. Solar charging station expansion

    Unnamed (chat), Unknown (chat)

    Question. Is Solex planning to expand into solar/EV charging business in a big way?

    Answer, Chetan Shah, Chairman & Managing Director. No plan to operate EV charging stations. The portfolio on website is the EPC capability showcase (utility-scale to street lighting). They build and hand over to clients as an EPC company.

  8. 8. Brand mix, EPC contribution and margin guidance

    Karan Sanwal, Unknown

    Question. OEM vs Solex brand mix for H1 FY25? Will it hold? EPC contribution in H1 FY25? Margin guidance for current year and next two years — EBITDA and PAT?

    Answer, Chetan Shah, Chairman & Managing Director. Mix shifted: H2 FY24 was 70:30 (OEM:Solex); H1 FY25 is ~50:50; H2 FY25 expected ~80:20 Solex:OEM. Mix will oscillate 50:50–60:40 depending on season. H1 FY25 actual EPC contribution ~₹32 Cr, rest ~₹240 Cr from modules. EBITDA margin guided 9–11% with year-on-year improvement; PAT margin ~5%.

  9. 9. Debt, working capital, TOPcon reliability, line fungibility, ALCM

    Aman Madrecha, Unknown

    Question. Peak debt level by end FY26 with 4 GW ramp? Working capital need for ₹1,300–1,400 Cr turnover? N-Type TOPcon reliability vs Mono PERC — degradation/UV concerns? Will TOPcon remain relevant over 2–4 years? Module line fungibility for TOPcon? India cell infrastructure status and ALCM outlook?

    Answer, Chetan Shah, Chairman & Managing Director. Vipul Shah: existing term debt ~₹60 Cr; planned ₹210 Cr debt for 4 GW expansion; total term debt ~₹300 Cr. Working capital cycle target 45 days, supported by creditors and customer advances. Chetan on TOPcon: noted initial degradation/UV concerns reported by reputed labs; Indian developers conservative — P-Type still preferred. Expected improvement in N-Type for Indian climate by early 2025. Current lines can produce TOPcon (already done with 10-busbar; upgrade to 16-busbar planned); upcoming 800 MW and 2.5 GW lines designed for back-contact/HJT also. ALCM: cell manufacturing takes 20–24 months from announcement; ~10 GW cell capacity in India; ALCM will be imposed once capacity is built up — Solex engages with MNRE on timeline.

    Partly answered.

  10. 10. EBITDA margin benchmarking, nameplate vs actual capacity, US self-sufficiency

    Mohit Arora, Unknown

    Question. EBITDA margins lower than peers — reason? Difference between nameplate and real production capacity? US moving towards self-sufficiency with 31 GW capacity vs 50 GW requirement?

    Answer, Chetan Shah, Chairman & Managing Director. Vipul Shah on margins: 9–11% is industry-appropriate and Solex achieved it in the quarter. Chetan on nameplate vs actual: nameplate is max-efficiency output without breakdown/changeover; current industry realisation 70–75% vs <50% pre-2019. Solex current production at 27 sec/module, new 800 MW at 23 sec, 2.5 GW at 14–16 sec. On US: actual demand 50 GW needs ~100 GW nameplate; US has only 10–12 GW installed and zero raw-material base — imports needed from SE Asia. Higher US manufacturing cost, no coastal routes, internal logistics expensive. India will remain long-term strategic supplier; US manufacturing viable only with sustained government support.

  11. 11. P-Type to N-Type cost variance

    Pranjal Soni, Unknown

    Question. Major cost variance in percentage terms transitioning from P-Type Mono PERC to N-Type? Will it majorly affect cost structure?

    Answer, Chetan Shah, Chairman & Managing Director. Initially there was cost difference between P-Type and N-Type but as N-Type demand grew, costs converged. Today there is practically no major cost difference between P-Type and N-Type for either developer or manufacturer.

  12. 12. US manufacturing plant

    Devansh Doshi, Unknown (chat)

    Question. Other Indian players setting up solar PV manufacturing in US — is Solex?

    Answer, Chetan Shah, Chairman & Managing Director. Vipul: detailed study done, visited US, evaluated 3–4 states with full subsidy/OpEx/CapEx planning — did not find worthwhile currently. Chetan: prefers India-based manufacturing; US policy has oscillated Obama–Trump–Biden–Trump with incentive swings; investing huge and being at mercy of subsidies is risky. Will keep watching and disclose if a sustainable US opportunity arises.

What was said

Topic by topic, in the order it was spoken

Company background and OEM positioning · Chetan Shah (CMD)

  • Solex is a 29-year-old RE company that transitioned from thermal to PV in 2007 and listed in 2018.
  • Operates as an OEM for 22 domestic and 2 international module brands, with Solex-branded sales alongside.
  • Manufacturing positioned as a 'global factory' meeting international documentation, traceability and quality standards.
  • Highest number of modules listed in ALMM compared to any Indian competitor.

Vision 2030 and capacity roadmap · Chetan Shah (CMD)

  • Vision 2030: 15 GW module + 5 GW cell manufacturing capacity with ~$1 Bn cumulative investment.
  • 4 GW module capacity targeted by June 2025; 1.5 GW building already constructed, balance 2.5 GW building under construction.
  • Cell plan: 2 GW already initiated (1 GW + 1 GW N-Type TOPcon); remaining 3 GW deferred to assess next-gen tech (back-contact, HJT).
  • Tap-R N-Type TOPcon product with rectangular G12R cells (210x182) offering 625 Wp output to launch mid-Jan to early-Feb 2025.

H1 FY25 financial performance · Chetan Shah (CMD)

  • Revenue grew 192% YoY to ₹274 Cr in H1 FY25 vs ₹93 Cr in H1 FY24; growth driven by commissioning and order-book conversion.
  • EBITDA up 167.7%, EBIT up 294%, PBT up 1,194% and PAT up ~17x; PAT margin expanded from 0.8% to 4.8%.
  • Management attributed seasonality to monsoon deferrals and stressed that H2 FY25 should be materially stronger.
  • Solectex Green Energy (EPC subsidiary) contributing rooftop, street lighting and ground-mounted solutions across industrial, commercial and residential segments.

Industry outlook and overcapacity rebuttal · Chetan Shah (CMD)

  • India's 500 GW RE target likely to be revised to 750 GW with path to 1 TW; solar to contribute >60%.
  • Current Indian nameplate capacity is 70 GW (effective ~35 GW); expected to hit 100 GW by March 2025 — not overcapacity given exports + repowering demand.
  • Electricity consumption growth has stepped up from 3% historical to 9% currently, heading to 12% — supportive of incremental demand.
  • Khavda 35 GW hybrid project cited as proof point for execution capability within India.

US/Europe export opportunity · Chetan Shah (CMD)

  • US installed capacity only 10–12 GW vs ~50 GW demand, requiring ~100 GW nameplate even at half-target — large gap for Indian exporters.
  • Europe and Africa exports already commenced last year; full push planned post 4 GW ramp.
  • Management views Trump policy uncertainty as net positive for India given US supply-chain gaps and prior China trade tensions.
  • First Indian company to achieve MCS certificate for UK/Commonwealth markets.

Closing prepared remarks · Chetan Shah (CMD)

  • Management reiterated 'baby steps then jump' expansion philosophy and long-term manufacturer identity.
  • Claimed sustainable business model resilient to industry, pricing and geographic volatility.
  • Thanked investors and reiterated commitment to conservative execution of the announced roadmap.

In their words

we have declared 15 GW of module manufacturing and 5 GW of cell manufacturing... we have declared our intention to invest almost about $1 billion in manufacturing.
Chetan Shah (CMD, Solex Energy)
PAT almost 17x higher than the previous half 1,697%... previous half was a 0.8%, and then this half is a 4.8%. So it's a phenomenal growth.
Chetan Shah (CMD, Solex Energy)
U.S. is basically inconsistent in terms of the investment in manufacturing there. So I find a little bit safer, when it comes to the investment here, more investment in India.
Chetan Shah (CMD, Solex Energy)

To check next time

What management committed to on this call, or the dates they gave.

  • Whether the 1.5 GW line commissions and lifts monthly module output toward 1,25,000 modules.
  • Whether production-line orders for the remaining 2.5 GW are placed by 15-30 December 2024.
  • Whether Tapi-R N-Type TOPcon production launches in mid-January or early-February 2025.
  • Progress toward making the full 4 GW capacity operational by June 2025.
  • FY25 revenue progress against ₹800 Cr, including ₹650 Cr from modules and ₹150 Cr from EPC.
  • H2 FY25 delivery against the stated 80% Solex brand and 20% OEM mix.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Wed 13 Nov 2024₹1,536.00−5.00%−1.36%
5 sessions Thu 21 Nov 2024₹1,525.00−5.68%−2.23%
20 sessions Thu 12 Dec 2024₹1,506.10−6.85%+2.79%

From the close of Tue 12 Nov 2024, ₹1,616.80: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Solex Energy's other calls

  • Q2 FY27Sat 14 Nov 2026Tone: Mixed
  • Q1 FY27Tue 22 Sept 2026Tone: Optimistic
  • Q1 FY27Mon 17 Aug 2026Tone: Cautious
  • Q4 FY26Mon 18 May 2026Tone: Confident
  • Q3 FY26Thu 12 Feb 2026Not read
  • Q2 FY26Mon 10 Nov 2025Tone: Confident
  • Q4 FY25Tue 27 May 2025Tone: Confident