SPML Infra Q3 FY25 earnings call

Mon 17 Feb 2025SPMLINFRA

In brief

Q3 standalone revenue fell to Rs. 201 crore and PAT rose to Rs. 10.4 crore; management targets 30-50% FY26 revenue growth.

Management's tone
Mixed
What was said
Mixed
Guidance
First guidance issued
Analyst pushback
Low
Stock, next session
+2.89% (Nifty 50 +0.13%)
  • Standalone Q3 EBITDA was Rs. 23 crore versus Rs. 5 crore last quarter, while PAT reached Rs. 10.4 crore versus Rs. 1 crore.
  • The order book was Rs. 2,500 crore, and Rs. 2,853 crore of L1 orders were expected to become profitable orders in Q4 FY25 and Q1 FY26.
  • Management set a 30-50% FY26 revenue growth target and expected revenue and profitability to improve from Q1 FY26 as new orders contribute.
  • Debt was about Rs. 460 crore, linked to arbitration awards through 2028, with receipts earmarked for repayment.
  • Management was pursuing BESS on an EPC basis and expected at least one order in FY26; possible orders were sized at Rs. 300 crore to Rs. 1,000 crore.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q3 FY25

This quarterA year agoLast quarterMargin
Revenue₹186 cr−26.2%−1.2%
EBITDA (excl. other income)₹8.1 cr—−37.0%4.3% (-1.4% a year ago)
Net profit₹9.9 cr+795.0%−23.9%5.3% (0.4% a year ago)
EPS (₹)₹1.20+421.7%−51.6%

From the company's filed results for the quarter ended 31 Dec 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Revenue: said Standalone Q3 revenue Rs. 201 crore; filed Consolidated revenue ₹186.27 cr. Management introduced the results as standalone; the filed figure is consolidated.
  • EBITDA margin: said Standalone Q3 EBITDA margin 11.5%; filed Consolidated EBITDA margin 4.3%. The standalone-versus-consolidated basis and the filed exclusion of other income make the margins non-comparable.
  • PAT: said Standalone Q3 PAT Rs. 10.4 crore; filed Net profit to owners ₹9.94 cr. Management presented standalone results, while the filed profit is consolidated and attributable to owners.
  • PAT margin: said Standalone Q3 PAT margin 5.2%; filed Net profit-to-owners margin 5.3%. Management used standalone margins; the filed margin is based on consolidated revenue and profit attributable to owners.

What moved the numbers, as management explained it

  • Revenue fell to Rs. 201 crore from Rs. 259 crore as lower market order inflows and delayed government approvals held back execution.
  • Q3 standalone EBITDA margin was 11.5% and PAT margin 5.2%; management linked future improvement to bidding only selected projects.
  • Finance cost was about Rs. 9 crore per quarter, mainly an IndAS provision rather than cash cost; GCA, mobilisation advances and some interest made it slightly higher. (accounting)
  • Management said orders run 3-3.5 years; most revenue falls in the next three years, with less at the end from touch-up, final billing and start-up. (accounting)

The numbers management led with

  • Order book (executed): Rs. 2,500 crore
  • L1 orders (pending LOA): Rs. 2,853 crore across four tenders
  • Bid pipeline: Rs. 9,000–9,518 crore of projects in tendering stage
  • Arbitration award value: Rs. 625 crore with accumulated interest; ~Rs. 800 cr expected over 4 years

Guidance

Guidance on this call

WhatForWhat management saidFiled
Revenue jumpFY26FY26 revenue growth target of 30% to 50%, depending on how quickly orders arrive.12.1%, below the range
Order book—Target order book of Rs. 5,000 crore to Rs. 7,000 crore every quarter.—
Order margin (Water orders)—Target 10% to 15% margin on new water orders.—
Net margin (Water orders)—Net margin of 8% to 10% after project-level overheads.—
Margin across tenders (Water tenders)—Target 12% to 15% margin across tenders.—
L1 orders (Water)Q4 FY25-Q1 FY26Rs. 2,853 crore of L1 orders expected to materialize into profitable orders in tranches.—
Battery energy storage system order (BESS)FY26At least one battery energy storage system order in FY26.—
NARCL loan bookFY25FY25 NARCL payment of Rs. 44 crore, leaving a loan book of about Rs. 433 crore.—
Arbitration awardFY26-FY29About Rs. 800 crore of arbitration award targeted over four years; 75% funds NARCL and 25% company cash flow.—
Vivad se Vishwas receiptsQ4 FY25Rs. 26 crore of Vivad se Vishwas receipts possible in Q4 FY25; at least Rs. 15 crore expected.—
Warrant proceedsFY25-FY27About Rs. 155 crore of warrant proceeds still to be received, staged from FY25 into FY27.—
Cash balance—Cash could reach around Rs. 450 crore if warrant and Vivad se Vishwas inflows are added.—
Bank guarantee limit—Non-fund-based bank-guarantee limit targeted at Rs. 400 crore, up from Rs. 200 crore.—
Q1 normalizationQ1 FY26Q1 FY26 expected to be normalized, with revenue and profitability better from Q1.—
Annual revenue conversion thumb rule (Water orders)—One-third of order value is expected to convert annually over three years, or 25% over four years, plus/minus 5-10%.—

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

What changed since the Tue 12 Nov 2024 call

WhatOn the Tue 12 Nov 2024 callOn this call
Revenue outlook (restated)H2 FY25 revenue similar to Q2 unless new orders; Q4 slightly higher.Q4 better than Q3 but still tight; FY26 revenue growth target of 30-50%.
L1 pipeline (raised)Rs. 1,400-1,500 crore L1 position awaiting LOI conversion, predominantly Rajasthan tenders.Rs. 2,853 crore L1 pipeline, expected to convert in Q4 FY25 and Q1 FY26.
Order-book target (restated)FY25 closing order book of Rs. 1,500-2,000 crore minimum; Rs. 2,500-3,000 crore including old orders.Current order book of Rs. 2,500 crore and a recurring Rs. 5,000-7,000 crore target.
New-order margin target (raised)Targeting 10-12% EBITDA margin on new orders.Targeting 10-15% on new orders and later citing 12-15% across tenders.
Cash and funding (restated)Rs. 280 crore FD; Rs. 460 crore expected with warrants and an arbitration tail.Rs. 270 crore cash at December-end; around Rs. 450 crore expected with warrants and Vivad se Vishwas.
Arbitration receipts (restated)Rs. 180 crore Supreme Court award expected in FY25; total Rs. 620 crore pipeline, with Rs. 430 crore to banks over five years.Rs. 625 crore award with accrued interest; about Rs. 800 crore targeted over four years.
ICRA rating and BG funding (achieved)Pursue an ICRA rating to unlock bank BG limits for larger bids.Long-term fund-based loan rated BBB-minus Stable; BG limit planned from Rs. 200 crore to Rs. 400 crore.
BESS (new)No BESS business or target was discussed.BESS pursued on an EPC basis, with at least one order expected in FY26.

The business

By business

River to reservoir

Preferred bulk water segment focused on laying large-diameter pipelines for water transport; no segment-specific Q3 FY25 revenue was disclosed.

Reservoir to tap

Second of the company's three water-supply segments; no separate Q3 FY25 performance or outlook was disclosed.

Home to rivers

Third water-supply segment discussed by management; no separate Q3 FY25 performance or outlook was disclosed.

Battery energy storage systems

SPML was exploring BESS as an EPC business alongside transformer supply; battery-container manufacturing remained a future possibility.

Possible order size Rs. 300 crore to Rs. 1,000 crore

Outlook: At least one order was expected in FY26; management planned to remain focused on EPC rather than manufacturing.

Balance sheet, capex and funding

  • Cash was about Rs. 270 crore on December 31, later described as Rs. 260 crore; management expected about Rs. 450 crore after warrant and Vivad se Vishwas inflows.
  • NARCL dues were Rs. 700 crore; Rs. 224 crore was paid last year and Rs. 44 crore was due this year, including Rs. 40 crore from a property sale.
  • Debt was about Rs. 460 crore and linked to arbitration receipts, with interest tranches payable through 2028.
  • The arbitration award was about Rs. 625 crore with accrued interest; management targeted about Rs. 800 crore over four years, split 75% to NARCL and 25% to company cash flow.
  • Outstanding warrants totalled about Rs. 155 crore; Rs. 37.5 crore was due in Q4 FY25 or Q1 FY26 and Rs. 118 crore in FY26 and possibly FY27.
  • Non-fund-based bank-guarantee limits were planned to rise from Rs. 200 crore to Rs. 400 crore; these would remain contingent liabilities rather than financial debt.

The industry, as management sees it

Water infrastructure spend underpinned by Jal Jeevan Mission (extended to 2028, Rs. 67,000 cr FY26 outlay) and large river-linking projects (Rs. 40,000 cr Rajasthan, Rs. 44,605 cr Ken-Betwa). Industry-wide Q2/Q3 slowdown from JJM renewal gap now resolving as tendering restarts. BESS opened as new vertical given 10% battery storage mandate on renewable projects.

Risks management named

  • Government tendering slowdown in Q2/Q3 due to Jal Jeevan Mission renewal gap and election-year factors
  • Q4 FY25 revenue only marginally better than Q3 — recovery pushed to Q1 FY26
  • Single-segment exposure to water infrastructure; top-line highly dependent on government ordering cycle

Q&A

Q&A was dominated by two themes: order-book visibility / FY26 growth path and balance-sheet deleveraging via arbitration awards. Analysts pressed hard on whether the Rs. 2,853 cr L1 + Rs. 9,000 cr bid pipeline actually translates into the 30–50% FY26 revenue growth — Manoj Digga stuck to the one-third-per-year thumb rule and declined to quantify L1-to-LOA conversion timing in granular terms. NARCL/finance-cost mechanics drew multiple follow-ups but were explained clearly. There was minimal pushback overall — analysts were largely seeking clarity rather than challenging management.

Not answered directly

  • BESS revenue and order timing specifics
  • Win-rate from the Rs. 9,000 cr bid pipeline
  • Exact quarter-by-quarter L1 conversion schedule

Asked for a number, answered without one

  • Win rate on Rs. 9,000 crore tenders: Management called tender conversion too forward-looking to comment on, while saying it had qualified and expected a reasonable amount from bulk orders.
  • BESS top-line contribution: Management expected at least one order in FY26 and cited possible order sizes of Rs. 300 crore to Rs. 1,000 crore, but gave no revenue contribution.
  • BESS capital expenditure: Management said the business would initially be EPC-only, with capex similar to other EPC work, but gave no capex or funding amount.
  • Q4 FY25 consolidated margin: Management only reiterated a 10% to 15% margin target on selective new orders and did not quantify a consolidated Q4 margin.
  • 12-month cash and net position: Management gave current cash and an aggregate expected cash figure, but no dated 12-month path or net-worth figure.

Every question, with its answer

  1. 1. Order book and L1 pipeline

    Kevin, Siddharth Partners

    Question. Could you repeat the L1 and pipeline numbers — order book Rs. 2,500 cr, what is the L1 value and future bid pipeline?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. L1 is Rs. 2,853 crore across four tenders. Targeted bidding pipeline is ~Rs. 9,518 crore of projects already announced with tenders to start soon.

    Follow-up. What is the cash and cash-equivalent position and net debt as on date?

    Answer. Cash balance ~Rs. 270 crore as on 31 Dec 2024. Debt is ~Rs. 460 crore, structured and to be paid in tranches from arbitration award proceeds up to 2028 — no debt servicing from operating cash. Earlier ~Rs. 470 cr figure included ~Rs. 150 cr expected warrant proceeds and ~Rs. 26 cr from Vivad se Vishwas (~Rs. 15 cr expected in Q4).

  2. 2. Warrant inflows and cash management

    Kevin, Siddharth Partners

    Question. Are the warrant and Vivad se Vishwas inflows expected in Q4?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Some Vivad se Vishwas money (Rs. 15 cr minimum, full Rs. 26 cr possible) expected from Q4 FY25. Warrants will be called from shareholders based on need; not needed immediately given Rs. 260 cr current cash and lower-margin BG availability.

    Follow-up. Is the warrant money from NARCL or who are the large investors?

    Answer. Largely from promoters. Preferential issue of ~Rs. 294 cr; ~Rs. 118 cr warrant money to come and Rs. 37.5 cr earlier promoter warrant.

  3. 3. Revenue trajectory and normalisation

    Raman K. V., Sequent Investments

    Question. Previous quarter you said we'd match FY24 revenue; with Q3 also slow, can we still match FY24 or fall short?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Government fund deployment reduced substantially this year (election etc.); Q2 and Q3 were under pressure as flagged. Q4 will be marginally better than Q3. Normalisation expected from Q1 FY26 when new-order revenue starts contributing.

    Follow-up. Can you give revenue guidance for FY26?

    Answer. FY26 revenue targeted to grow 30%–50% over FY25, contingent on L1 orders converting in Q4 / early Q1. Q4 FY25 and Q1 FY26 will be better as tenders re-start.

    Partly answered.

  4. 4. Margin guidance

    Raman K. V., Sequent Investments

    Question. Can Q4 margins improve, or will they stay at 4–5%?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Focus is bottom-line, not top-line. No excess orders in market so we bid selectively; targeting 10–15% margin on every order.

    Follow-up. Please explain NARCL repayment mechanics via arbitration awards.

    Answer. NARCL dues Rs. 700 cr; Rs. 224 cr paid last year, Rs. 44 cr this year (Rs. 40 cr from identified property sale + Rs. 4 cr from FD interest and cash flow), leaving Rs. 433 cr to be paid over next four years. Arbitration award ~Rs. 625 cr (with accumulated interest) expected in tranches — Rs. 200 cr Supreme Court-level hearing cited. Total targeted arbitration realisation ~Rs. 800 cr over 4 years, of which 75% to NARCL and 25% retained as business cash.

  5. 5. NARCL debt reconciliation

    Raman K. V., Sequent Investments

    Question. Is the Rs. 433 cr NARCL residual different from the Rs. 460 cr debt number you mentioned earlier?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Reconciled the Rs. 700 cr NARCL dues less Rs. 224 cr paid last year and Rs. 44 cr being paid this year to arrive at Rs. 433 cr residual.

    Partly answered.

  6. 6. Margin clarification

    Aditya Sen, RoboCapital

    Question. When you say 10–15% margin, is that EBITDA or PAT?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. No interest payable and no depreciation, so EBITDA effectively equals PAT. Gross margin from plant is 10–15%; net margin after overhead allocation is 8–10%.

  7. 7. Industry order delays and JJM renewal

    Prathamesh Dhiwar, Tiger Assets

    Question. What is the main reason for order delays in the water industry (called out in Q2 and now Q3)?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Jal Jeevan Mission renewal was pending — every order linked to JJM was either tendered but not allotted or not tendered at all. Now extended to 2028 and tendering has resumed. Applied for ~Rs. 2,800 cr L1 expected in March / early April; ~Rs. 9,800 cr in tendering to be awarded in Q1.

    Follow-up. What growth and orders are we looking at from the BESS segment and when do we expect orders?

    Answer. BESS tenders just started; expecting at least one order in FY26. Order sizes range Rs. 300 cr to Rs. 1,000 cr each. Water remains the bigger focus.

  8. 8. Revenue recognition pattern

    Ajinkya, Individual Investor

    Question. What is the revenue recognition timeline for orders that take 3–3.5 years to complete?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Accounting standard governs revenue recognition. Thumb rule: roughly one-third of each order is converted to revenue per year over a 3-year execution; 25% per year for 4-year orders. Cited Jharkhand ~Rs. 620 cr order example producing ~Rs. 200 cr annual revenue.

    Follow-up. Break-up of short-term and long-term debt and how you plan to finance next year's order book?

    Answer. NARCL is all long-term; Rs. 30 cr of FY25 payment shown as short-term and balance long-term linked to arbitration inflows. Working capital handled via non-fund-based BG limit being expanded from Rs. 200 cr to Rs. 400 cr — sits in contingent liability, not financial debt. No fund-based limit required.

  9. 9. Finance cost outlook

    Ajinkya, Individual Investor

    Question. Will finance cost go up in coming quarters or year?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Finance cost steady ~Rs. 9 cr per quarter — primarily IndAS adjustment on Rs. 700 cr NARCL book. No actual cash outflow for this interest. Marginal increase from GCA / mobilisation advance / operational interest.

  10. 10. Warrant structure and use of proceeds

    Raman K. V., Sequent Investments

    Question. What was the total warrant size issued to the promoter and what will the funds be used for?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Total warrant pending ~Rs. 155 cr — Rs. 37.5 cr from earlier promoter issue (Q4 / Q1 next year) and Rs. 118 cr from recent preferential offer (Rs. 80–85 cr promoter + rest public), received in FY26 / early FY27. Use: business growth only — no NARCL payment from warrants.

    Follow-up. Earlier you mentioned a battery-pack manufacturing plant — what's the status?

    Answer. Not doing battery-pack manufacturing right now; only EPC of BESS. Manufacturing is a future possibility.

    Partly answered.

  11. 11. Order book composition and bid conversion

    Raman K. V., Sequent Investments

    Question. Out of the Rs. 2,500 cr order book, what's the L1 component, and what's the win rate from the Rs. 9,000 cr bid pipeline?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Existing order book Rs. 2,500 cr; L1 Rs. 2,853 cr (four-five orders, conversion in Q4 / early Q1). ~Rs. 9,000 cr bidding pipeline with 12–15 tenders being targeted. Order conversion comment declined as forward-looking; only flagged focus on bulk-segment orders.

    Not answered directly.

  12. 12. Revenue math reconciliation

    Aditya Sen, RoboCapital

    Question. If order book is ~Rs. 5,000 cr by Q1 FY26 and 30% executes each year, that's Rs. 1,500 cr revenue — doesn't tally with 30–50% growth implying Rs. 1,000–1,150 cr.

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Confirmed thumb-rule one-third of total order book per year, ±5–10%. Reaffirmed that Q4 FY25 will be marginally better than Q3 and revenue + profitability step-up visible from Q1 FY26 onwards with new-order flows.

    Partly answered.

  13. 13. Surety bonds and warrant conversion price

    Kevin, Siddharth Partners

    Question. Some peers are using surety bonds to reduce costs — are we exploring the same? Also warrant conversion price.

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Yes, discussing with one or two insurance companies for surety bond limit. Mainly seen in road projects; only one or two water projects so far. On warrants: two tranches — Rs. 118 cr issue at one price and last preferential offer at Rs. 215 cr conversion price.

  14. 14. BESS strategy and qualification

    Mayur Gathani, OHM Portfolio Equi Research Pvt Ltd

    Question. What do you intend to do in BESS and how does the capex work?

    Answer, Manoj Digga, Director Commercials & Chief Financial Officer. Government mandated 10% battery storage in renewable energy; we are EPC-ing battery containers supplied alongside transformer. Capital expenditure follows standard EPC pattern; payments received via running bills. Future plan may include battery-pack manufacturing. Three-four BESS tenders already out; expecting at least one order next financial year. Already qualified via 40-year transformer track record — no separate qualification required.

What was said

Topic by topic, in the order it was spoken

Industry context: water crisis and policy backdrop · Manoj Digga (CFO)

  • Central water infra push underlined by NITI Aayog warning of groundwater depletion in 25 cities by 2025
  • United Nations projection of India becoming water-stressed by 2025
  • Drivers cited: erratic monsoon from global warming, urbanisation burden, inefficient supply infra

Government initiatives: Jal Jeevan Mission and river linking · Manoj Digga (CFO)

  • Jal Jeevan Mission outlay Rs. 3.6 lakh crore since 2019; extended to 2028 to hit 100% coverage
  • Rs. 67,000 crore allocated in FY26 Union Budget for water supply
  • 15 crore+ rural households (~80% rural population) now have functional tap connections
  • PM-launched Rs. 40,000 crore river-linking project in Rajasthan and Rs. 44,605 crore Ken-Betwa link in MP

SPML business model and three-segment structure · Manoj Digga (CFO)

  • Three segments: river-to-reservoir (bulk / preferred), reservoir-to-tap, home-to-river
  • River-to-reservoir bulk pipeline laying is the focus area; 45 years in water + power
  • Q3 muted due to lower quantum of orders awarded across the industry, not company-specific

Order book and bid pipeline · Manoj Digga (CFO)

  • Executed order book stands at Rs. 2,500 crore
  • L1 orders worth Rs. 2,853 crore across four tenders — expected to convert Q4 FY25 / Q1 FY26 in tranches
  • Bidding for ~Rs. 9,000–9,518 crore of projects currently in tendering stage
  • Fresh tenders expected to float on the back of new Union Budget allocation

Credit rating and global recognition · Manoj Digga (CFO)

  • ICRA assigned BBB-minus Stable to Rs. 477 cr long-term fund-based term loan
  • BBB-minus Stable also to Rs. 200 cr proposed non-fund-based limit
  • Lower bank margin expected; access to further debt for expansion
  • All-time best rank of 14 in GWI World Top 50 Private Water Companies

Q3 and 9M FY25 financial performance · Manoj Digga (CFO)

  • Q3 FY25 standalone revenue Rs. 201 cr (vs Rs. 259 cr in Q3 FY24)
  • Q3 EBITDA Rs. 23 cr (vs Rs. 5 cr in Q2); PAT Rs. 10.4 cr (vs Rs. 1 cr YoY)
  • Q3 EBITDA margin 11.5% and PAT margin 5.2% — in line with target
  • 9M FY25 revenue Rs. 622.7 cr (vs Rs. 867 cr); EBITDA Rs. 75.7 cr; PAT Rs. 37.5 cr

New vertical: BESS and renewable energy · Manoj Digga (CFO)

  • Exploring battery energy storage system (BESS) market on the back of government focus
  • Pre-qualified to participate in BESS tenders; leveraging 40-year transformer credentials
  • Current plan is EPC execution; battery-pack manufacturing only a future possibility

Closing remarks and forward outlook · Manoj Digga (CFO)

  • Headwinds expected to settle; next year should be better for all water companies
  • Five-year opportunity theme: water + irrigation + river linking + BESS
  • Bottom-line focus reiterated; targeting Rs. 5,000–7,000 crore order book level
  • Investor relations via Kapil Joshi (company) and Adfactors PR (agency)

In their words

Our arbitration award, which if we take four years, which is our targeted period, we should get roughly around Rs. 800 crore, so we are double covered in arbitration award.
Manoj Digga (Director Commercials & CFO, SPML Infra)
We will be very focused in the bottom-line and we will target to have an order book which is good, profitable and which is easy to do, complete.
Manoj Digga (Director Commercials & CFO, SPML Infra)
Our target is getting orders between 10% to 15% margin and we are still continuing with that. We are targeting only those orders where we will have a 10% to 15% margin.
Manoj Digga (Director Commercials & CFO, SPML Infra)

To check next time

What management committed to on this call, or the dates they gave.

  • Q4 FY25 revenue versus Q3: management expected improvement over Q3, but continued pressure.
  • Conversion of the Rs. 2,853 crore L1 pipeline into LOIs and profitable orders in Q4 FY25 and Q1 FY26.
  • Q4 funding: Rs. 15-26 crore of Vivad se Vishwas and Rs. 37.5 crore of promoter warrants expected by Q4 FY25 or Q1 FY26.
  • Rs. 44 crore FY25 NARCL payment, including Rs. 40 crore from the executed property sale.
  • Progress toward the Rs. 5,000-7,000 crore order-book target and the FY26 BESS order goal.
  • Arbitration award tranches, including the targeted Rs. 200 crore Supreme Court-level award.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Mon 17 Feb 2025₹173.50+2.89%+0.13%
5 sessions Fri 21 Feb 2025₹174.94+3.75%−0.58%
20 sessions Tue 18 Mar 2025₹150.44−10.78%−0.41%

From the close of Fri 14 Feb 2025, ₹168.62: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

SPML Infra's other calls

  • Q2 FY27Mon 16 Nov 2026Tone: Mixed
  • Q1 FY27Mon 17 Aug 2026Tone: Confident
  • Q4 FY26Mon 1 Jun 2026Tone: Confident
  • Q3 FY26Tue 17 Feb 2026Tone: Confident
  • Q2 FY26Fri 14 Nov 2025Tone: Confident
  • Q1 FY26Wed 20 Aug 2025Tone: Confident
  • Q4 FY25Mon 2 Jun 2025Tone: Optimistic
  • Q2 FY25Tue 12 Nov 2024Tone: Mixed
  • Q1 FY25Tue 13 Aug 2024Tone: Mixed
  • Q4 FY24Fri 31 May 2024Tone: Confident