SPML Infra Q2 FY27 earnings call
In brief
SPML Infra kept FY27 top-line and profit growth guidance at at least 25%; NTPC BESS revenue is expected from H2 on a ₹1,128 crore order.
- Management's tone
- Mixed
- What was said
- Leaned positive
- Guidance
- Guidance held
- Analyst pushback
- Medium
- Stock, next session
- −3.26% (Nifty 50 +0.58%)
- Management retained FY27 guidance of at least 25% revenue and profit growth and expects H2 revenue and profitability to exceed H1.
- Standalone Q2 revenue was ₹238.7 crore (+20%), EBITDA ₹26.3 crore (+36%; 11% margin), and PAT ₹22.2 crore (+46%); H1 PAT rose 64% to ₹45 crore.
- The NTPC BESS order received design approval; management expects H2 FY27 revenue and about ₹300 crore from the ₹1,128 crore order in FY27.
- The order book was about ₹5,056 crore; ₹1,161 crore was legacy and the balance was expected to carry 10%+ operating margins.
- H1 operating cash flow swung to ₹82.4 crore from a ₹44.1 crore outflow, while cash and equivalents rose to ₹119 crore.
An AI read of our transcription of the recording · the filing
The numbers
The quarter, Q2 FY27
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹234 cr | +24.8% | −17.6% | |
| EBITDA (excl. other income) | ₹21.3 cr | +142.4% | −20.6% | 9.1% (4.7% a year ago) |
| Net profit | ₹21.6 cr | +43.8% | — | 9.2% (8% a year ago) |
| EPS (₹) | ₹2.45 | +16.7% | −10.6% |
From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
Where management's figures differ from the filing
- EBITDA: said ₹26.3 crore, +36%; 11% margin (standalone); filed ₹21.34 crore, +142.4%; 9.1% margin (consolidated, ex other income). Management's standalone EBITDA is not directly comparable with filed consolidated EBITDA excluding other income; the value and growth rate differ materially.
What moved the numbers, as management explained it
- Management cited the approximately ₹5,056 crore order book as revenue visibility; standalone Q2 revenue rose 20% YoY to ₹238.7 crore.
- Legacy subcontracted orders carry much lower margins; as they complete and 10%+ new orders rise, Q2 EBITDA margin increased to 11% from 10%.
- Commodity and forex movements had no material effect on profitability because management bids with price-variation clauses, including the BESS contract.
- Monsoon months constrained H1 site activity, so management expects H2 revenue and profitability contribution to exceed H1.
- H1 operating cash flow turned positive at ₹82.4 crore versus a ₹44.1 crore outflow, reflecting fully funded project selection and low legacy working-capital needs.
The numbers management led with
- NTPC BESS order: ₹1,128 crore BESS order from NTPC
- Total order book: Approximately ₹5,056 crore as of September 2026
- FY27 order-inflow target: ₹5,000 crore for FY27
- H1 operating cash flow: ₹82.4 crore in H1 FY27 versus a ₹44.1 crore outflow in H1 FY26
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| FY27 top-line growth | FY27 | Formal FY27 revenue growth guidance remains at least 25%. |
| FY27 bottom-line growth | FY27 | Formal FY27 PAT growth guidance remains at least 25%. |
| FY27 order intake | FY27 | On track for ₹5,000 crore of FY27 order intake. |
| NTPC BESS project revenue | FY27 | Around ₹300 crore of NTPC project revenue is expected in FY27, starting from H2. |
| Multi-year top-line growth | — | Management expects 25% top-line growth over the next few years, with annual updates. |
| Multi-year bottom-line growth | — | Management expects 25% bottom-line growth over the next few years, with annual updates. |
| H2 contribution versus H1 | H2 FY27 | H2 revenue and profitability contribution is expected to be more than H1. |
| Operating cash flow sustainability | — | Management expects operating cash flow to remain positive in future as funded projects increase. |
| Expected operating margin on new orders | — | New orders are expected to carry operating margins of 10% or higher. |
| Additional BESS EPC order conversion | FY27 | One more BESS EPC order is targeted for conversion in FY27. |
| Potential BESS EPC order value | FY27 | The additional BESS order may be worth ₹500-1,000 crore, depending on the tender won. |
| Similar substation order conversion (Power) | Q3 FY27 | Management expects another substation order of a similar type in Q3 FY27. |
| Pune BESS manufacturing capacity | H1 FY28 | Pune BESS capacity is targeted at 5 GW by H1 FY28. |
| Container manufacturing capacity (BESS) | H1 FY28 | The 600-container manufacturing facility is targeted for completion in H1 FY28. |
| Legacy order completion | FY27-FY28 | Legacy orders are expected to be completed during FY27 and FY28. |
What changed since the Mon 17 Aug 2026 call
| What | On the Mon 17 Aug 2026 call | On this call |
|---|---|---|
| FY27 revenue growth guidance (held) | >25% YoY revenue growth for FY27 | At least 25% growth guidance remained unchanged for now |
| FY27 PAT growth guidance (held) | >25% YoY PAT growth for FY27 | At least 25% bottom-line growth guidance remained unchanged for now |
| FY27 EBITDA growth guidance (not repeated) | >25% YoY EBITDA growth for FY27 | Not mentioned |
| FY27 order intake (held) | ₹5,000 crore FY27 order intake target; ₹1,293 crore booked in Q1 | ₹5,000 crore FY27 order intake target remained on track |
| NTPC BESS approval and revenue (achieved) | ₹200-300 crore expected in Q4 FY27, subject to NTPC approval by December 2026 | Design approval received; revenue expected from H2 FY27 and around ₹300 crore in FY27 |
| BESS manufacturing and containers (held) | Expand from 2.5 GW to 5 GW with 600 container units/yr by H1 FY28 | Pune Phase 1 is operational; 5 GW capacity and a 600-container plant targeted by H1 FY28 |
| Legacy debt (cut) | ₹375 crore remaining, backed by a ₹678 crore arbitration award | ₹330 crore had been repaid; ₹370 crore remained, backed by an approximately ₹655 crore award |
| Net worth (raised) | Net worth doubled from ₹500 crore to ₹1,000+ crore | Net worth reached ₹1,185 crore at September 2026 |
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| Revenue jump | FY26 | 30–50% (on the Q3 FY25 call) | 12.1%, below the range |
| PAT growth | FY26 | 50% (on the Q4 FY25 call) | 55.8%, above the figure guided |
| Revenue growth | FY26 | 50% (on the Q4 FY25 call) | 12.1%, below the figure guided |
| FY26 revenue growth | FY26 | 25–30% (on the Q3 FY26 call) | 12.1%, below the range |
| FY26 PAT growth | FY26 | 40–50% (on the Q3 FY26 call) | 55.8%, above the range |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
Water
H1 water bidding consolidated, then tenders began picking up. SPML highlighted the 1,650 MLD Indore water project and Kolar irrigation order, while targeting funded Jal Jeevan Mission 2.0 opportunities.
1,650 MLD intake · 480 metre approach bridge
Outlook: H2 opportunities are expected in irrigation, sanitation and desalination; management will pursue quality orders in financially strong states to rebuild the water order book.
Power transmission and substation
SPML won a ₹186 crore PGCIL contract for extending the Bhadla 3 and Ramgarh substation, marking entry into the 765 kVA extra-high-voltage transmission segment.
₹186 crore contract · 765 kVA segment · Roughly 30-35% of order book from power
Outlook: Management expects similar substation orders in FY27 as the T&D segment expands, while maintaining price-variation and funding discipline.
BESS
The NTPC order received design and drawing approval; Pune Phase 1 is operational. SPML is targeting one more FY27 EPC order and building an OEM battery-pack business.
₹1,128 crore NTPC order · Around ₹300 crore expected FY27 revenue · 2.5 GW current capacity · 5 GW capacity target · 104.4 kWh battery pack · 600-container manufacturing facility · More than ₹8,000 crore of tenders participated · ₹500-1,000 crore potential next order value
Outlook: Management expects revenue to start in H2 FY27; one more EPC order is targeted for FY27, with 5 GW capacity and a 600-container plant by H1 FY28.
Balance sheet, capex and funding
- Cash and cash equivalents were ₹119 crore at September 2026, up 88% from ₹63 crore at March 2026.
- H1 operating cash flow was ₹82.4 crore versus a ₹44.1 crore outflow in H1 FY26.
- Net worth was ₹1,185 crore, supported by profit accretion and warrant conversion of about ₹700 crore of legacy obligation.
- The company had repaid ₹330 crore; ₹370 crore remained, backed by an approximately ₹655 crore arbitration award and interest.
- Arbitration claims stood at about ₹3,827 crore; two matters worth around ₹100 crore were at an advanced stage.
- Working capital: management prioritised fully funded projects; legacy subcontracted orders required no major SPML working capital.
The industry, as management sees it
Management sees sustained multi-year investment cycles in water infrastructure, transmission, distribution and BESS, supported by river linking, irrigation modernization, renewable-capacity additions and grid-expansion programs. Funding discipline and evolving BESS pricing mechanisms will influence the pace and profitability of order conversion.
Risks management named
- Order conversion timing remains uncertain as water and BESS tenders are still under evaluation
- BESS scale-up depends on successful NTPC execution, approvals, certifications and container-ramp readiness
- Contracts without price variation expose margins to commodity and foreign-exchange inflation
- Monsoon disruption constrained H1 site activity and can affect execution timing
- Legacy orders are lower-margin and must complete without working-capital or subcontractor exposure
- Large arbitration recoveries remain unrealized until awards are settled and converted into cash
Q&A
Analysts concentrated on order inflows, BESS commercialization, cash-flow durability and the credibility of FY27 guidance. Pushback was strongest around the absence of orders since NTPC and the lack of segment-level bid-pipeline detail; management defended its selective approach and maintained rather than raised guidance. The exchange was broad and orderly, with the largest information gap remaining around quantified L1 positions and the exact order-conversion timetable.
Not answered directly
- Segment-wise L1 positions and bid-evaluation quantum
- Precise O&M margin and legacy-order execution percentages
- Specific ISTS pre-qualifications and commercial or residential BESS pipeline
Asked for a number, answered without one
- L1 bids and evaluation split: Management described tender availability and expected Q3-Q4 water and power orders, but gave no L1 value, evaluation amount or split.
- O&M margin: Management said O&M is more profitable than EPC but did not state an O&M margin percentage.
- Legacy revenue recognition and margin: Management said legacy work is mainly subcontracted, carries much lower margins, requires no major working capital and has no loss risk; no percentage margin was given.
- Legacy order execution: Management said legacy orders would complete in FY27 and FY28; it did not quantify the amount already executed or short-closed.
- BESS tender success rate: Management said it expects one more order to convert in FY27, but gave no percentage success rate.
- Water share of order book: Management put power at roughly 30-35% and called the balance water, but did not state a water percentage.
Every question, with its answer
1. BESS order conversion
Arpan Gandhi, AG Capital
Question. Why has SPML not secured new orders since the NTPC BESS order despite strong bidding activity?
Answer, Management. Management said tendering in both PSU and non-PSU BESS markets remains strong, the Pune plant is operational at Phase 1, and SPML is targeting one more BESS conversion in FY27 while pursuing shorter-cycle OEM pack orders. It said the NTPC order has design-and-drawing approval, revenue should begin in H2 FY27 and approximately ₹300 crore should be recognised in FY27.
Follow-up. When does commercial production begin, and how will SPML demonstrate a moat while the Pune facility is still scaling and the BESS offering is potentially commoditized?
Answer. SPML plans to work toward 5 GWh of Pune capacity by H1 FY28. Its stated differentiation is a certified 104.4 kWh proprietary pack, domestic manufacturing, Energy Vault collaboration and full-system integration; successful NTPC execution is expected to demonstrate execution capability rather than commodity production alone.
2. FY27 growth guidance
Harshal Sharma, ASR Advisors
Question. Given H1 performance, is SPML on track to exceed its at-least-25% revenue and profit growth guidance, and will management revise that guidance?
Answer, Management. Management said the at-least-25% revenue and profit growth guidance remained unchanged for now. It expected H2 revenue and profitability to exceed H1 because monsoon months constrained site activity, and said the company could overperform, but it did not formally raise guidance.
Follow-up. How sustainable is the positive operating cash flow, and how are rising commodity prices affecting profitability?
Answer. Management attributed H1 operating cash flow to fully funded projects, timely execution and early design approvals, and expected positive operating cash flow to continue. It said price-variation clauses protect margins from commodity and foreign-exchange movements; the NTPC BESS contract also has such a clause, so recent price moves had no material margin impact.
3. Power orders and multi-year growth
Sharadha, Axis Capital
Question. How is the power-sector outlook evolving, are new power orders being won, and what growth framework applies over the next three to four years?
Answer, Management. Management said the ₹186 crore Power Grid order for Bhadla 3 and Ramgarh substations was the new power order won during the quarter and expected similar orders in the current quarter. It saw strong substation demand from PSU and non-PSU customers and a sizable BESS opportunity, while maintaining limits on fixed-price, unclear-cash-flow or sub-10% margin projects. Management still expected at least 25% top-line and bottom-line growth over the next few years, subject to annual order-book updates, and said FY27 would exceed guidance.
4. Arbitration award realization
Harshal Sharma, Ace Advisors
Question. Is there any update on the arbitration awards and their expected realization?
Answer, Management. Management said roughly ₹100 crore of arbitration awards were at a very advanced stage and that settlement was expected soon, although no firm date was provided. It said realization would materially reduce debt and improve liquidity.
Partly answered.
5. BESS capacity roadmap
Vivek Bhatt, Unknown
Question. Beyond the stated 2030 BESS-capacity ambition, will SPML continue scaling to 12.5 or 15 GWh, or expand into other businesses?
Answer, Management. Management said SPML would remain focused on water, BESS and power for the next five to seven years. It would keep expanding BESS manufacturing, with a 600-container facility planned to start next financial year, and could subsequently move toward a five-to-ten-gigawatt range depending on the order book and market conditions; no diversification beyond the three sectors was indicated.
Follow-up. Will the Pune facility be sufficient for expansion to 10 GWh or more, or will SPML need another location to reduce transportation costs?
Answer. SPML said Pune remains the sole planned manufacturing location for now. The 25-acre site has expansion potential up to 10, 15 or even 20 GWh, and management would review further locations or additions only later.
6. JJM funding and water orders
Abhishek Gupta, Tuscan Investment
Question. Given apparent underspending against the Jal Jeevan Mission budget through August-September, does management see a funding problem for JJM 2.0?
Answer, Management. Management did not view underspending as a threat to JJM 2.0, citing expedited state funding, improving liquidity, continued irrigation needs and the strategic priority of river linking. It expected substantial water and power orders while maintaining selective bidding and said obtaining ₹5,000-6,000 crore of annual orders should not be a challenge.
Follow-up. Of the approximately ₹5,000 crore order book, how much is water and how much is power?
Answer. Management estimated roughly 30-35% of the cited order book as power and the balance as water, while also saying the relevant government/JJM portion was included. The exchange remained unclear on the exact perimeter, but management maintained the ₹5,000 crore annual order target.
Partly answered.
7. Order inflows and bid pipeline
Miss Shalini, Unknown
Question. Why was Q2 order inflow so light—tender deferments, selective bidding or losses on price—and how large are current L1 positions and bids under evaluation by water, T&D and BESS?
Answer, Management. Management attributed light Q2 inflows to limited recent water tenders and monsoon-season activity, with major water schemes expected in Q3 or Q4, power tenders continuing and BESS tenders expected to carry price-adjustment provisions. It said sizable water wins would support the ₹5,000 crore FY27 target but did not provide segment-wise L1 positions or the amount under evaluation.
Follow-up. When will FY27 orders convert to revenue; what is the EPC/O&M mix and O&M margin; how are legacy orders recognized and margined; when will the ₹1,161 crore legacy order complete; is there residual VGLD or performance exposure; are JJM releases slowing; and which ISTS tenders is SPML pre-qualified for?
Answer. Management said new orders need roughly 3-6 to 6-9 months for design and drawing approvals, so FY27 orders will mostly contribute revenue in FY28. O&M is higher-margin than EPC, but no numeric O&M margin was given; legacy subcontracted orders carry lower margins with little company working capital and are expected to complete in FY27-FY28. Management said there is no residual VGLD or performance exposure and no further loss expected. JJM funding and legacy contractor dues are being cleared, while new awards have funding clarity. The company is mainly pursuing substations rather than ISTS and did not identify specific pre-qualifications.
Not answered directly.
8. BESS container manufacturing
Satyam Agrawal, Sharda Projects Limited
Question. What is the update on the BESS container manufacturing facility?
Answer, Management. Management said container manufacturing has started and the facility should be completed by H1 FY28. It may supply part of the NTPC tender, while future tenders are intended to use SPML's own containers.
Follow-up. How large is SPML's BESS tender pipeline and expected conversion rate, what order value may convert, do all contracts carry escalation clauses, and is the company targeting commercial or residential BESS?
Answer. Management said SPML has participated in more than ₹8,000 crore of BESS tenders, targets one more FY27 EPC conversion and estimates the possible order at ₹500-1,000 crore. All bids require price-escalation clauses. Commercial and residential BESS is not being pursued now because deal sizes are small; the company is prioritizing larger systems and says its facilities could serve that market later.
What was said
Topic by topic, in the order it was spoken
Call Opening and Management Introduction · Rohan Baranwal (Arihant Capital Markets)
- Rohan Baranwal welcomed participants to the Q2 and H1 FY27 earnings call hosted by Arihant Capital Markets.
- He introduced Manoj Trika, Malayanti Chakraborty and newly promoted CFO Anil Agarwal, along with Kapil Joshi and Komal Agarwal from investor relations.
- The format was management opening comments and business outlook followed by an analyst question-and-answer session.
Company Positioning and Infrastructure Opportunity · Management (SPML Infra Limited)
- Management cited continuing Indian infrastructure requirements across water, power, transmission and energy storage.
- SPML was described as having more than 40 years of operating history and over 700 completed projects.
- Management said its execution capabilities and disciplined selection process position it to participate in large, technically demanding projects.
Water Infrastructure Investment Pipeline · Management (SPML Infra Limited)
- Of 30 identified river-linking projects, Ken-Betwa was cited as the first under implementation at ₹44,605 crore, with a 2030 completion target.
- The Pradhan Mantri Krishi Sinchai Yojana was described as having a ₹93,668 crore outlay for 2021-26, with ₹6,587 crore allocated in the Union Budget 2026-27.
- The new command-area development and water-management sub-scheme has a ₹1,600 crore outlay and is accelerating modern pipe-irrigation adoption.
- The Parvati-Kashi-Chambal link project was estimated at ₹72,000 crore, with the central government bearing 90% of the cost.
- Management cited around ₹17 lakh crore of planned government investment across JJM, Amrut 2.0, Namami Ganga, river linking and related water schemes.
Power and Transmission Investment Cycle · Management (SPML Infra Limited)
- The National Electricity Plan was described as envisaging about ₹9.15 lakh crore of transmission investment by 2032 and 6.48 lakh circuit kilometers of network.
- The revamped distribution-sector scheme was cited with a ₹3.04 lakh crore outlay focused on loss reduction and smart metering.
- Green Energy Corridor Phase 3, approved in September 2026, was described as adding ₹1.36 lakh crore and supporting evacuation of up to 139 GW by FY33.
BESS Platform and OEM Strategy · Management (SPML Infra Limited)
- Management expected BESS demand to rise materially through FY32 as renewable penetration increased and grid stability became more important.
- The Pune facility was described as ready for production at Phase 1, with a working target of 5 GWh by FY28.
- The Energy Vault collaboration spans battery-pack manufacturing, system integration and project execution.
- SPML is developing an OEM business for battery packs with shorter turnaround times to create a more balanced and predictable revenue mix.
Selective Bidding and Price Protection · Management (SPML Infra Limited)
- SPML is pursuing projects with visible funding and a reasonable likelihood of timely payments.
- Management said contracts should carry price-variation clauses covering commodity, component-cost and foreign-exchange movements over multi-year execution.
- The company consciously avoids fixed-price contracts that do not adequately protect against input-cost escalation.
- It is focusing on complex, technically demanding projects where competition is more limited and visibility and margins are generally higher.
Recent Orders and Technical Credentials · Management (SPML Infra Limited)
- The NTPC Baroni BESS order was described as one of India's largest BESS orders.
- The Indore water project includes a 1,650 MLD intake, well-cum-sump and pump house with a 480-meter approach bridge.
- The Kolar irrigation assignment combines micro-irrigation with modifications to an existing canal system.
- A 765 kVA extra-high-voltage substation-extension order strengthens SPML's pre-qualification credentials for more complex transmission work.
H2 Pipeline, JJM and BESS Execution · Management (SPML Infra Limited)
- Management expects H2 opportunities in irrigation, sanitation and desalination while targeting financially strong states.
- SPML has no direct exposure to the previously mentioned Jal Jeevan Mission projects; improved payment clearance and funded JGM 2.0 awards create new opportunities.
- The ₹1,128 crore NTPC BESS order received design-and-drawing approval, with revenue expected from H2 FY27.
- SPML is bidding on both PSU and non-PSU BESS tenders and is targeting additional orders during FY27.
- The proprietary 104.4 kWh battery pack has cleared key international certifications and testing.
Order Book and FY27 Inflow Target · Management (SPML Infra Limited)
- The order book was approximately ₹5,056 crore as of September 2026.
- Only about ₹1,161 crore relates to legacy projects; the balance predominantly carries expected operating margins of 10% or higher.
- Management said it remained on track for its ₹5,000 crore FY27 order-inflow guidance.
- Water activity consolidated during H1, but management said tenders were picking up and a healthy pipeline was available for H2.
Execution Recognition and Claims Discipline · Management (SPML Infra Limited)
- SPML received the Construction World Global Awards 2026 recognition for the fastest-growing construction company in the prime segment.
- Management reiterated that resolving legacy matters and realizing value from outstanding claims remained important alongside operational growth.
H1 Performance Framing · Management (SPML Infra Limited)
- Management presented standalone Q2 and H1 FY27 revenue, EBITDA and PAT as materially stronger year on year.
- The prepared update said operating margins and PAT margins had improved.
- Net worth was reported at ₹1,185 crore as of September 2026.
- Management characterized H1 FY27 as evidence that the SPML 2.0 growth phase was translating into stronger profitability and resilience.
Cash Generation and Liquidity Turnaround · Management (SPML Infra Limited)
- H1 FY27 operating cash flow was ₹82.4 crore compared with a ₹44.1 crore outflow in H1 FY26.
- Cash and equivalents rose 88% to ₹119 crore at September 2026 from ₹63 crore at March 2026.
- Management linked the turnaround to prioritizing fully funded projects in cash-rich states and obtaining early design approvals.
- The cash improvement was presented as evidence that the new project-selection discipline was translating into cash flow.
Legacy Obligation and Arbitration Recovery · Management (SPML Infra Limited)
- Warrant conversion supported the settlement of an approximately ₹700 crore legacy obligation.
- The company had repaid ₹330 crore, with the remaining ₹370 crore backed by an arbitration award of approximately ₹655 crore plus accumulating interest.
- Management also reported arbitration claims of approximately ₹3,827 crore.
- Two high-value matters worth around ₹100 crore were described as at a very advanced stage.
- Converting the awards into cash was identified as a priority because it would directly strengthen the balance sheet.
In their words
We remain selective, pursuing projects where we have adequate visibility on funding and a reasonable likelihood of timely payments.
We bid for contracts that carry a price variation clause. Infrastructure projects executed over multi-year execution cycles during which commodity prices, component costs, and exchange rates can move significantly.
Turning this award into cash remains a priority, and it will directly strengthen our balance sheet.
To check next time
What management committed to on this call, or the dates they gave.
- Check whether H2 FY27 revenue and profitability exceed H1, as management expects.
- Track NTPC BESS revenue recognition from H2 FY27 against the approximately ₹300 crore FY27 expectation.
- Check progress toward ₹5,000 crore FY27 order intake and conversion of one additional BESS order.
- Track the 5 GW Pune capacity and 600-container facility targeted for H1 FY28.
- Check cash realization of the approximately ₹100 crore arbitration matters described as advanced and expected soon.
- Check legacy-order completion across FY27-FY28 and the resulting margin mix.
Transcript
Read along with the recording
The whole call, 197 lines from 12 speakers over 46:58. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 16 Nov 2026 | ₹147.57 | −3.26% | +0.58% |
From the close of Fri 13 Nov 2026, ₹152.54: the last close before the call, which began at 15:00 IST. Adjusted daily closes; the move includes everything else that happened in those sessions.