Rail Vikas Nigam Q4 FY26 earnings call
In brief
RVNL Q4 FY26: consolidated revenue +4.8% YoY but standalone EBITDA margin fell to 5.83%; FY27 revenue growth guided at 15-20%.
- Management's tone
- Cautious
- What was said
- Mixed
- Guidance
- First guidance issued
- Analyst pushback
- Low
- Stock, next session
- −4.66% (Nifty 50 −0.49%)
- Q4 FY26 standalone EBITDA margin fell to 5.83% from 10.36% in Q3 with PAT down 32% YoY, on INR 54 cr onerous contract and INR 35 cr SPV reconciliation.
- Order book at INR 99,262 cr as of March 31, 2026; FY26 standalone order inflow was INR 5,875 cr with JV additions of INR 1,201 cr.
- Guides FY27 revenue growth of 15-20% with margin improvement; first Vande Bharat sleeper prototype targeted for December 2026.
- Rishikesh-Karnaprayag rail project at 74% physical progress, targeting December 2029 completion; BharatNet project at 15.01% progress.
- Interim dividend of INR 208 cr paid; board recommended final dividend of INR 148.03 cr subject to shareholder approval.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q4 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹6,696 cr | +4.2% | +42.9% | |
| EBITDA (excl. other income) | ₹269 cr | −38.0% | +21.7% | 4% (6.7% a year ago) |
| Net profit | ₹187 cr | −59.3% | −42.1% | 2.8% (7.1% a year ago) |
| EPS (₹) | ₹0.90 | −59.1% | −41.9% |
From the company's filed results for the quarter ended 31 Mar 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
What moved the numbers, as management explained it
- INR 54 cr onerous contract provision and INR 35 cr SPV reconciliation adjustment cited as primary reasons for the Q4 EBITDA and PAT decline. (one-off)
- Building works revenue rose 129.50% YoY and contributed 31.40% of total operating revenue, supporting topline.
- JV and subsidiary reconciliation impact pulled down consolidated EBITDA despite higher turnover. (one-off)
- Receivables buildup from Ministry of Railways (INR 3,400 cr pending at year-end) led to lower cash and other income in FY26.
- Standalone EBITDA margin compressed to 5.83% in Q4 FY26 from 10.36% in Q3 FY26, reflecting cost and margin pressure during execution.
The numbers management led with
- Order book: INR 99,262 crore as on March 31, 2026
- BharatNet project value: INR 13,236 crore for 8,206 km OFC; 15.01% physical progress
- Rishikesh-Karnaprayag project value: INR 37,000 crore; 125 km; 74% physical progress; 96% tunnel excavation
- Vande Bharat sleeper project value: INR 14,400 crore with 35 years maintenance
- Krishnapatnam Railway Co receivable: INR 1,116 crore (INR 890 cr interest component)
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| FY27 revenue growth | FY27 | FY27 revenue growth of 15-20% |
| Bidding work margin target | — | 5-10% profit from each works of bidding |
| Vande Bharat sleeper prototype launch | FY27 | First prototype training set is targeted for launch in December 2026 |
| Rishikesh-Karnaprayag rail project completion | FY30 | Target for completion by December 2029 |
| Vande Bharat sleeper set deliveries | — | 120 sets will be supplied in five years time |
| BharatNet revenue and margin outlook | FY27 | expecting good revenue and profit margin in this year |
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| FY26 revenue | FY26 | ₹21,000–22,000 cr (on the Q2 FY26 call) | ₹20,412 cr, below the range |
| FY26 EBITDA margin | FY26 | 4–5% (on the Q2 FY26 call) | 3.7%, below the range |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
Railways
Core segment with INR 57,000 cr in order book; bidding-work execution rose 129% from INR 2,737 cr in FY25 to INR 6,283 cr in FY26, now 50% of order book with rest on nomination.
Order book ₹57,000 cr · Bidding execution ₹6,283 cr FY26 · Bidding execution ₹2,737 cr FY25 · Nomination order book ₹45,000 cr · Bidding order book ₹45,000 cr
Outlook: Selective bidding with target of 5-10% profit per work; PMC works pursued from NMDC and Visakhapatnam Port Trust
Metro
Metro projects account for INR 9,900 cr of order book; discussed in the context of diversified order book mix rather than detailed segment commentary.
Order book ₹9,900 cr
Roads, Highways and Port
Combined order book of INR 10,400 cr; company actively pursuing additional PMC assignments from PSUs and government entities.
Order book ₹10,400 cr
Outlook: Actively pursuing PMC works from NMDC, Visakhapatnam Port Trust and other PSUs/government
Power and Transmission
Order book of INR 4,000 cr; cited as part of diversification beyond core railways, alongside hydro and irrigation (INR 2,000 cr).
Order book ₹4,000 cr
BharatNet project
INR 13,236 cr BSNL-awarded project covering 8,206 km of OFC for rural broadband; only 15.01% physical progress to date but execution pace has improved.
Project value ₹13,236 cr · OFC length 8,206 km · Physical progress 15.01%
Outlook: Expecting good revenue and profit margin in FY27
Vande Bharat sleeper train sets
INR 14,400 cr project with 35-year maintenance being executed via Kinet Railway Solutions SPV; received Bronze Air Design Award 2026 in Italy; first prototype targeted December 2026.
Project value ₹14,400 cr · 35-year maintenance · Total sets 120 · First-year delivery 5 sets
Outlook: First prototype targeted December 2026; 120 sets to be delivered over 5 years with ramp-up
Balance sheet, capex and funding
- Cash flow was negative in FY26 due to receivables from Ministry of Railways; INR 3,400 cr received in April 2026 post period-end.; working_capital
- Krishnapatnam Railway Company receivable stands at INR 1,116 cr (including INR 890 cr interest); INR 290 cr repaid in FY26 with INR 50 cr dividend (RVNL share INR 25 cr).; working_capital
- No specific debt, capex, or new funding plans were stated on the call.; other
The industry, as management sees it
Management sees continued government emphasis on infrastructure development and remains confident about long-term growth. They are positioning to capture more works on nomination basis, PMC with PSUs, and selectively bid contracts targeting 5-10% margins.
Risks management named
- Margin pressure from onerous contracts and JV reconciliation adjustments in Q4
- Cash flow strain due to delayed receivables from Ministry of Railways (INR 3,400 cr)
- Krishnapatnam Railway Company outstanding of INR 1,116 cr pending recovery
- Q1 FY27 likely to remain challenging before margin recovery kicks in
- Fixed-price competitive bid exposure to commodity price fluctuation
Q&A
Only two analysts (Vishal Periwal of PL Capital and Abhishek K Leekha of Nestle Wealth) participated across 13 exchanges. Discussion was dominated by margin pressure explanation, FY27 outlook, order book composition, and receivables quality. Management was accommodative and forthcoming on margin recovery path and bidding strategy, with no aggressive pushback. The Krishnapatnam receivable and the strategic shift to selective bidding at 5-10% margin were the two most substantive disclosures beyond the standard earnings narrative.
Not answered directly
- Defense logistics corridor opportunity
Asked for a number, answered without one
- FY27 EBITDA margin level: even the margins will definitely increase. That I want to assure you. And it will be much better than this year.
- Krishnapatnam receivable recovery amount: we hope that in the coming two years time, mostly their receivables will be wiped out, and the steel will also turn profitable
- Q1 FY27 margin trajectory: the first quarter will be slightly challenging for us, but we are hopeful to achieve the targets and have a good revenue and good profit, good margins.
Every question, with its answer
1. Q4 margin pressure and FY27 outlook
Vishal Periwal, PL Capital
Question. On the margins, you clarified it is coming from one of the JV works. Is it fair to say the work has concluded and we will have better margins from Q1 FY27, or do you think 4-4.5% EBITDA margin is a new base?
Answer, Saleem Ahmad, Chairman & Managing Director. PAT looks lower this quarter, but adjusting for onerous contract of INR 54 crores and municipal taxes on new building plus INR 35 crores SPV reconciliation, PAT is slightly better than last year and last quarter. The adjustment for onerous contract has been done and we are hopeful of improving margins in Q1 FY27.
Follow-up. Receivables have increased in FY26, leading to lower cash and lower other income. Is this from a specific segment?
Answer. Cash flow is a challenge because we work for Ministry of Railways. INR 3,400 crores were recoverable from MoR which we could not get within the year but received in April. That was the reason for cash flow negative.
2. Krishnapatnam receivable recovery
Abhishek K Leekha, Nestle Wealth LLP
Question. On the receivable from Krishnapatnam Railway Company at INR 1,116 crores (INR 890 cr interest), what is the resolution timeline and how much can we realistically recover?
Answer, Mritunjay Pratap Singh, Director (Operations). Krishnapatnam gave a healthy return of INR 290 crore last year. With continued good performance, we hope their receivables will be wiped out in two years. The SPV will also turn profitable. They gave a total dividend of INR 50 crore this year of which RVNL's share is INR 25 crore.
Follow-up. What top line growth can be expected in FY27 and how should we take the margin outlook? Last concall you mentioned FY27 execution and margins would be brighter.
Answer. We are definitely expecting a good rise in revenue of around 15-20% and margins will definitely increase, much better than this year. QoQ and year-wise there will be improvement, though Q1 will be slightly challenging. We are hopeful to achieve targets.
3. Timing of FY27 margin recovery
Abhishek K Leekha, Nestle Wealth LLP
Question. Should we expect top line growth and margin growth to start from Q1 FY27 itself (June quarter onwards)?
Answer, Saleem Ahmad, Chairman & Managing Director. Yes definitely, QoQ and year-wise there will be improvement. The first quarter will be slightly challenging for us, but we are hopeful to achieve the targets and have good revenue and good margins.
4. Order book composition and bidding strategy
Vishal Periwal, PL Capital
Question. On the order book of INR 99,000+ crores, what is the breakout between nomination and competitive bidding?
Answer, Saleem Ahmad, Chairman & Managing Director. Breakup is almost 50-50 between nomination and bidding. Presently INR 45,000 cr in bidding and INR 45,000 cr on nomination basis. Business strategy is to focus on railway works already in pipeline (INR 30,000 cr), talk to PSUs and government for management works on PMC basis (NMDC, Visakhapatnam Port Trust), and limit competitive bidding to 5-10% profit per work.
Follow-up. For JVs, can you share inflows in Q4 and FY26?
Answer. In JV we got one work recently from railways, a bidding work of INR 400 crores. We expect more work in future.
5. Order inflow vs execution reconciliation
Vishal Periwal, PL Capital
Question. If I look at order inflow including JVs at INR 7,000+ cr for the year and execution of INR 20,000+ cr, with order book increasing, is the change coming from scope change?
Answer, Saleem Ahmad, Chairman & Managing Director. Order book inflow and execution match at around INR 6,000-6,300 cr. Going forward, execution from bidding works will increase tremendously. In FY25-26 bidding execution was INR 6,283 cr vs INR 2,737 cr in FY24-25, a 129% increase. Many projects also have change of scope per site and client requirements.
Follow-up. On cost inflation, nomination orders pass through but are competitive bid contracts fixed price or with escalations?
Answer. Different types of contracts. Some are fixed, some are dynamic, but in most contracts we get price variation which controls market fluctuation. Challenges will be there though.
6. Vande Bharat delivery schedule
Vishal Periwal, PL Capital
Question. On Vande Bharat order, prototype targeted December 2026, total order of 120 - by when will this conclude and what is the delivery schedule after prototype?
Answer, Mritunjay Pratap Singh, Director (Operations). Prototype will be completed this year; we'll bring two prototypes. Total Vande Bharat order to be completed in 5 years with greater increase every year. After prototype, 3-4 months needed for trials and variances. Year 1: 5 sets supplied. Thereafter ramped up, 120 sets over 5 years total.
7. Execution acceleration measures
Abhishek K Leekha, Nestle Wealth LLP
Question. What steps is the company taking for fast-track execution - automation or other measures to enhance execution capability?
Answer, Saleem Ahmad, Chairman & Managing Director. Main challenge is faster execution for good revenue and margins. Team is focused on it. Using latest technologies - pay model with 5G functions for progress tracking, drones for site inspection, software dashboards for performance tracking. Many things being done at every level from supervisory to top management.
Follow-up. Can we have a presentation showing execution readiness and exciting work the company is doing?
Answer. Thank you for the suggestion. We will definitely implement it and put it on our website so every stakeholder can go through it and provide suggestions.
8. Defense logistics opportunity
Abhishek K Leekha, Nestle Wealth LLP
Question. Has RVNL been approved to upgrade corridors specifically for defense logistics given the war scenario and railways can be used for defense logistics?
Answer, Saleem Ahmad, Chairman & Managing Director. Yes, definitely we are doing, but we will not be able to explain here. There will be many strategic projects in pipeline.
Not answered directly.
What was said
Topic by topic, in the order it was spoken
Portfolio overview and MoU rating · Saleem Ahmad (CMD)
- RVNL portfolio spans rail infrastructure, metros, roads/highways, transmission, and ports/harbors
- FY26 was a challenging year for the company but operational performance sustained and key projects executed timely
- Company achieved MoU rating of 'Very Good' for FY25 from Department of Public Enterprises
- Continued government emphasis on infrastructure development underpins long-term confidence
Order book and inflow position · Saleem Ahmad (CMD)
- Standalone order inflow Q4 FY26: INR 4,644 crores
- Standalone order inflow FY26: INR 5,875 crores
- JV order inflow FY26: INR 1,201 crores
- Total order book as on March 31, 2026: INR 99,262 crores
- Order book mix: Railways INR 57,000 cr, Signalling INR 14,900 cr, Port/Roads/Highways INR 10,400 cr, Metros INR 9,900 cr, Power/Transmission INR 4,000 cr, Hydro/Irrigation INR 2,000 cr
- Growth supported by new railway and multi-sector works, execution-driven revenue recognition, and disciplined margin-focused selective bidding
Q4 FY26 financial performance · Saleem Ahmad (CMD)
- Standalone turnover +47.6% QoQ, +4.78% YoY (Q4 FY25 vs Q4 FY26), +0.72% YoY in FY26
- Consolidated turnover +42.94% QoQ, +2.45% YoY
- Standalone EBITDA declined 16.88% QoQ and 26.74% YoY; EBITDA margin compressed from 10.36% to 5.83%
- PAT declined 19.66% QoQ and 32% YoY
- Decline driven by onerous contracts and JV reconciliation adjustments
- Building works contributed 31.40% to total revenue from operations, up 129.50% YoY
Major project progress · Saleem Ahmad (CMD)
- BharatNet project: INR 13,236 cr value, 8,206 km OFC network, 15.01% physical progress; execution momentum improved
- Rishikesh-Karnaprayag Rail Link: INR 37,000 cr, 125 km, 74% overall progress, 96% tunnel excavation, target Dec 2029
- Vande Bharat sleeper train set: INR 14,400 cr with 35-year maintenance via SPV Kinet Railway Solutions; first prototype targeted Dec 2026; SPV won Bronze Air Design Award 2026 in Italy
JV, subsidiaries, dividends and productivity · Saleem Ahmad (CMD)
- JVs/subsidiaries contributed INR 399.86 cr to consolidated revenue and INR 64.23 cr to PAT in Q4
- Additional dividend income from JVs/subs: INR 43.45 cr in Q4 and INR 47.88 cr for full year
- Interim dividend paid: INR 208 crores
- Final dividend proposed: INR 148.03 crores (subject to shareholder approval)
- Employee productivity improved from INR 21.23 cr to INR 22.46 cr reflecting better resource utilization
Strategic outlook and execution focus · Saleem Ahmad (CMD)
- Focus on efficient project delivery, margin discipline, and conversion of L1/LOA pipeline
- Actively pursuing diversified infrastructure and emerging business areas
- Strategic priorities: existing railway pipeline, PMC works with PSUs (NMDC, Visakhapatnam Port Trust), selective competitive bidding
- Confident of long-term sustainable growth and value creation
In their words
PAT looks lower in this quarter, but if we adjust for the onerous contract of INR 54 crores, and we have paid municipal taxes on new building, and we have readjusted after reconciliation of our SPV amounting to INR 35 crores, you will see that the PAT is slightly better than last year and last quarter. So definitely, now the adjustment for the onerous contract has been done, and we are hopeful that we will definitely improve our margins in the first quarter of '27 year.
We have kind of positioned ourselves like that, that we should get at least 5-10% profit from each works of bidding. So that is our target and our strategy.
The total order, Vande Bharat order book is to be completed in five years time and with a greater increase every year. The first year after prototype, we have to supply, because after supplying the prototype, it takes around three to four months time for the various trials and other work variances by the street. Thereafter, in the first year, five sets will be supplied.
To check next time
What management committed to on this call, or the dates they gave.
- Q1 FY27 EBITDA margin recovery after INR 54 cr onerous contract and INR 35 cr SPV one-offs in Q4 FY26
- Vande Bharat sleeper prototype launch progress (December 2026 target via Kinet Railway Solutions SPV)
- FY27 revenue growth against 15-20% guidance and order inflow trajectory including JVs
- BharatNet project execution pace and FY27 revenue traction (15.01% physical progress)
- Krishnapatnam Railway Company receivable recovery trajectory (INR 1,116 cr outstanding)
- Final dividend of INR 148.03 cr shareholder approval outcome and combined FY26 payout of INR 356 cr
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Tue 26 May 2026 | ₹259.75 | −4.66% | −0.49% |
| 5 sessions Tue 2 Jun 2026 | ₹240.75 | −11.64% | −2.28% |
| 20 sessions Tue 23 Jun 2026 | ₹240.13 | −11.86% | −0.86% |
From the close of Mon 25 May 2026, ₹272.45: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.