Rail Vikas Nigam Q2 FY27 earnings call

Tue 17 Nov 202616:00 ISTRVNL

In brief

RVNL's Q2 PAT rose 59.04% QoQ; FY27 guidance included 6-7% core EBITDA margin and INR 20,000-25,000 crore of work orders.

Management's tone
Mixed
What was said
Mixed
Guidance
Guidance held
Analyst pushback
Medium
Stock, next session
−3.32% (Nifty 50 −0.63%)
  • Q2 revenue from operations was INR 4,700 crore, 8.79% above Q1 FY27, while consolidated PAT rose 59.04% sequentially to INR 253.7 crore.
  • Q2 consolidated EBITDA was INR 294 crore at a 6.26% margin, versus INR 190.78 crore and 4.4% in Q1 FY27.
  • The September 30 order book was INR 90,099 crore, led by railways at INR 56,816 crore and signaling at INR 12,224 crore.
  • H1 consolidated operating cash flow was positive INR 589 crore, versus negative INR 1,250 crore in H1 FY26.
  • Management expected about INR 10,000 crore of works to be awarded in the next one or two months, including railway and NMDC orders.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY27

This quarterA year agoLast quarterMargin
Revenue₹4,701 cr−8.2%+8.8%
EBITDA (excl. other income)₹264 cr+21.7%+43.0%5.6% (4.2% a year ago)
Net profit₹249 cr+8.3%+56.5%5.3% (4.5% a year ago)
EPS (₹)₹1.20+9.1%+57.9%

From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • EBITDA excluding other income: said Consolidated EBITDA INR 294 crore; margin 6.26%; filed ₹263.98 cr; 5.6% margin, excluding other income. Management did not reconcile the quarter figures; it later said its 6-7% margin target excludes other income.

What moved the numbers, as management explained it

  • Q2 consolidated revenue from operations was INR 4,700 crore, 8.79% above Q1 FY27, which management attributed to steady execution and improved project activity.
  • Management reported sequential profitability improvement: consolidated PAT rose to INR 253.7 crore from INR 159.52 crore and EBITDA margin reached 6.26% from 4.4%.
  • H1 revenue was INR 9,022 crore, down 0.11% YoY, which management attributed to a project closure in KSA.
  • Management said Q2 execution was held back by the monsoon and geopolitical effects, while Q3 and Q4 were expected to carry maximum execution.
  • H1 subsidiaries contributed INR 6.36 crore to PAT, JV and associate profit was INR 36.59 crore, and dividend income was INR 21.34 crore.
  • Revenue per employee rose from INR 9.6 crore to INR 10.22 crore QoQ, which management linked to better efficiency and resource utilisation.

The numbers management led with

  • Total order book: INR90,099 crore as of September 30, 2026
  • Vande Bharat project: INR14,400 crore project with 35-year maintenance arrangements
  • Rishikesh-Karnaprayag Rail Project: INR37,119 crore project; 125 kilometres; 79% overall progress; about 97% of tunnel excavation completed; targeted for December 2029
  • Expected near-term awards: About INR10,000 crore over the next one or two months

Guidance

Guidance on this call

WhatForWhat management said
Top-line revenue growthFY27Opening remarks cited around 10%; Q&A targeted around 10-15% FY27 top-line growth.
Bottom lineFY27The bottom line was projected to increase by approximately 8-10% in FY27.
Core EBITDA marginFY27Management targeted a 6-7% core EBITDA margin, explicitly excluding other income.
Work ordersFY27Around INR 25,000 crore was targeted; management later restated the FY27 target as INR 20,000-25,000 crore.
Total revenue targetFY27The CMD targeted total FY27 revenue of INR 22,000 crore.
Revenue at prior-year seasonalityFY27At prior-year seasonality, FY27 revenue was expected around INR 22,500-23,000 crore.
Expected works awardsH2 FY27Works of almost INR 10,000 crore were expected to be awarded in the next one or two months.
Railway works (Railways)H2 FY27Railway works of almost INR 4,000 crore were expected to be awarded in the month.
NMDC workH2 FY27Another INR 2,500 crore NMDC award was expected in two months.
International orders (International markets)—Management expected to get a few orders soon from its international pipeline.
Vande Bharat first prototype (Railways)Q1 FY28The first Vande Bharat prototype was expected between March and June 2027.
Rishikesh-Karnaprayag completion (Railways)FY30The 125-km Rishikesh-Karnaprayag rail project was targeted for completion by December 2029.
BharatNet revenue and profit margins (Signaling and telecommunication)FY27Management expected good revenue and profit margins from BharatNet this year.
Defense EOIFY27Management expected some defense EOI to come in the market during FY27.
Execution speedH2 FY27Management's H2 priority was to pick up execution, maintain margin discipline and convert L1 positions and LOAs into active projects.

What changed since the Thu 13 Aug 2026 call

WhatOn the Thu 13 Aug 2026 callOn this call
FY27 revenue growth (cut)Around 15% YoY growth in FY27Opening target around 10%; Q&A cited 9-10% and 10-15% FY27 growth
FY27 PAT growth (cut)15-20% YoY PAT growth in FY27Opening bottom-line growth 8-10%; around 10% cited in Q&A
FY27 work-order inflow (held)INR 20,000-25,000 crore target; INR 5,500 crore receivedTarget INR 20,000-25,000 crore; H1 receipts stated as INR 7,132 crore and later INR 7,600 crore
EBITDA margin (restated)5-7% EBITDA margin over the medium term6-7% core EBITDA margin targeted for FY27, excluding other income
Railway and bidding order mix (not repeated)50:50 railway-management and bidding order mix within three yearsNot mentioned
Return on equity (not repeated)12-13% ROE over the medium termNot mentioned
Overseas bidding margins (not repeated)15-20% expected margins for overseas bidding worksNot mentioned
Dividend payout policy (not repeated)Higher of 30% of PAT or 4% of net worth per DIPAMNot mentioned

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY26 revenueFY26₹21,000–22,000 cr (on the Q2 FY26 call)₹20,412 cr, below the range
FY26 EBITDA marginFY264–5% (on the Q2 FY26 call)3.7%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Railways

Railways led the order book; the Vande Bharat prototype was targeted for March-June 2027 and Rishikesh-Karnaprayag reached 79% progress.

Order book INR 56,816 crore · Vande Bharat project INR 14,400 crore · Rishikesh-Karnaprayag project cost INR 37,119 crore · Project length 125 kilometers · Overall progress 79% · Tunnel excavation 97%

Outlook: First Vande Bharat prototype delivery by Q1 FY28; Rishikesh-Karnaprayag completion by December 2029.

Signaling and telecommunication

Signaling and telecommunication was the second-largest order-book category; BharatNet execution was progressing at a good pace.

Order book INR 12,224 crore · BharatNet project INR 13,236 crore · OSP infrastructure 82,607 kilometers

Outlook: Management expected good revenue and profit margins from BharatNet this year.

Building works

Building works contributed 33.53% of H1 operating revenue, up 11% YoY, and work on the INR 6,504 crore NMDC contract had started.

H1 revenue contribution 33.53% · Year-on-year increase 11% · Order book INR 6,504 crore · NMDC contract value INR 6,504 crore · NMDC contract value received during H1 INR 3,869 crore

Outlook: NMDC work was picking up; another INR 2,500 crore award was expected in two months.

Metros

RVNL qualified for the Israel Metro and was pursuing the opportunity with a partner.

Order book INR 5,346 crore · Israel Metro package size about INR 20,000 crore · RVNL share if awarded about INR 10,000 crore

Outlook: Management said the Israel order would not materialize in FY27 and might come next year.

Power and transmission

Power and transmission formed a INR 3,876 crore component of the September order book.

Order book INR 3,876 crore

Ports, roads and highways

Ports, roads and highways formed a INR 3,534 crore component of the order book as management cited broader infrastructure headroom.

Order book INR 3,534 crore

Outlook: Management continued to explore fresh business avenues in ports, highways and sustainable infrastructure.

Hydro and irrigation

Hydro and irrigation formed a INR 1,237 crore component of the order book.

Order book INR 1,237 crore

Outlook: Management cited considerable headroom for growth in hydro.

International markets

Works remained ongoing in Maldives, Saudi Arabia and Rwanda; RVNL qualified in Serbia and was L1 in Sierra Leone.

Serbia order opportunity INR 12,000 crore · Sierra Leone grant project around INR 220 crore

Outlook: Management expected a few orders soon and said the Serbia order would not materialize this year, maybe next year.

Balance sheet, capex and funding

  • H1 FY27 consolidated operating cash flow was positive INR 589 crore, versus negative INR 1,250 crore in H1 FY26.
  • Consolidated total liquidity was INR 10,181 crore at September 30, 2026, versus INR 9,835.36 crore at March 31, 2026.
  • Cash and cash equivalents were INR 691 crore at September 30, 2026, versus INR 556 crore at March 31, 2026.
  • RVNL said it is infusing equity with other stakeholders in multimodal logistics parks in Chennai and Bangalore.

The industry, as management sees it

Management sees government railway and infrastructure spending, logistics-cost reduction and multimodal logistics development as structural growth drivers across railways, highways, waterways and sustainable infrastructure.

Risks management named

  • Margin improvement remains a focus after H1 FY27 core margins remained modest.
  • The Vande Bharat prototype has slipped, leaving execution dependent on the March-June 2027 window.
  • FY27 growth relies on a seasonally stronger H2 after nearly flat H1 revenue.
  • International qualifications in Serbia and Israel are not yet orders and may slip beyond FY27.
  • Defense opportunities remain at the EOI stage, with details and outcomes undisclosed.

Q&A

Analysts pressed hardest on the H2 revenue bridge, order replenishment, margins, Vande Bharat timing and cash adequacy. Management generally offered directional reassurance, but revenue growth, order-inflow and annual-target figures varied across answers, while the CFO did not participate. International qualification updates were concrete, whereas liquidity adequacy and the sizing of defense and logistics opportunities were not answered.

Not answered directly

  • Liquidity adequacy and use of cash
  • Sizing of defense and strategic logistics opportunities
  • Sources of one-offs behind the quarterly margin
  • Details and certainty of the defense pipeline

Asked for a number, answered without one

  • Defense and logistics opportunity size: Management said defense was in the pipeline, expected an EOI in FY27, and described logistics opportunities in railways, highways and waterways without sizing them.

Every question, with its answer

  1. 1. International order pipeline

    Vivek Nayak, Individual Investor

    Question. What is the current status of RVNL's international port and harbour projects, why has progress stalled, and where is the pipeline now?

    Answer, Saleem Ahmad, Chairman & Managing Director. Management said work was ongoing in the Maldives, Saudi Arabia and Rwanda, with additional bidding focused on Ghana and other African countries. RVNL had qualified in Serbia and the Israel Metro and was the lowest bidder for an approximately INR220 crore grant project in Sierra Leone. Management expected some international orders soon.

  2. 2. Vande Bharat prototype delay

    Abhishek Leekha, Neste Wealth LLP

    Question. The Vande Bharat project has reportedly been delayed several times. Is the December 2026 prototype deadline final, and how confident is management that there will be no further slippage?

    Answer, Saleem Ahmad, Chairman & Managing Director. Saleem Ahmad called Vande Bharat a complex and new project for RVNL, with Russian partners experienced in rolling-stock manufacturing. Initial approval issues were resolved and manufacturing was underway at the Latur factory. He expected the first prototype in Q1 or, at the latest, Q2, implying March-June 2027, and said the broader contract timetable was expected to hold after testing.

    Follow-up. Does this mean the December 2026 deadline is maintained, followed by testing before the full contract schedule moves ahead?

    Answer. Saleem Ahmad reiterated that the first prototype was expected between March and June 2027, after which it would be fully tested.

    Partly answered.

  3. 3. Order win rate and mix

    Abhishek Leekha, Neste Wealth LLP

    Question. What is the order-win percentage, given that most orders are coming through nomination rather than competitive bidding?

    Answer, Saleem Ahmad, Chairman & Managing Director. Management said H1 inflows comprised almost INR3,800 crore from an NMDC nomination contract and about INR7,500 crore overall, resulting in a 41% nomination and 59% competitive mix. It said the competitive bid-win rate was 7-10% or slightly higher and that bidding was being pursued aggressively.

    Follow-up. The order book fell from about INR93,000 crore in Q1 to INR90,000 crore, suggesting Q2 execution was not fully replenished. What is management doing to address this?

    Answer. Management attributed the softer Q2 to the monsoon season and expected better order-book progress in the remaining quarters.

  4. 4. FY27 growth guidance

    Abhishek Leekha, Neste Wealth LLP

    Question. Are RVNL's maintained revenue and profitability growth targets still achievable for the full year given the slower Q2 execution?

    Answer, Saleem Ahmad, Chairman & Managing Director. Management maintained growth guidance of 9-10% and expressed confidence in a better Q3 and Q4, when most execution is expected. It said Q2 had been held back by the monsoon and the geopolitical situation and its effects.

    Partly answered.

  5. 5. Liquidity and long-term growth

    Abhishek Leekha, Neste Wealth LLP

    Question. Is INR500-100 crore of cash sufficient liquidity, and what is RVNL's game plan to achieve materially higher and sustained growth after revenue remained broadly unchanged over five years?

    Answer, Saleem Ahmad, Chairman & Managing Director. Saleem Ahmad redirected the question to FY27 growth of around 10-15% in revenue and about 10% in profit, citing railway and highway bidding and international opportunities. He did not directly assess whether the stated cash balance was adequate or quantify a multi-year revenue-growth plan beyond these avenues.

    Not answered directly.

  6. 6. H2 revenue growth

    Vishal Periwal, PL Capital

    Question. H1 revenue appears broadly flat year on year despite full-year growth guidance of 10%. Is management assuming a materially stronger second half to deliver that target?

    Answer, Saleem Ahmad, Chairman & Managing Director. Management agreed that H1 revenue had increased only about 1.2% year on year. It said Q3 and Q4 carry most revenue execution and reiterated the expectation of 10-15% revenue growth in the second half and for the year.

  7. 7. Margin guidance and one-offs

    Vishal Periwal, PL Capital

    Question. Were there any one-offs behind the quarter's margin improvement, and what is the expected full-year margin trajectory?

    Answer, Saleem Ahmad, Chairman & Managing Director. Management said margins would improve and targeted a 6-7% margin, while expecting a better next quarter. It did not identify whether any one-offs contributed to the quarter's performance. On clarification, management said the 6-7% target excludes other income and refers to core EBITDA or core margins.

    Follow-up. Does the 6-7% margin target include other income?

    Answer. Saleem Ahmad clarified that the target is without other income and represents core EBITDA or core margins.

    Partly answered.

  8. 8. Serbia and Israel order pipeline

    Vishal Periwal, PL Capital

    Question. Will the Serbia and Israel qualifications convert into orders this year, and what is the potential size of each opportunity?

    Answer, Saleem Ahmad, Chairman & Managing Director. Management said H1 orders were about INR7,600 crore against an annual target of INR20,000-25,000 crore. Because Serbia and Israel were only prequalified, management said the orders would not materialize in FY27 and might be awarded the following year. It expected other pipeline orders to be secured during FY27.

    Follow-up. What is the order size in Israel and Serbia separately?

    Answer. Management said Israel's eight metro packages were each about INR20,000 crore, with RVNL's potential share around INR10,000 crore. Serbia was described as an approximately INR12,000 crore project being pursued through a joint venture.

  9. 9. International JV rationalization

    Rushank Mody, Choice Institutional Equities

    Question. With the South African subsidiary closed and the Kyrgyz JV being wound up, is RVNL retreating from these markets, and which countries are now priorities?

    Answer, Mritunjay Pratap Singh and Saleem Ahmad, Director (Operations) and Chairman & Managing Director. Mritunjay Pratap Singh said existing JVs in Saudi Arabia and Uzbekistan were not being closed and that new JVs were planned in Serbia and Romania. He said Kyrgyzstan was a non-starter and South Africa was not progressing, while Ghana and other African countries remained priorities. Saleem Ahmad added that only those two subsidiaries had been closed and that RVNL was L1 for an approximately INR220 crore Sierra Leone project.

  10. 10. Defense and logistics opportunity

    Rushank Mody, Choice Institutional Equities

    Question. How large could the defense and strategic logistics opportunity be for RVNL compared with the existing business?

    Answer, Mritunjay Pratap Singh and Saleem Ahmad, Director (Operations) and Chairman & Managing Director. Mritunjay Pratap Singh said logistics investment was expanding across railways, highways and multimodal logistics parks and would create opportunities in associated roads and waterways. Saleem Ahmad said RVNL was already participating in multimodal logistics parks in Chennai and Bangalore and planned to inject equity with other stakeholders. Neither management speaker quantified the opportunity size.

    Partly answered.

  11. 11. H2 revenue bridge and awards

    Abhishek Leekha, Neste Wealth LLP

    Question. H1 revenue of INR9,022 crore was slightly below the prior year's INR9,031 crore. What quarterly revenue run rate is required to deliver 10% full-year growth, and is the target realistic?

    Answer, Saleem Ahmad and Mritunjay Pratap Singh, Chairman & Managing Director and Director (Operations). Saleem Ahmad said H1 revenue was down only 0.11% because of a KSA project closure and expected better standalone operating revenue. He set an FY27 total target of INR22,000 crore, with the maximum contribution in Q4. Mritunjay Pratap Singh said H1 normally contributes about 40% and H2 60%, implying INR22,500-23,000 crore. Saleem Ahmad added that about INR3,000 crore of NMDC work, INR4,000 crore of railway work and another INR2,500 crore of NMDC work were expected over the next one or two months.

    Partly answered.

  12. 12. Defense pipeline

    Abhishek Leekha, Neste Wealth LLP

    Question. What is the status of the defense opportunities mentioned previously, and is an expression of interest or bid expected within this financial year?

    Answer, Saleem Ahmad, Chairman & Managing Director. Saleem Ahmad said defense opportunities remained in the pipeline and that details could not be disclosed. He expected an EOI to emerge during the year, allowing RVNL to participate in bidding, and indicated that he expected this to occur within FY27.

    Partly answered.

What was said

Topic by topic, in the order it was spoken

Call Opening and Forward-Looking Notice · Nirmiti Bohra (Choice Connect)

  • Nirmiti Bohra welcomed participants to RVNL's Q2 and H1 FY27 earnings call and introduced the six-member management team.
  • She noted that forward-looking statements reflect current expectations, involve risks and uncertainties, and carry no obligation to update.

Strategic Diversification and Growth Runway · Saleem Ahmad (Chairman & Managing Director)

  • Management described diversification across transmission, roads and highways, ports and harbours, metros, solar and international markets as a resilience driver.
  • The broader infrastructure focus includes real estate, ports and hydro, highways, sustainable infrastructure and government-backed railway investment.
  • Management said the diversified mix and project pipeline support durable, long-term value creation and a sustained growth trajectory.

Q2 and H1 Profitability Momentum · Saleem Ahmad (Chairman & Managing Director)

  • Management said consolidated PAT rose about 59% sequentially and H1 profitability grew year on year, signalling stronger execution.
  • Consolidated Q2 revenue from operations was INR4,700 crore, while H1 revenue from operations reached INR9,022 crore.
  • Consolidated PBT, PAT, EPS and EBITDA improved sequentially; H1 consolidated PAT rose 13.25% year on year.
  • Standalone PAT and EBITDA also improved sequentially, following a similar trend to consolidated profitability.

FY27 Growth and Work-Order Targets · Saleem Ahmad (Chairman & Managing Director)

  • Management targeted new work orders of around INR25,000 crore during FY27, in addition to the existing order book.
  • INR7,132 crore of work orders had been received during H1 FY27, leaving most of the annual target ahead.
  • Prepared guidance called for roughly 10% top-line growth and approximately 8-10% bottom-line growth.

Order Book Scale and Composition · Saleem Ahmad (Chairman & Managing Director)

  • Total order book stood at INR90,099 crore as of September 30, 2026, with railways contributing INR56,816 crore.
  • Signaling and telecommunication accounted for INR12,224 crore, building works INR6,504 crore and metros INR5,346 crore.
  • Power and transmission contributed INR3,876 crore; ports, roads and highways INR3,534 crore; hydro INR1,237 crore; and other works INR562 crore.
  • Management attributed order-book support to new awards, steady revenue conversion and selective, margin-focused bidding.

Revenue and Profitability Execution · Saleem Ahmad (Chairman & Managing Director)

  • Q2 consolidated revenue from operations increased 8.79% sequentially to INR4,700 crore; standalone turnover was INR4,663.27 crore, up 5.5% year on year.
  • Consolidated PBT rose to INR325 crore from INR223 crore, while PAT increased to INR253.7 crore from INR159.52 crore and EPS reached INR1.20.
  • Consolidated EBITDA was INR294 crore at a 6.26% margin versus 4.4% in Q1; standalone EBITDA margin improved to 4.94% from 3.99%.
  • H1 consolidated PAT increased 13.25%, comprehensive income rose 19.28%, and standalone H1 PAT increased 14.29%.

Cash Flow and Liquidity Improvement · Saleem Ahmad (Chairman & Managing Director)

  • Consolidated operating cash flow for H1 FY27 was positive INR589 crore, compared with negative INR1,250 crore in H1 FY26.
  • Total liquidity increased to INR10,181 crore at September 30, 2026 from INR9,835.36 crore at March 31, 2026.
  • Cash and cash equivalents rose to INR691 crore from INR556 crore over the same comparison.

Margins and Workforce Productivity · Saleem Ahmad (Chairman & Managing Director)

  • Management said margins remained an important area of focus and would be tracked closely.
  • Building works contributed 33.53% of H1 FY27 revenue from operations, showing an 11% increase from the prior year.
  • Revenue from operations per employee improved sequentially from INR9.6 crore to INR10.22 crore, reflecting better resource utilization.

Major Project Execution Milestones · Saleem Ahmad (Chairman & Managing Director)

  • RVNL began work on the INR6,504 crore NMDC contract, of which INR3,869 crore was received during H1 FY27.
  • The INR13,236 crore BharatNet project covers 82,607 kilometres of OSP infrastructure under the DBOM model and was progressing at a good pace.
  • The INR14,400 crore Vande Bharat sleeper train project includes 35-year maintenance arrangements, with the first prototype targeted for Q1 2027.
  • The INR37,119 crore, 125-kilometre Rishikesh-Karnaprayag project reached 79% overall progress and about 97% tunnel excavation completion.
  • Rishikesh-Karnaprayag is targeted for completion by December 2029 and is expected to improve regional access, tourism, border connectivity and travel times.

Joint Ventures and Subsidiary Contribution · Saleem Ahmad (Chairman & Managing Director)

  • Subsidiaries contributed INR56.11 crore to consolidated revenue and INR6.36 crore to PAT during H1 FY27.
  • RVNL's share of profit from joint ventures and associates was INR36.59 crore, while dividend income was INR21.34 crore.

H2 Execution Priorities and New Opportunities · Saleem Ahmad (Chairman & Managing Director)

  • With the monsoon season behind it, management prioritized faster execution and margin discipline in H2.
  • The company intended to convert its L1 positions and LOAs into active projects.
  • Management continued to explore broader infrastructure segments, including real estate, ports, hydro, highways and sustainable infrastructure.
  • International markets and execution picking up pace in the coming quarters were presented as the main growth avenues.

In their words

Definitely, there's a delay, but I think this delay is only for the first prototype.
Mr Saleem Ahmad (Chairman & Managing Director, Rail Vikas Nigam Limited)
In total, we will do around the same INR 13,000 crore. Our total target is INR 22,000 crore, which we are targeting.
Mr Saleem Ahmad (Chairman & Managing Director, Rail Vikas Nigam Limited)
If we look at last year's trend also, the first two quarters contributed around 40% of annual revenue, and the balance 60% came in Q3 and Q4.
Mr Mritunjay Pratap Singh (Director (Operations), Rail Vikas Nigam Limited)

To check next time

What management committed to on this call, or the dates they gave.

  • Q3 FY27 revenue and PAT: management expected much better results as Q3-Q4 carry maximum execution.
  • FY27 core EBITDA margin: progress toward 6-7% excluding other income, with Q3 expected to be much better.
  • FY27 total revenue: delivery toward INR 22,500-23,000 crore if prior-year seasonality held.
  • New awards: about INR 10,000 crore within one or two months, including railway and NMDC work.
  • Vande Bharat: first prototype delivery between March and June 2027 after manufacturing began at Latur.
  • International pipeline: Serbia and Israel were not expected in FY27 and may be won next year.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Wed 18 Nov 2026₹189.00−3.32%−0.63%

From the close of Tue 17 Nov 2026, ₹195.50: the call began at 16:00 IST, after the market closed, so that day's close is the base. Adjusted daily closes; the move includes everything else that happened in those sessions.

Rail Vikas Nigam's other calls