Rail Vikas Nigam Q1 FY26 earnings call

Tue 12 Aug 2025RVNL

In brief

RVNL Q1 revenue -3.4% YoY but cumulative ahead of last year; order book Rs. 1,01,000 cr; Vande Bharat first prototype by June 2026.

Management's tone
Mixed
What was said
Even-handed
Guidance
None given
Analyst pushback
Low
Stock, next session
−3.81% (Nifty 50 −0.40%)
  • Q1 revenue fell 3.4% YoY but RVNL is already ahead of last year cumulatively as bidding turnover tripled.
  • Order book at Rs. 1,01,000 cr with Rs. 1,000 cr added this quarter; civil Rs. 26,000 cr, electrical Rs. 10,900 cr, signalling/telecom Rs. 14,700 cr.
  • Net margin dip from Rs. 60 cr one-offs: Rs. 20 cr BharatNet pre-bid and Rs. 40 cr provision for 3 new onerous contracts.
  • Vande Bharat first prototype by June 2026, with revenue from 6-8 trains expected in FY27; total 120 train sets by 2032.
  • International order book at Rs. 4,000 cr; targeting Rs. 30,000-35,000 cr of overseas bids this year at 15-20% strike rate.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q1 FY26

This quarterA year agoLast quarterMargin
Revenue₹3,909 cr−4.1%−39.2%
EBITDA (excl. other income)₹52.9 cr−70.9%−87.8%1.4% (4.5% a year ago)
Net profit₹135 cr−39.9%−70.7%3.4% (5.5% a year ago)
EPS (₹)₹0.65−39.3%−70.5%

From the company's filed results for the quarter ended 30 Jun 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • Turnover mix shifted: railway work fell ~25% YoY while bidding turnover tripled; bidding share is now structurally larger.
  • Gross margin dipped 13.57% as lower-margin bidding projects (entered revenue recognition) replaced higher-margin railway work.
  • Rs. 20 cr one-off pre-bid consultancy expense booked for BharatNet project in indirect expenditure. (one-off)
  • Rs. 40 cr provision for three new onerous bidding contracts recognised this quarter, dragging PBT and PAT. (one-off)

The numbers management led with

  • Total order book: Rs 1,01,000 crores (Rs 60,500 cr bidding + Rs 41,000 cr legacy railway)
  • Vande Bharat RVNL JV share: Rs 8,640 crores capital cost
  • Total Q1 one-off PAT impact: Rs 60 crores (BharatNet + onerous contracts)
  • Vande Bharat revenue contribution target: 6-8 train sets in FY26-27, 120 by 2032

Guidance

Guidance on this call

WhatForWhat management said
Consolidated revenueFY26We will be exceeding the last year's revenue.
Vande Bharat train revenue (Vande Bharat Train Manufacturing)FY27we can expect revenue of at least 6-8 Vande Bharat trains
International bidding pipeline (International & JVs)FY26We are expecting to bid almost Rs. 30,000-Rs. 35,000 crores of projects this year only overseas

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY25 turnoverFY25₹23,000 cr (on the Q4 FY24 call)₹19,923 cr, below the figure guided

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Civil Engineering

Order book Rs. 26,000 cr spread across railways, highways, metros and irrigation; metro Rs. 10,000 cr, highway Rs. 9,000 cr, civil/irrigation Rs. 7,000 cr.

Order book Rs. 26,000 cr · Metro Rs. 10,000 cr · Highway Rs. 9,000 cr · Civil/irrigation Rs. 7,000 cr

Outlook: Bidding turnover up 3x; mix shifting from legacy railway work to bidding projects.

Electrical

Order book Rs. 10,900 cr across overhead electrification (2x25 kV conversion), RDSS distribution and transmission line projects.

Order book Rs. 10,900 cr

Signalling & Telecom

Order book Rs. 14,700 cr including automatic signalling, modernization and BharatNet (Rs. 6,800 cr capital, Rs. 13,000 cr over 10 years including O&M).

Order book Rs. 14,700 cr · BharatNet capital cost Rs. 6,800 cr · BharatNet total over 10 years Rs. 13,000 cr

Outlook: Margins to improve once bidding work starts in full swing; change-of-scope claims pending sanction.

Vande Bharat Train Manufacturing

120 train sets order with RVNL's share Rs. 8,640 cr in JV; production started at Latur factory in advance designing stage.

120 train sets · RVNL's share Rs. 8,640 cr

Outlook: First prototype by June 2026 (delayed 10 months); 6-8 trains revenue expected in FY27; full delivery by 2032.

International & JVs

Order book Rs. 4,000 cr; solar pipeline ~800 MW across Uzbekistan, Saudi Arabia, Armenia, Romania; MoUs in nuclear (Rosatom) and rolling stock maintenance.

International order book Rs. 4,000 cr · Solar pipeline ~800 MW

Outlook: Targeting Rs. 30,000-35,000 cr of overseas bids in FY26 at 15-20% strike rate; SPRCL and 2 SPVs have already declared dividends.

Risks management named

  • Margin compression as newly-awarded bidding projects are in early execution with structurally lower margins
  • Three onerous contracts recognized in Q1 with potential end-of-project losses flagged by CFO
  • 10-month Vande Bharat delay from configuration changes; railways extended timeline accordingly
  • Vande Bharat margin profile not quantified; CEO said 'nothing extraordinary' on either side

Q&A

Q&A was dominated by Antique Stock Broking (Vishal Periwal) with focused follow-ups from MoneyOre (Rajesh Agarwal). Discussion centred on order book composition, the soft Q1 margin print (with management attributing Rs 60 cr of PAT impact to clearly-explained one-offs), Vande Bharat timing — including a candid admission of a 10-month prototype slip — and international expansion plans. Management was not pressed hard on margin sustainability or Vande Bharat economics; pushback intensity was low and the friendly tone produced broad disclosure but limited analytical challenge.

Not answered directly

  • Vande Bharat margin profile (CEO declined to give a number, said tracking as planned with nothing extraordinary)

Asked for a number, answered without one

  • Vande Bharat margin: Management said "Nothing extraordinary, neither on positive side nor on negative side"; cost built on existing ICF supply chain.

Every question, with its answer

  1. 1. Order inflows and order book

    Vishal Periwal, Antique Stock Broking

    Question. Can you share order inflows last quarter and how the order book has closed? Any update would help.

    Answer, M. P. Singh, Director Operations. Q1 inflows from civil and electrical engineering aggregated ~Rs 1,000 cr. Total contracts stood at 96. Residual order book from open bidding is ~Rs 60,500 cr, plus legacy railway projects of ~Rs 41,000 cr, giving a combined order book of ~Rs 1,01,000 cr.

    Follow-up. Can you provide a sector-wise split of this order book?

    Answer. Civil (railways, highways, metros) ~Rs 26,000 cr; electrical ~Rs 10,900 cr; signalling and telecom ~Rs 14,700 cr. Within civil — metros Rs 10,000 cr, highways Rs 9,000 cr, traditional railways/irrigation Rs 7,000 cr. BharatNet capital cost ~Rs 6,800 cr and Rs 13,000 cr including 10-year O&M. Vande Bharat RVNL JV share is Rs 8,640 cr.

  2. 2. Revenue growth outlook

    Vishal Periwal, Antique Stock Broking

    Question. At end of FY25, FY26 revenue growth was hinted at ~10%. Given a muted Q1 across the industry, how do you see full-year growth panning out?

    Answer, Pradeep Gaur, Chairman and Managing Director. Situation in control. Railway share of turnover is down ~25% but bidding-project turnover has grown ~3x, providing offset. As of today we are already ahead of last year's run-rate. The full year will not only match FY25 but exceed it.

  3. 3. Q1 margin pressure

    Vishal Periwal, Antique Stock Broking

    Question. Q1 saw margin pressure with other expenses and other line items up. Is that because lower-margin competitive-bid projects are now entering revenue recognition?

    Answer, M. P. Singh, Director Operations. Gross margin dipped ~13.57% because MoR-sourced income fell while bidding-project income rose ~67%. Net margin compression also reflects Rs 60 cr of one-offs: Rs 20 cr of BharatNet pre-bid consultancy expense and Rs 40 cr of onerous-contract cost provisions, which together hit PBT and PAT.

    Follow-up. What was the nature of the Rs 60 cr?

    Answer. Chandan Verma clarified: BharatNet pre-bid consultancy is a one-time indirect expenditure. A few newly-awarded bidding projects recognized this quarter turned onerous as expenditure started getting booked on a spread basis; value additions via change-of-scope are expected to improve the picture in due course.

  4. 4. BharatNet one-off expense

    Rajesh Agarwal, MoneyOre

    Question. On the BharatNet order, how much of extra expense have you booked without commensurate revenue?

    Answer, Chandan Kumar Verma, Chief Financial Officer. Approximately Rs 20 cr on BharatNet pre-bid consultancy work.

    Follow-up. Any other one-off expenses?

    Answer. M. P. Singh: No other one-offs.

  5. 5. Q2 revenue trajectory

    Rajesh Agarwal, MoneyOre

    Question. Do you feel the revenue mix will start improving from Q2?

    Answer, M. P. Singh, Director Operations. Yes, shoots are already visible. By end of Q2 cumulatively we expect to match last year's revenue. Pradeep Gaur added that RVNL is already ahead of last year in absolute revenue terms and will exceed FY25.

    Follow-up. What about margins?

    Answer. Chandan Verma: Bidding-project booking has just started, so it is too early to call. Margins will improve as work scales and pending change-of-scope claims are sanctioned by the client.

    Partly answered.

  6. 6. JV profitability and dividends

    Rajesh Agarwal, MoneyOre

    Question. When will profitability from railway JVs (like Kutch railway) start flowing in?

    Answer, Chandan Kumar Verma, Chief Financial Officer. Krishnapatnam JV turned profitable for the first time this year. SPRCL has already paid a dividend and two other SPVs have also paid dividends this year. With traffic improvement and lower capital-service costs, more dividends are expected.

    Follow-up. Is the Vande Bharat project on schedule now?

    Answer. M. P. Singh: All roadblocks cleared; in advanced design stage; production started at Latur; first prototype by June 2026. Pradeep Gaur added that the 10-month delay stemmed from configuration changes, and railways correspondingly extended the timeline.

  7. 7. Vande Bharat revenue timeline

    Vishal Periwal, Antique Stock Broking

    Question. After the June 2026 prototype, what is the path to commercial rollout and when does revenue start recognising?

    Answer, M. P. Singh, Director Operations. Under the contract, 90% of the train-set cost is released on prototype production and successful trial balance; 10% thereafter. After trials and clearance, regular production starts. In FY26-27 we expect prototype plus regular production train sets. CEO added trials typically take 60 days, design is ICF-based (sleeper variant), and spares for 10 train sets are already on order — so FY26-27 should see 6-8 Vande Bharat train sets in revenue.

    Follow-up. When does the 120-train-set order conclude?

    Answer. Pradeep Gaur: 2032, spread over 5 years. Original September 2025 prototype target slipped by 10 months due to configuration issues.

  8. 8. Vande Bharat pipeline beyond 200 sets

    Vishal Periwal, Antique Stock Broking

    Question. Total Vande Bharat opportunity has been talked about as 500-1,000 train sets. Any new tenders coming or is the pipeline capped at 200?

    Answer, Pradeep Gaur, Chairman and Managing Director. No tenders are presently in the pipeline. The 200 train sets is what is on the table. M. P. Singh added that ICF and RCF will continue producing their own train sets in parallel.

    Follow-up. The 80-train-set award is mapped to which consortium and factory?

    Answer. M. P. Singh: BHEL and Titagarh Wagons consortium. They will manufacture at their own facility on the ICF platform, parallel to RVNL's Latur production. Pradeep Gaur noted both will manufacture on the ICF platform, with RVNL at Latur.

  9. 9. JV and MoU traction

    Vishal Periwal, Antique Stock Broking

    Question. On the MoUs and JVs — any business traction visible, or are they still at preliminary stage?

    Answer, M. P. Singh, Director Operations. Good potential visible. Maintenance of rolling stock and engines — Indian Railways has bid out electrical-engine maintenance at two workshops; MoUs already signed with two firms, expecting to compete. Nuclear — MoU with Rosatom, proposal submitted to Ministry of Railways. Solar — Uzbekistan and Saudi Arabia successes, now bidding in Armenia and Romania. CEO added the solar pipeline is ~800 MW and the partnership is expanding into Europe.

    Follow-up. What is the international share of the Rs 1 lakh cr order book?

    Answer. M. P. Singh: ~Rs 4,000 cr. Pradeep Gaur: Already bid ~Rs 10,000 cr overseas this year with Rs 6,000 cr more in pipeline; targeting Rs 30,000-35,000 cr of bids this year overseas, expecting 15-20% strike rate to materially expand the international book.

  10. 10. Vande Bharat margin profile

    Vishal Periwal, Antique Stock Broking

    Question. Vande Bharat is still pre-commercial. What kind of margin profile do you see — single-digit, high single-digit, low double-digit?

    Answer, Pradeep Gaur, Chairman and Managing Director. Costs were bid based on internal working. Supply chain is largely the established one RVNL already supplies to ICF, with one or two foreign items that had sanction-related issues now resolved. Nothing extraordinary on margins either positive or negative — tracking as planned.

    Not answered directly.

What was said

In their words

So, roughly, the order book of RVNL is Rs. 1,01,000 crores, which is unlimited.
M. P. Singh (Director Operations, Rail Vikas Nigam Limited)
absolutely no issue. We will be exceeding the last year's revenue.
Pradeep Gaur (Chairman and Managing Director, Rail Vikas Nigam Limited)
So, roughly, the order book of RVNL is Rs. 1,01,000 crores
M. P. Singh (Director Operations, Rail Vikas Nigam Limited)

To check next time

What management committed to on this call, or the dates they gave.

  • Vande Bharat first prototype by June 2026; trial 60 days, then regular production from FY27.
  • Q2 FY26 revenue: management expects cumulative to match or exceed last year.
  • Margin recovery as bidding projects ramp up and change-of-scope claims get sanctioned.
  • International order inflow from Rs. 30,000-35,000 cr FY26 bid target at 15-20% strike rate.
  • BharatNet revenue recognition and whether Rs. 60 cr one-offs repeat in Q2.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Tue 12 Aug 2025₹329.45−3.81%−0.40%
5 sessions Tue 19 Aug 2025₹327.75−4.31%+1.61%
20 sessions Wed 10 Sept 2025₹333.45−2.64%+1.58%

From the close of Mon 11 Aug 2025, ₹342.50: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.