Vikram Solar Q3 FY26 earnings call
In brief
Vikram Solar Q3 PAT up over 5x to ₹98 cr on 9.5 GW module base; Gangaikondan cell line on track for Dec 2026
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- First guidance issued
- Analyst pushback
- Low
- Stock, next session
- −9.70% (Nifty 50 −1.38%)
- Q3 FY26 PAT jumped to ₹98 cr from ₹19 cr YoY, with EBITDA of ₹205 cr at 18.5% margin (vs ₹85 cr, 8%) on 796 MW volume (vs 590 MW).
- Commissioned the 5 GW Vallam module facility in Tamil Nadu, taking total installed module capacity to 9.5 GW and completing transition to a full N-type/TOPCon portfolio.
- Order book stood at 10.58 GW, up 28% YoY, with mix IPP 55%, C&I 21%, government+EPC 11%, distribution 13%; exports 16%.
- Gangaikondan 6 GW module + 12 GW cell project on track: module plant commissioning Q1 FY27, first cell out December 2026 from Thailand-shifted line.
- Entered BESS with ₹4,300 cr capex: 5 GWh battery pack to commission in FY27, 7.5 GWh integrated cell+pack to follow; ₹10,000 cr total capex over 24-30 months.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q3 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹1,106 cr | — | −0.4% | |
| EBITDA (excl. other income) | ₹199 cr | — | −15.2% | 18% |
| Net profit | ₹98 cr | — | — | 8.9% |
| EPS (₹) | ₹2.71 | — | −29.2% |
From the company's filed results for the quarter ended 31 Dec 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
What moved the numbers, as management explained it
- Volume growth: Q3 sales 796 MW vs 590 MW YoY; 9M 2.3 GW vs 1.1 GW YoY, driving operating leverage and 18.5% Q3 / 20.3% 9M EBITDA margin.
- Mix shift: Q3 FY26 was 100% non-DCR execution vs Q3 FY25 which included a DCR utility-scale contract, lowering blended realization; ~30% of Q3 execution was lower-margin government contracts.
- Cost discipline: higher throughput, automation at Vallam, tighter indirect cost; weighted average finance cost down to 6.5% (9MFY26) from 7% (H1 FY26).
- Realization pressure: Non-DCR module prices dropped 30-40% YoY due to soft market; partial offset from 88% cell cost pass-through on order book.
- Accounting: management's reported Q3 EBITDA of ₹205 cr appears to include other income (₹20.23 cr) whereas filed 'EBITDA excluding other income' is ₹199.28 cr at 18.0% margin. (accounting)
- One-off: 5 GW Vallam line commissioned during the quarter; lease accounting of ~₹400 cr at 8.5% adds ~₹108 cr/year in lease+interest charge over 5 years, slightly weighing on finance cost optics. (one-off)
The numbers management led with
- Total module capacity post-Vallam commissioning: 9.5 GW (fully TOPCon)
- Order book position: 10.58 GW as of 9M FY26 (up 28% YoY from 8.2 GW)
- 9MFY26 sales volume: 2.3 GW (vs 1.1 GW in 9MFY25); surpassed full FY25 by 23%
- Gangaikondan project scope: 6 GW module + 12 GW cell integrated facility; module plant commissioning Q1 FY27, first cell-out Dec 2026
- BESS entry scope: 5 GWh battery pack in FY27 + 7.5 GWh integrated cell+pack facility; total capex INR4,300 cr
- Total capex commitment (module+cell+BESS): INR10,700 cr over 24-30 months; equity INR2,400 cr from internal accruals, debt INR6,600 cr, IPO proceeds INR1,500 cr
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| Non-DCR EBITDA margin sustained (Solar modules (Non-DCR)) | — | Non-DCR business to deliver 18% to 20% EBITDA margin on a sustained basis |
| Non-DCR realization (Solar modules (Non-DCR)) | — | Non-DCR realization expected at ₹14 to ₹14.5 per watt peak |
| DCR realization (Solar modules (DCR)) | — | DCR module price to remain at ₹23-24 per watt peak (unchanged) |
| Gangaikondan module plant commissioning (Solar modules (Gangaikondan)) | Q1 FY27 | Module plant on track for commissioning in Q1 FY27 |
| Gangaikondan first cell out (Solar cells (Gangaikondan)) | Q3 FY27 | First cell out expected by December 2026 |
| BESS capex | FY28 | BESS capex of ₹4,300 cr to be deployed over next 30 months |
| BESS 5 GWh battery pack commissioning | FY27 | 5 GWh battery pack facility to be commissioned in fiscal 2027 |
| BESS integrated cell + battery pack | — | 7.5 GWh integrated cell + battery pack facility planned |
| Order book cover | FY27 | Target order book of 1.2x-1.3x scheduled deliveries for the next four quarters (rolling) |
| Utility DCR demand (industry view) (Solar modules (DCR, industry)) | FY28 | Industry utility-scale DCR demand of 30-35+ GW expected in FY28 |
| Gangaikondan total capex (Solar cells + modules (Gangaikondan)) | FY28 | Overall Gangaikondan (6 GW module + 12 GW cell) capex of ₹6,400 cr; debt ₹3,800 cr, balance equity |
The business
By business
Solar modules
Core business; total installed module capacity raised to 9.5 GW after 5 GW Vallam commissioning; launched Hypersol Pro (N-type, 23.7% efficiency, 640 Wp); entire portfolio now TOPCon.
Q3 FY26 sales volume 796 MW · 9MFY26 sales volume 2.3 GW · Total module capacity 9.5 GW · Q3 capacity utilization 90% · 9M capacity utilization 88%
Outlook: Non-DCR realization ₹14-14.5/Wp; Non-DCR EBITDA sustained at 18-20%; DCR realization held at ₹23-24/Wp; full N-type/TOPCon focus going forward.
Solar cells (Gangaikondan)
Under construction: 12 GW cell + 6 GW module integrated project; statutory approvals and core site infrastructure complete; cell line being shifted from Thailand.
12 GW cell + 6 GW module planned · Capex ₹6,400 cr (debt ₹3,800 cr, equity ~₹2,600 cr) · First cell out Dec 2026 · Module plant commissioning Q1 FY27
Outlook: Thailand line capable of M10R and G12R cells; shifting exercise starts April-May; cell line to provide 1-year cost bridge before own cell availability.
BESS
New vertical announced; battery pack unit first, integrated cell+pack to follow; technology partnership in advanced stages.
BESS capex ₹4,300 cr · Debt-equity 65:35 (debt ~₹2,800 cr) · Phase 1: 5 GWh battery pack · Phase 2: 7.5 GWh integrated (incl. 2.5 GWh additional assembly)
Outlook: Phase 1 (5 GWh battery pack) to commission in FY27; financial closure underway; capex funded over next 30 months from internal accruals.
Balance sheet, capex and funding
- 9MFY26 capex spent: ~₹300 cr; Q4 FY26 capex planned at ₹1,000-1,200 cr; total ₹10,000 cr capex over 24-30 months.
- Gangaikondan (6 GW module + 12 GW cell): ₹6,400 cr; debt ₹3,800 cr; equity ~₹2,600 cr (₹1,500 cr from IPO, balance from internal accruals).
- BESS: ₹4,300 cr; debt-equity 65:35 (~₹2,800 cr debt, ~₹1,500 cr equity/internal accruals) over 30 months.
- Vallam 5 GW line on lease: ₹400 cr debt at 8.5% for 5 years; ~₹108 cr/year including interest.
- Weighted average finance cost on debt: 6.5% in 9MFY26 vs 7% in H1 FY26, supported by reset in declining rate environment.
- India Ratings upgraded long-term facility rating to Ind A+ (stable) from Ind A, and short-term to Ind A1+ from Ind A1; BloombergNEF Tier 1 for 8th consecutive quarter.
The industry, as management sees it
Management views India's solar sector as structurally robust, expected to become the second-largest solar market globally in 2026 with 50+ GW additions, supported by RCO framework formalisation, MNRE's efficiency threshold hike (20% to 21.5% by FY28), and the impending ALMM List II/III regime. Removal of China's 9% VAT export rebate is seen as constructive, expected to moderate state-supported pricing distortions and level the playing field. However, short-term supply chain realignment — polysilicon production controls, surging silver prices, and pending DGTR anti-dumping outcome (90-day window lapsed on 29 Dec 2025) — creates a tightening input cost environment that will require cost discipline to navigate.
Risks management named
- Silver cost pressure on N-type cell economics; mitigation via LECO, copper-paste alternatives
- Chinese supply chain shifts including 9% VAT export rebate removal from April 2026 raise raw material costs
- Pending outcome of DGTR anti-dumping recommendation (23-30%) on Chinese cell imports
- Forex volatility on imported cells and polysilicon; managed via 30:70 forward hedging policy
- Q3 EBITDA margin moderated vs Q2 due to non-DCR realization drop of 30-40% and mix shift
Q&A
Q&A was broad and balanced, covering 12 analysts across 8 brokerages. The most probed topics were the cell pass-through mechanism, China VAT export rebate impact, capacity expansion execution (Gangaikondan + Thailand cell line), and the new BESS foray with its INR4,300 cr capex. Management was consistently direct with specific numbers (INR14-14.5/Wp non-DCR realization, INR23-24/Wp DCR, 18-20% sustained non-DCR EBITDA margin, INR6,400 cr + INR4,300 cr capex split). There was no notable deflection, and the few evasive moments were around competitive pricing — management dismissed pricing pressure as confined to legacy Mono PERC players rather than the TOPCon quality tier.
Asked for a number, answered without one
- Order inflow target for FY27: Management described a rolling target of 1.2x-1.3x of scheduled deliveries for the next 4 quarters, not a discrete FY27 number.
- Capex split across FY26/FY27/FY28: Management only said total capex to be spent over 24-30 months and equity of ~₹2,400 cr from internal accruals; no annual split provided.
Every question, with its answer
1. Raw material pass-through and realizations
Ketan Jain, Avendus
Question. On the raw material pass-through claim: are all inputs (cells, aluminum racks, forex) pass-through? How does the payment mechanism work — does the client pay the difference in raw material cost at ordering vs delivery?
Answer, Ranjan Jindal, Chief Financial Officer. Most transactions are with large utilities and are LC-backed. Pass-through applies to the cell price only (not BORM), and 88% of the order book has this benefit. The balance 12% is being renegotiated with customers. Change-in-law triggers can also be repriced. Cell-cost increase from China VAT removal or silver price rise is fully pass-through. Going forward, Non-DCR EBITDA margin guided at 18-20% sustained, with Non-DCR realization at INR14-14.5/Wp and DCR at INR23-24/Wp. DCR pricing will not move on the cell cost change — developers absorb it.
Follow-up. So at the time of delivery, the client pays a revised price based on revised raw material cost?
Answer. Exactly.
2. Module technology mix
Shivam Patel, PL Capital
Question. Can you split the current 9.5 GW capacity into TOPCon vs Mono PERC?
Answer, Ranjan Jindal, Chief Financial Officer. The entire 9.5 GW is TOPCon. All additions going forward, including the 6 GW, will be TOPCon.
3. Realization drop and capacity plan revision
Sahil Sheth, Anand Rathi
Question. There has been a 20% YoY drop in realization and a steep sequential drop. Comments? And previous guidance for total module capacity was 17.5 GW but now 15.5 GW — has the 2 GW Falta expansion been cancelled?
Answer, Rinal Shah, Investor Relations. On realization: Q3 had 100% non-DCR execution, vs Q3 last year which had a DCR utility-scale contract that lifted blended realization. The 30-40% drop in non-DCR realizations is the main driver. On capacity: the 2 GW Falta expansion has not been cancelled; the 15.5 GW figure is retained for now to ensure 75% backward integration with the 12 GW cell plan. The Falta decision will be revisited once ALMM-II cells become mandatory.
Follow-up. Any viable technology substitute to reduce silver consumption on the cell front, or still under R&D?
Answer. LECO is a short-term viable option as it narrows finger footprint and reduces metallization. Longer term, copper electroplating with nickel barrier and silver-coated copper paste on rear side are being considered; Jinko and AIKO have run successful commercial tests.
4. Order book trend and cell sourcing diversification
Harshit Patel, Equirus Securities
Question. Order book reduced Q-on-Q from Q2 to Q3 — was this due to industry slowdown or pruning of projects? And what is the current China vs Southeast Asia cell procurement mix and how will it evolve over 2-3 years?
Answer, Rinal Shah, Investor Relations. There is a net addition to the order book, but execution momentum was higher this quarter. The domestic order book is adequate for the next 4-5 quarters until cell capacity comes in. DCR enquiries for CY27 delivery are now in active discussion. On sourcing: currently heavily skewed to China due to cost advantage, but as state-supported subsidising recedes (9% VAT export rebate removal), cost parity is establishing in Southeast Asia. Conversations with SE Asian partners are activated; only a 1-year runway since own cells come in after that.
5. Lease structure, export compliance and TOPCon pricing
Nidhi Shah, ICICI Securities
Question. On the 5 GW Vallam line which is leased: what is the yearly lease payment and total lease on books, and the rationale for leasing vs owning? Also, is the 16-20% export order book using Indian cells? Lastly, are customers paying a premium for TOPCon over Mono PERC?
Answer, Ranjan Jindal, Chief Financial Officer. Vallam was funded via INR400 cr debt at 8.5% lease, with ~INR108 cr annual outflow (including interest), amortised over 5 years. Rationale: speed to commission (target Oct 2025 from Feb 2025 conception), asset-light structure with right-of-use treatment, and no tax disadvantage. Rinal added: Indian cells are unviable for exports due to reciprocal tariffs; UFLPA/FEOC-compliant supply chain from SE Asia is used with CBP pre-approval for US. On TOPCon vs PERC: in DCR, TOPCon supply is insufficient so PERC DCR remains valid for now; in non-DCR, the market has completely pivoted to TOPCon.
Follow-up. Are we seeing a price differential between Mono PERC and TOPCon for non-DCR modules?
Answer. Non-DCR: there is hardly any expectation from the market of Mono PERC.
6. Cell plant execution and G12R/M10 capability
Akshay, UBS
Question. Status of the 9 GW cell plant from Thailand and the 3 GW organic expansion? Also, you mentioned shifting all modules to G12R — but the Thailand plant is M10-based. What is the disconnect?
Answer, Ranjan Jindal, Chief Financial Officer. The 12 GW cell plant is being handled collectively. Thailand cell line shift will take ~4 months from start of dismantling to delivery at site. Clean room expected ready by Sept-Oct, with first cell-out by Dec 2026; shifting exercise to start around April-May. Rinal clarified: both upcoming cell plants will be capable of manufacturing M10R and G12R cells; the G12R shift refers to module portfolio of existing 9.5 GW.
Follow-up. So the Thailand line is already G12R capable?
Answer. Got it. Yes.
7. Pricing pressure and margin outlook
Sarang Joglekar, Vimana Capital
Question. With significant module capacity already added, do you see aggressive pricing by competitors and a further decline in margins going forward?
Answer, Rinal Shah, Investor Relations. A few basis points swing is not a decline; Q3 had ~30% of execution from government contracts taken a year back, which is normal course. Top 10 customers are 70% repeat customers. Overcrowding exists only in the lesser efficient legacy systems: top 15 manufacturers control ~100 GW supply while 95 other manufacturers control only 45 GW, mostly policy-driven Mono PERC supply.
8. FY28 DCR demand visibility and capex funding
Nikhil Abhyankar, UTI Mutual Fund
Question. Outlook on utility-scale DCR demand in FY28? And funding source for the new ~INR44 bn capex (including BESS)?
Answer, Rinal Shah, Investor Relations. Post the 1 Sep 2025 threshold date, ~20 GW of RFSs have come through, of which one tender has given results. Tracking each tender's bid submission and result timelines, 30-35+ GW of utility-scale DCR demand is expected in FY28 with more RFSs to be announced. Ranjan added: total module+cell capex is INR6,400 cr (debt INR3,800 cr, INR1,500 cr from IPO, balance from internal accruals). BESS capex is INR4,300 cr at 65:35 debt-equity, financial closure underway; INR2,800 cr debt and INR1,300 cr from internal accruals over 30 months.
9. Developer deferment risk and FY28 DCR demand
Bharani, Avendus
Question. In times of increasing module prices (similar to post-COVID), are developers deferring module purchases? And how are you confident of 35 GW DCR utility demand in FY28 when awarding activity is much lower than last year?
Answer, Ranjan Jindal, Chief Financial Officer. Deferment triggers LD (liquidated damages); so far no developer has asked for supply shift. Production and sales are at the same level, customer-wise dispatch mapping and LCs are in place. Rinal added: addressable market of tendered capacity is ~104 GW non-DCR + 15+ GW DCR for the next two fiscals, ensuring installation run rate has no risk of slowdown. Even if the 42 GW PPA-pending capacity is excluded, 70-75 GW TAM remains. RCO framework, PM-KUSUM, PM Surya Ghar and C&I adoption will sustain momentum for 5-10 years.
Follow-up. Can you break down the 108 GW of tenders — is it adjusted for the 40 GW without PPA?
Answer. The 42 GW has not been officially cancelled by the ministry, but even excluding it leaves 70-75 GW TAM, which is AC. DCR demand sits separately.
10. BESS scope, silver pass-through and capex phasing
Sagar Parekh, Renaissance Asset Managers
Question. On BESS: is the INR4,300 cr for battery cells or battery pack? Tie-up status? And on the silver cost as % of BOM — and the capex split between FY26, FY27 and FY28?
Answer, Rinal Shah, Investor Relations. Starting with 5 GWh battery pack (FY27), then 7.5 GWh integrated cell+pack facility (additional 2.5 GWh assembly). Technology partnership in advanced stages; announcement soon. Silver: no direct silver cost as cells are imported; cell inflation is pass-through in 88% of order book, so no price impact. Ranjan added: capex will be spent over 24-30 months, equity component ~INR2,400 cr from internal accruals. ~INR300 cr spent in 9MFY26; FY26 total expected INR1,000-1,200 cr (Q4FY26 capex-heavy at ~INR900 cr).
11. FY27 order inflow target and export outlook
Darshil Jhaveri, Crown Capital
Question. Order inflow target for FY27 given current book will be fully executed in ~4 quarters? And from which customer segment will the orders flow? Also, post-cell manufacturing, how do you see the export market potential?
Answer, Gyanesh Chaudhary. Target is to maintain 1.2-1.3x rolling order book coverage of scheduled deliveries; FY27 target implied at ~14-15 GW. Order mix: IPP ~50%, C&I and distribution are the focus areas. Rinal added: government contribution is sporadic. Gyanesh on exports: India has achieved critical mass in manufacturing with access to technology, capital and scale; Vikram will compete with China at a global scale. Current tariff regime creates challenges but solar deployment is structurally strong globally due to unmatched LCOE.
12. FEOC compliance and SE Asia sourcing rationale
Prakhar Parwal, Ambit Capital
Question. Under FEOC restrictions, does Chinese value-addition limit apply to cell only or also to wafer and polysilicon? And given 88% of orders are pass-through, what is the rationale for shifting from China to SE Asia if SE Asia cells are costlier?
Answer, Rinal Shah, Investor Relations. It is non-Chinese from wafer onwards, plus no Xinjiang-region polysilicon — UFLPA is the stricter benchmark. SE Asian cell producers source non-Chinese/non-Xinjiang inputs. On the China-to-SE-Asia shift: rationale is not commercial but supply diversification; Chinese cells attract 27.5% levy (BCD+AID), so non-Chinese SE Asian cells are priced at parity. Own cell capacity comes in only after a 1-year runway.
What was said
Topic by topic, in the order it was spoken
Global energy transition context · Gyanesh Chaudhary (CMD)
- Clean energy transition is now in a more industrial phase, defined by delivery capability, manufacturing credibility and long-term resilience.
- Next phase is system-led, shaped by convergence of generation, storage and grid infrastructure rather than standalone assets.
- India's storage and green hydrogen ambitions will require significant scale-up in integrated renewable + storage capacity over the next decade.
Capacity build-out and integration roadmap · Gyanesh Chaudhary (CMD)
- Successfully commissioned and stabilised 5 GW advanced module facility at Vallam (Tamil Nadu), taking total installed module capacity to 9.5 GW.
- Fully transitioned product portfolio to high-efficiency N-type modules to support bankability across utility, C&I and distribution segments.
- Execution focus now on Gangaikondan site: 6 GW modules + 12 GW cells; depth in domestic manufacturing and supply-chain resilience seen as critical under ALMM List II/III.
Industry sizing and policy support · Gyanesh Chaudhary (CMD)
- NISE assessment indicates over 3,300 GW of deployable ground-mounted solar potential; India to become second-largest solar market globally in 2026 with 50+ GW additions.
- MNRE raising minimum module efficiency threshold (20% to 21.5% for utility-scale by FY28) encourages technology upgradation.
- China's removal of 9% VAT export rebate viewed as a constructive development that may moderate state-supported pricing distortions.
Q3 and 9MFY26 operating performance · Ranjan Jindal (CFO)
- Q3 sales volume 796 MW (vs 590 MW YoY); 9MFY26 sales volume 2.3 GW, surpassing FY25 full year by 23%.
- Q3 revenue INR1,106 cr; 9MFY26 revenue INR3,349 cr (vs INR2,230 cr). Q3 EBITDA INR205 cr at 18.5% margin; 9MFY26 EBITDA INR682 cr at 20.3%.
- Q3 PAT INR98 cr vs INR19 cr YoY; 9MFY26 PAT INR360 cr vs INR49 cr. Effective capacity utilisation 90% in Q3 and 88% in 9M.
Sector developments and policy · Ranjan Jindal (CFO)
- India added ~8.5 GW solar in Q3; cumulative 30 GW in 9M taking total installed solar capacity to 136 GW. Renewables account for 50% of 510 GW total installed power capacity.
- RCO framework formalised in late 2025 with unified target rising from 29.9% in FY25 to 43.33% by FY30; PM-KUSUM and PM Surya Ghar driving distributed solar demand.
- DGTR recommended 23-30% anti-dumping duty on Chinese cells but 90-day window lapsed on 29 Dec 2025 with no notification; ALMM List III draft roadmap for wafers (effective 1 June 2028) issued.
Cost efficiency, order book and BORM · Ranjan Jindal (CFO)
- Cost efficiency improved via higher throughput, greater automation, tighter indirect cost control; Vallam features advanced automation reducing manual touch points and labour cost.
- Weighted average finance cost of debt declined to 6.5% in 9MFY26 from 7% in H1 FY26, supported by disciplined cash flow and reset of interest rates.
- Order book at 10.58 GW (vs 8.2 GW YoY, up 28%): IPPs 55%, C&I 21%, government+EPC 11%, distribution 13%; 88% of order book has cell-price pass-through.
Capex, human capital and product · Ranjan Jindal (CFO)
- Gangaikondan module plant on track for Q1 FY27 commissioning; cell plant phased with first cell-out Dec 2026; long-lead utility items under finalisation.
- Headcount up from 1,587 (Dec 2024) to 2,413 (Dec 2025) to support new facility ramp-up; ~INR300 cr capex spent in 9MFY26.
- Launched Hypersol Pro N-type module at REI Expo 2025: 23.7% efficiency, up to 640 Wp output; secured 8th consecutive BloombergNEF Tier-1 Bankability rating and India Ratings upgrade to A+/A1+.
In their words
The next phase of this transition is increasingly system-led, shaped by convergence of generation, storage, and grid infrastructure rather than standalone assets.
I wouldn't call a few basis points swing in the margin as a decline. You have to understand that quarter-to-quarter, our realizations depend on a particular set of execution that we have committed to.
The company has started sourcing cells from Southeast Asian countries, thereby reducing China dependence... Module Supply Contracts signed by the company are designed to pass through the impact of such rising input costs to the consumers since we operate in a cost-plus business model.
To check next time
What management committed to on this call, or the dates they gave.
- Vallam 5 GW ramp-up to full utilization on the 9.5 GW module base.
- Gangaikondan 6 GW module plant: structural works, roofing completion ahead of Q1 FY27 commissioning.
- Thailand cell line dismantling start (April-May 2026) and clean-room readiness (Sept-Oct 2026).
- Q4 FY26 capex outflow of ~₹1,000-1,200 cr and progress on ₹2,400 cr equity build-up from internal accruals.
- BESS 5 GWh battery pack financial closure and any tie-up announcement for lithium-ion cells.
- Cell sourcing shift from China to Southeast Asia; status of 27.5% Basic Customs Duty on Chinese cells and 9% China VAT export rebate removal from April 2026.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Tue 20 Jan 2026 | ₹214.88 | −9.70% | −1.38% |
| 5 sessions Tue 27 Jan 2026 | ₹199.20 | −16.29% | −1.60% |
| 20 sessions Mon 16 Feb 2026 | ₹224.60 | −5.61% | +0.38% |
From the close of Mon 19 Jan 2026, ₹237.96: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.