Vikram Solar Q2 FY27 earnings call
In brief
Q2 revenue fell to INR1,077 crores on 591 MW; management expects an H2 volume recovery and March 2027 COD for the 9 GW cell line.
- Management's tone
- Mixed
- What was said
- Mixed
- Guidance
- Guidance held
- Analyst pushback
- Medium
- Stock, next session
- −2.73% (Nifty 50 +0.58%)
- Q2 revenue was INR1,077 crores on 591 MW; EBITDA was INR101 crores at a 9.4% margin and profit was INR6 crores as volume fell about 40% QoQ.
- Order flow more than doubled sequentially to 1.7 GW, including 1.3 GW from key accounts; closing order book was 8.2 GW after a 1 GW US order removal.
- The 9 GW TOPCon Plus cell facility remained on schedule for first output in December, project COD in March 2027 and full commercial ramp-up within four to six months.
- EBITDA per watt peak rose 37% QoQ from INR1.25 to INR1.71 as distribution reached 44% of volume and DCR volume within distribution grew 71% QoQ.
- VSL PowerHive planned Q1 FY28 commercial operations for 7.5 GWh of BESS assembly and a second 7.5 GWh battery-cell plant.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q2 FY27
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹1,077 cr | −2.9% | −31.1% | |
| EBITDA (excl. other income) | ₹101 cr | −56.9% | −19.7% | 9.4% (21.2% a year ago) |
| Net profit | ₹5.9 cr | — | — | 0.6% (0% a year ago) |
| EPS (₹) | ₹0.16 | −95.8% | −70.9% |
From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
What moved the numbers, as management explained it
- Q2 volume fell about 40% QoQ to 591 MW: IPP customers deferred offtake over evacuation and land constraints, the monsoon slowed installations, and late ALMM clarity moved C&I offtake to Q3.
- Distribution reached 44% of volume; DCR volume within it grew 71% QoQ and H1 realization per watt rose about 15%, cushioning the lower-volume quarter.
- Procurement, bill-of-materials and plant-operations optimisation delivered savings; other expenses fell 25%, partly from lower volume.
- Finance cost fell 13% QoQ to INR43 crores, partly offsetting the fall in absolute EBITDA from INR126 crores in Q1 to INR101 crores in Q2.
- Crude at sub-90 levels increased freight and logistics costs in Q2; prior-quarter inventory prevented a production issue, and lower crude should reduce logistics costs.
- The 8.2 GW closing order book excludes 1 GW of US orders removed after Section 232 imposed a minimum import price and 15% ad valorem duty.
The numbers management led with
- Quarterly order flow: 1.7 GW, more than double the previous quarter
- U.S. orders removed and closing order book: 1 GW of U.S. orders removed; 8.2 GW closing order book
- 9 GW cell commercialization: First cell in December 2026, sequential commissioning through March 2027, four-to-six-month ramp and full commercial operation by Q2 FY28
- Gangaikondan integrated project spend: 6 GW modules and 9 GW cells; project cost INR5,800 crores; about INR1,700 crores spent and another INR3,800 crores planned in H2 FY27
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| Volume (Solar modules) | Q3 FY27 | Around 1 GW of volume in the coming quarter. |
| H2 volume (Solar modules) | H2 FY27 | H2 volumes are expected to be substantially higher than H1 as the order book converts, with distribution momentum continuing. |
| EBITDA per watt peak | H2 FY27 | For H2, EBITDA per watt peak is expected to hold at around current levels. |
| Order book execution and DCR mix | — | 60%-70% of the 8.2 GW order book should execute over 12-18 months; next-quarter DCR demand should lift DCR's share. |
| 9 GW cell facility commissioning and full ramp-up (Cell manufacturing) | Q2 FY28 | First cell output is due in December 2026, project COD in March 2027 and the last line is expected fully ramped by Q2 FY28. |
| ALMM List-II result time (Cell manufacturing) | Q4 FY27 | Enlistment inspection is planned for Q4 FY27; the List-II result takes 30-40 days. |
| Margin expansion from captive cells | FY28 | Captive cells will structurally improve margins for FY28; management said DCR margins would almost double versus procured cells. |
| Gangaikondan project spend (Cell manufacturing) | H2 FY27 | Another INR3,800 crores is planned to be infused in H2, mostly for the cell project. |
| 9 GW cell project cost (Cell manufacturing) | — | The 9 GW cell project requires about INR4,500 crores, within about INR500 crores per GW, with equity funding stated at 3:1. |
| 9 GW wafer/ingot project | FY28-FY29 | Wafer/ingot spending starts in FY28; the 9 GW project is estimated at INR5,600 crores and targeted for mid-FY29 commissioning. |
| 7.5 GWh BESS assembly commercial operations (VSL PowerHive BESS) | Q1 FY28 | First-container rollout and certifications are planned for Q4 FY27, with commercial operations in Q1 FY28. |
| 15 GWh BESS cell commissioning (VSL PowerHive BESS) | FY30 | Management said the 7.5 GWh cell plant would go live by 2029-2030, with 15 GWh of cell capacity commissioned in 2030. |
| 7.5 GWh BESS project cost (VSL PowerHive BESS) | FY28-FY29 | About INR3,600 crores is estimated for BESS spending over commissioning dates, including spending planned in FY28-FY29. |
| FY28 cell capex (Cell manufacturing) | FY28 | Major spending towards the cell-plant project is expected in FY28 at about INR3,800 crores. |
| Plant capacity utilization (Solar modules) | H2 FY27 | Plant utilization is expected to improve significantly in Q3-Q4 FY27 as scheduled deliveries are made. |
What changed since the Fri 7 Aug 2026 call
| What | On the Fri 7 Aug 2026 call | On this call |
|---|---|---|
| FY27 guidance (restated) | FY27 guidance was deferred to an H1 review, citing ALMM 2 uncertainty and minimal Q1 DCR volumes. | Management expects higher H2 volumes and Q2-like EBITDA per watt, but still declined numerical FY27 revenue or margin guidance. |
| 9 GW cell commissioning (held) | The 9 GW cell line was on track for Q4 FY27 commissioning. | First cell output is due in December 2026, project COD is March 2027 and full ramp-up is expected by Q2 FY28. |
| BESS assembly commercial operations (delayed) | Commercial operations for the 7.5 GWh BESS assembly plant were targeted for March 2027. | Management now plans commercial operations for the 7.5 GWh assembly plant in Q1 FY28. |
| BESS cell commissioning (restated) | The 7.5 GWh LFP cell plant was targeted for Q4 FY29. | Management now targets commissioning of 15 GWh of BESS cell capacity in 2030. |
| Wafer/ingot commissioning (restated) | The priority was a fully integrated ingot-to-module platform at Gangaikondan by FY30. | The 9 GW wafer/ingot project is now targeted for mid-FY29 commissioning, with spending phased from FY28. |
| Customer mix (achieved) | Management prioritised shifting from large accounts to large, mid-market and distribution channels. | The new mid-market segment added 400 MW and distribution reached 44% of Q2 volume. |
| FY27 capex (restated) | FY27 capex was set at about INR5,000 crores. | INR1,700 crores was spent by Q2 and another INR3,800 crores was planned for H2, mainly on cells. |
| Balance-sheet debt (new) | Management said the balance sheet remained long-term debt-free. | Gross debt was INR632 crores and net debt INR547 crores at Q2 end, with net debt-to-equity at 0.17. |
The business
By business
Solar modules
Q2 was a low-volume quarter: 591 MW and INR1,077 crores revenue. Key accounts, IPP, C&I and mid-market orders totalled 1.7 GW; the closing order book was 8.2 GW after removing 1 GW of US orders.
Revenue from operations INR1,077 crores · Volume 591 MW · EBITDA INR101 crores · EBITDA margin 9.4% · Profit INR6 crores · Order flow 1.7 GW · Key-account order flow 1.3 GW · Mid-market order flow 400 MW · Closing order book 8.2 GW · Removed US export orders 1 GW
Outlook: H2 offtake is expected to recover, with Q3 volume around 1 GW and higher H2 volumes as the order book converts; EBITDA per watt peak is expected near Q2 levels.
Distribution
Distribution volume rose about 80% from 145 MW to 259 MW and represented 44% of Q2 volume; the network expanded to 133 distributors and more than 750 dealers and system integrators.
Distribution volume 259 MW · Prior-quarter distribution volume 145 MW · Distribution growth about 80% · Distribution share of volume 44% · Distributors 133 · Dealers and system integrators more than 750
Outlook: Management expects distribution momentum over the next few quarters, and H2 priorities include scaling distribution while retaining PM Surya Ghar and small C&I demand.
DCR solar
DCR volume within distribution grew 71% QoQ and lifted realizations. The 8.2 GW order book remained primarily non-DCR; C&I DCR demand was expected to ramp after the December ALMM exemption deadline.
DCR volume growth within distribution 71% QoQ · H1 average realization per watt growth about 15%
Outlook: The 9 GW captive-cell project targets March 2027 COD; management expects meaningful FY28 margin improvement as output ramps and DCR mix expands.
Cell manufacturing
The TOPCon Plus cell project remains on schedule: first cell out in December 2026, sequential commissioning through March 2027 and a four-to-six-month ramp-up. It is intended to replace purchased cells.
Cell capacity 9 GW · Project cost about INR4,500 crores · Equity funding ratio 3:1 · First cell out December 2026 · Project COD March 2027
Outlook: Project COD is March 2027; the final line is expected fully ramped by Q2 FY28, and ALMM List-II inspection is planned for Q4 FY27.
VSL PowerHive BESS
The 7.5 GWh assembly equipment was undergoing factory acceptance tests, with first-container rollout and certifications planned for the next quarter. A second 7.5 GWh battery-cell plant is also planned.
Integrated BESS plan 15 GWh · Phase 1 assembly capacity 7.5 GWh · Battery-cell plant capacity 7.5 GWh · Estimated BESS spend about INR3,600 crores
Outlook: Commercial assembly operations are planned for Q1 FY28; the 15 GWh cell programme is targeted for commissioning in 2030.
Balance sheet, capex and funding
- Gross debt was INR632 crores and net debt INR547 crores at Q2 end, with net debt-to-equity at 0.17.
- The 6 GW module and 9 GW cell Gangaikondan project is costed at INR5,800 crores and funded roughly one-third equity and two-thirds debt.
- About INR1,700 crores was spent by Q2. Management said another INR3,800 crores was planned for H2, while in Q&A it called about INR3,800 crores the major FY28 cell spend.
- Estimated project costs were INR4,500 crores for 9 GW cells, INR5,600 crores for 9 GW wafer/ingot and INR3,600 crores for 7.5 GWh BESS.
- Management said wafer/ingot and BESS spending would run in FY28-FY29, with serious investment starting from the next fiscal year.
- Other current assets rose from INR360 crores to INR620 crores on capex and DCR advances; management also cited INR150 crores of safeguard duty withheld.
The industry, as management sees it
Management expects India's solar base to roughly triple from about 170 GW to 509 GW by FY36, supported by CEA demand growth, government schemes and Green Energy Corridor III. FY27 also features a module capacity build-up and a narrowing non-DCR market, creating price competition despite stronger longer-term rooftop, C&I and data-center demand.
Risks management named
- IPP offtake deferrals resulted from customer land-availability and evacuation constraints.
- ALMM List-II uncertainty delayed C&I decisions, while module overcapacity intensified price competition.
- U.S. Section 232 duties made 1 GW of export orders unviable and required their removal.
- Chinese export controls and MOFCOM registration create uncertainty for wafer/ingot and technical staffing.
- The 9 GW cell line requires disciplined sequential commissioning and a four-to-six-month ramp.
- The safeguard-duty exposure remained unresolved without a closure date.
- Crude-linked freight and logistics costs affected Q2.
Q&A
Q&A centered on converting the 8.2 GW order book into H2 and Q3 volumes, the capex, funding and ramp-up of the 9 GW cell and wafer roadmaps, and BESS execution. Management was direct on schedules, capacity and project costs, but repeatedly declined numerical FY27 revenue and margin guidance and any German-technology IRR work while China export rules remain unresolved. The sharpest unresolved matters were cell-ramp execution, ALMM timing and the safeguard-duty receivable.
Not answered directly
- Numerical FY27 revenue and EBITDA-margin guidance
- FY27 full-year volume guidance
- German-technology capex economics and IRR under China export controls
- Safeguard-duty resolution timing
- Q3-Q4 volume and 10% EBITDA-margin thresholds
Asked for a number, answered without one
- DCR share of order book: Management said the order book is primarily non-DCR and did not disclose a DCR share.
- Captive-cell spread benefit: Management declined to quantify it, saying captive-cell margins would almost double the present DCR margins of procured cells.
- Numerical FY27 revenue and margin guidance: Management said quantification was difficult; it expects higher H2 volumes and EBITDA per watt peak to hold at Q2's increased level.
- German-technology capex economics: Management said it had no current update and would provide colour only if the Chinese restrictions became real.
- Capacity utilization: Management said all current lines were fully ramped and utilization would improve significantly with scheduled Q3-Q4 deliveries, without giving a percentage.
- Q4 EBITDA margin threshold: Management said quantifying that was difficult and focused on retaining per-unit EBITDA and maximizing capacity utilization.
- Safeguard-duty resolution: Management said advisers were hopeful of closing the issue sooner but gave no resolution date.
Every question, with its answer
1. Order-book execution and cell margin benefit
Shubham Burade, ICICI Securities
Question. Of the 8.2 GW order book, how much is DCR and over what period will it be executed? How much spread benefit should the 9 GW cell capacity provide once commercialized?
Answer, Sameer Nagpal and Ranjan Jindal, CEO and CFO, Vikram Solar Limited. The 8.2 GW book is primarily non-DCR, and 60%-70% is expected to execute over the next 12-18 months. The CFO declined to quantify the spread with capacities still under discussion but said captive cells should almost double margins versus the current DCR margins on procured cells.
Follow-up. How much spread benefit should the 9 GW cell capacity generate once commercialized?
Answer. The CFO said it was not appropriate to quantify with capacities under discussion, but expected margins to almost double from current DCR margins on procured cells.
2. Integrated capacity, capex funding and BESS controls
Sahil Sheth, Anand Rathi Institutional Equities
Question. Why did the plan move from 12 GW of ingot, wafer and cell capacity in earlier disclosures to 9 GW in the current presentation? What is the capex and debt-versus-equity funding for the 9 GW integrated plan, and are China export controls delaying BESS commissioning?
Answer, Ranjan Jindal and Arun Mittal, CFO, Vikram Solar Limited; CEO, VSL PowerHive Private Limited. The 12 GW integrated plan remains intact. Phase 1 comprises 9 GW of cells backed by 9 GW of wafer and ingot, with the balance 3 GW of cell, wafer and ingot capacity provisioned for later. The 9 GW cell project is estimated at about INR4,500 crores, or around INR500 crores per GW, with management also citing a 3:1 funding contribution. Arun Mittal said China export controls do not affect Phase 1 BESS assembly; controls relevant to future cell equipment would be addressed.
Follow-up. For the 9 GW integrated capacity, what capex is required and how much would be debt-funded versus internal accruals?
Answer. Management estimated the 9 GW cell project at about INR4,500 crores, within about INR500 crores per GW, and cited a 3:1 funding contribution.
3. China technology controls and German alternatives
Dhaval Popat, Choice International Limited
Question. How exposed is the wafer/ingot expansion to China's proposed technology export curbs, and how would switching to German technology change capex economics and project IRR?
Answer, Sameer Nagpal, Chief Executive Officer, Vikram Solar Limited. The existing 9 GW cell line is not affected by restrictions still being drafted in China. For wafer and ingot, management is monitoring the final rules and will decide after the outcome is known. No capex or IRR economics for moving to German technology are available, and management will provide more detail only if the restrictions become real.
Follow-up. Could management quantify how German technology would change project IRR and economics if a switch became necessary?
Answer. Management said there was no update at that point and would provide more color as the situation developed.
Not answered directly.
4. Volume outlook and distribution versus DCR
Deepak Purswani, Svan Investments
Question. How should FY27 volume be viewed after the Q2 decline, and would about 1 GW be reasonable in the next quarter? Also, how should investors distinguish DCR from distribution, given that distribution is now partly DCR?
Answer, Sameer Nagpal, Chief Executive Officer, Vikram Solar Limited. Management characterized the Q2 decline as temporary because IPP and C&I offtake issues were being addressed, and said about 1 GW in the next quarter was a fair estimate. Distribution historically served small C&I customers in the non-DCR market but has been reoriented toward DCR; the strategy now has two legs: PM Surya Ghar and continued participation in small C&I.
Follow-up. Would about 1 GW be reasonable in the next quarter, and what is the distinction between DCR and distribution?
Answer. Management endorsed around 1 GW as a fair next-quarter estimate and explained that distribution contains both PM Surya Ghar DCR volumes and non-DCR small C&I volumes.
Not answered directly.
5. Wafer/BESS capex and IPP offtake delays
Sahil Sheth, Anand Rathi Institutional Equities
Question. What capex is planned for wafer/ingot and BESS, on what timetable will it be spent, and why did IPP orders remain a large part of the book while contributing little Q2 revenue? Is the IPP land issue concentrated in a particular state?
Answer, Ranjan Jindal, Rinal Shah and Sameer Nagpal, CFO; General Manager, Corporate Finance; CEO, Vikram Solar Limited. The 9 GW wafer/ingot estimate is about INR5,600 crores, or roughly INR620 crores per GW, while 7.5 GWh of BESS assembly is estimated at INR3,600 crores. Serious investment is expected from FY28, wafer/ingot commissioning is targeted for mid-FY29 and 15 GWh of BESS cells for 2030. IPP offtake was delayed by land and evacuation constraints, but normalization has begun. Management declined to identify the affected customers or geography.
Follow-up. Is the IPP land problem specific to a particular geographical area or state?
Answer. Management said the issues were customer- and contract-specific and it could not provide further detail.
6. H2 financial guidance and utilization
Saanj Arya, Resurgence Capital
Question. What revenue-growth and margin targets apply to FY27 and H2, and what is current capacity utilization and the expected improvement?
Answer, Ranjan Jindal and Rinal Shah, CFO; General Manager, Corporate Finance, Vikram Solar Limited. Management expects the order book to convert into stronger H2 volumes, subject mainly to IPP site offtake, and expects EBITDA per watt peak to remain at the improved Q2 level as retail penetration rises. It would not quantify revenue growth or margins. Management said all four module lines were fully ramped and that utilization would improve significantly as scheduled Q3 and Q4 deliveries were executed.
Follow-up. Can management provide numerical growth and margin targets, and what is current capacity utilization?
Answer. The CFO repeated that numerical guidance was difficult to quantify but said EBITDA per watt peak would be maintained. Rinal Shah said current lines were fully ramped and utilization would improve with Q3-Q4 offtake.
Not answered directly.
7. ALMM List-II approval timing
Athul Joby, Prosperity Wealth
Question. When is ALMM List-II approval expected after the solar cell plant is commercialized?
Answer, Rinal Shah, General Manager, Corporate Finance, Vikram Solar Limited. The enlistment inspection is planned for Q4 FY27 once sequential commissioning begins. Management expects the list result approximately 30-40 days after inspection.
8. Revenue, margin recovery and crude costs
Karan Kubetia, Unknown
Question. Why did revenue fall sequentially and why have margins not been sustained, and how should both recover after cell manufacturing? How much has crude and war-related freight inflation affected raw-material and logistics costs?
Answer, Ranjan Jindal, Chief Financial Officer, Vikram Solar Limited. The 40% volume decline reduced revenue, although a higher DCR mix cushioned the impact and H1 revenue was higher year on year. Management expects a serious H2 volume increase, broadly maintained EBITDA per watt and a material change in FY28 as captive cells support DCR penetration. Crude below $90 reduced some pressure; freight and logistics affected Q2, but inventory prevented a production disruption and logistics costs should fall further.
Follow-up. How much are crude prices and the war affecting raw-material costs, and what mitigation is in place?
Answer. The CFO said crude had fallen below $90, freight affected Q2 to some extent, prior-quarter inventory prevented production issues and logistics costs should decline as crude eases.
9. 9 GW cell commissioning and ramp-up
Mukesh Aggarwal, Turbo
Question. By when will the full 9 GW cell capacity become fully operational and commercially productive?
Answer, Sameer Nagpal, Chief Executive Officer, Vikram Solar Limited. First cell output is expected in December, with lines commissioned sequentially through March. Ramping normally takes four to six months, so the last line should be fully operational for commercial production by Q2 FY28; earlier lines and sales would ramp sooner.
Follow-up. Does this mean the full 9 GW cell line will be operational by Q2 FY28?
Answer. Management confirmed Q2 FY28 for the last line, while emphasizing that earlier lines would ramp faster and begin contributing production and sales sooner.
10. Current assets and safeguard-duty recovery
Vaibhav Shah, Equirus Securities
Question. Why did other current assets increase sharply from about INR360 crore to INR620 crore, and when can the Emphasis of Matter relating to safeguard duty and INR50 crore of customer receivables be resolved?
Answer, Ranjan Jindal, Chief Financial Officer, Vikram Solar Limited. The current-asset increase was attributed mainly to advances to capital-equipment vendors and deposits or advances to DCR suppliers; management expected these to convert into recoveries in Q3 and Q4. On safeguard duty, management referred to an exposure of INR150 crore, said consultants and advisers were hopeful of a prompt resolution and offered no specific date.
Not answered directly.
11. Volume recovery, margin threshold and DCR mix
Bala Murali Krishna, Oman Investment Advisors
Question. How should volumes shape up in Q3, Q4 and after own-cell production begins? Could EBITDA margin reach 10% by Q4? Why did an approximately 8 GW order book restrict Q2 volume to around 0.5 GW, and how will the DCR/non-DCR order-book mix change in FY28?
Answer, Rinal Shah, Ranjan Jindal and Sameer Nagpal, General Manager, Corporate Finance; CFO; CEO, Vikram Solar Limited. Management expects a significant Q3-Q4 volume increase from 1.7 GW of Q2 intake, including shorter-cycle mid-market orders, IPP demand and C&I orders linked to the December non-DCR deadline, but did not assign a volume number. It also declined to confirm a 10% EBITDA-margin threshold, focusing instead on per-watt EBITDA and utilization. IPP land and evacuation delays caused the Q2 shortfall and have begun normalizing. The current book is mainly non-DCR; DCR should increase next quarter with C&I demand and rise further as own cells become available.
Follow-up. Would Q4 EBITDA margin reach 10%, what caused the order-book-to-volume mismatch, and how will DCR rise in FY28?
Answer. Management would not quantify the margin threshold, reiterated that IPP constraints caused the mismatch, and said DCR participation is currently limited by purchased-cell pricing but should increase as C&I demand recovers and captive cells come online.
Not answered directly.
12. Capex schedule and module production
Akshay Mane, Nuvama
Question. What capex guidance applies for the next two years and how much has been spent in FY27 to date? What was module production in the quarter compared with approximately 0.59 GW of sales?
Answer, Ranjan Jindal, Chief Financial Officer, Vikram Solar Limited. About INR1,700 crore had been spent in FY27 to date. Major FY28 spending of about INR3,800 crore is directed toward the cell plant, while FY28-FY29 spending covers wafer/ingot and BESS. Wafer/ingot commissioning is targeted for mid-FY29, followed by phased BESS additions totaling 15 GWh. Module production was similar to quarterly sales of approximately 0.59 GW.
Follow-up. What was module production during the quarter compared with sales of approximately 0.59 GW?
Answer. The CFO said production was similar to sales.
13. Non-DCR C&I recovery and FY28 margin uplift
Vinod Bansal, HUF
Question. Has normalcy returned to the non-DCR C&I segment affected by ALMM requirements, and will EBITDA per watt hold near Q2 levels before rising as own cells ramp in FY28?
Answer, Sameer Nagpal, Chief Executive Officer, Vikram Solar Limited. The July clarification allowing C&I to continue using non-DCR through December resumed customer decision-making and brought the company back into the segment; 400 MW of current orders came primarily from it, in addition to larger C&I orders. Management confirmed that EBITDA per watt should hold near current levels in H2. Once own cells flow into DCR modules, Vikram Solar will capture cell margin, supporting an FY28 uptick.
Follow-up. Can management confirm whether EBITDA per watt will hold near Q2 levels and then increase as own cells ramp in FY28?
Answer. Management confirmed the H2 unit-economics outlook and said the margin uplift would begin as commissioned own cells enter DCR module applications.
14. Cell commissioning phases and technical staffing
Mohsin Alam, Unknown
Question. How is the cell-line commissioning phased, and what is the dependence on Chinese engineers and MOFCOM registration for installation?
Answer, Sameer Nagpal, Chief Executive Officer, Vikram Solar Limited. The phases are continuous and sequential rather than separate chunks: individual cell lines commission and ramp one after another without a break. Management sees no current MOFCOM impact. Chinese engineers are required for installation, although visa conditions have eased, and an additional non-Chinese technical consultant has been appointed above the supplier's Chinese manpower to mitigate ramp-up risk.
Follow-up. How dependent is the installation on Chinese engineers, and is MOFCOM registration currently required?
Answer. Management said MOFCOM registration has no current impact, acknowledged that Chinese engineers are required and cited eased visa conditions plus an additional technical-consulting layer as mitigation.
What was said
Topic by topic, in the order it was spoken
Demand and Policy Backdrop · Sameer Nagpal (CEO)
- CEA expects peak power demand to rise from 289 GW to 459 GW by FY36, while India's solar capacity must roughly triple from about 170 GW to 509 GW.
- PM Surya Ghar added 23.5 lakh systems, roughly 7 GW, in H1 FY27 versus 16.5 lakh systems in all of FY26.
- Utility-scale solar tendering rose 61% QoQ; PM-KUSUM, agrivoltaics and the INR5,000 crore PM Surya Sarovar Yojana widen the addressable market.
C&I, Data Centers and Grid Capacity · Sameer Nagpal (CEO)
- C&I users account for 51% of India's power consumption but remain among the least penetrated by solar.
- India's data-center capacity is projected to grow fourfold to 6 GW by 2029; every 1 GW of round-the-clock load typically needs 4-5 GW of solar plus storage.
- The Union Cabinet approved INR1.86 lakh crores for Green Energy Corridor Phase-III, capable of evacuating up to 135 GW of renewable energy.
Q2 Performance and Order Flow · Sameer Nagpal (CEO)
- Q2 volume was 591 MW and revenue was INR1,077 crores, with both below Q1.
- Order flow reached 1.7 GW, more than double the previous quarter; key accounts contributed 1.3 GW and the new mid-market channel added 400 MW.
- EBITDA per watt increased 37% sequentially from INR1.25 to INR1.71, while distribution and DCR volumes grew strongly.
Volume Reset and Distribution Growth · Sameer Nagpal (CEO)
- IPP customers deferred existing-order offtake because of evacuation, land-availability and related constraints; the monsoon also contributed and industry installations fell 25% QoQ.
- Clarification on the ALMM List-II extension for C&I arrived only on July 18, delaying customer decisions and shifting offtake into Q3.
- Distribution volume rose about 80% from 145 MW to 259 MW, backed by DCR growth; the network expanded to 133 distributors from 119 and more than 750 dealers and system integrators.
Order Book Mix and Export Shock · Sameer Nagpal (CEO)
- The 1.7 GW of new orders spanned PM-KUSUM, C&I and IPP customers.
- The 10 largest orders represented 1.1 GW and smaller orders represented the remaining 600 MW, reducing concentration risk and carrying better payment terms.
- The U.S. Section 232 circular introduced a minimum import price and an additional 15% duty; 1 GW of U.S. orders became unviable and were removed, leaving an 8.2 GW closing order book.
TOPCon Plus Cell and Ingot Roadmap · Sameer Nagpal (CEO)
- The 9 GW TOPCon Plus cell facility remained on schedule for first cell output in December, sequential commissioning over the following three months and project COD in March 2027.
- Additional technical supervision and the relocation of senior leadership to the site were added to mitigate ramp-up risk.
- Captive DCR cell supply is expected to support volumes and margins, with the aim of converting technology leadership into market share.
- The board-approved 9 GW wafer and ingot project is the next integration step and will be commissioned in phases according to policy mandates and demand.
BESS Market and Capacity Plan · Arun Mittal (CEO, VSL PowerHive)
- CEA estimates India's BESS market will exceed 300 GWh by 2035, supported by Viability Gap Funding for more than 70 GWh and the ACC PLI scheme.
- The ACC PLI scheme of INR18,100 crores is intended to promote 50 GWh of domestic battery manufacturing.
- PowerHive plans 15 GWh of integrated BESS capacity in two phases: 7.5 GWh of assembly followed by 7.5 GWh of cell manufacturing.
- Assembly equipment was undergoing factory acceptance testing, with shipment planned in the current quarter and stabilization, first-container rollout and certification in the next quarter.
BESS Commercial Roadmap and Products · Arun Mittal (CEO, VSL PowerHive)
- Commercial operations for the 7.5 GWh BESS assembly plant are planned for Q1 of the next fiscal year.
- Work has begun on 7.5 GWh of battery-cell manufacturing, with commercial production targeted for 2029-2030.
- The planned portfolio includes 5 MWh and 6.25 MWh containers and 261 kWh and 418 kWh C&I systems.
- The VION low-voltage brand had more than 300 distributors in nine months, addressing residential storage and the L3 e-rickshaw mobility market.
Financial Review and Mix Improvement · Ranjan Jindal (CFO)
- India added 8.9 GW of solar in Q2, down 25% from 12 GW in Q1, taking the installed base to 171 GW; ground-mounted additions fell 31% from 6.4 GW to 4.4 GW.
- Q2 volume fell about 40%, reducing absolute EBITDA, while the richer distribution and DCR mix supported realizations and unit economics.
- Distribution reached 44% of volume and DCR volume within distribution grew 71% QoQ.
- H1 volume rose 3% YoY to 1,596 MW and average realization per watt increased about 15%; finance costs fell 13% QoQ and other expenses fell 25%.
Margin Levers and Capital Allocation · Ranjan Jindal (CFO)
- FY27 module manufacturing capacity increased substantially while the module-only non-DCR market narrowed ahead of ALMM List-II, resulting in industry price competition.
- Management identified four margin levers: channel mix, cost optimization, capacity utilization and backward integration through own cells.
- The Gangaikondan project comprises 6 GW of modules and 9 GW of cells, with an INR5,800 crore project cost; about INR1,700 crore has been spent and another INR3,800 crore is planned for H2.
- Gross debt was INR632 crore and net debt INR547 crore, leaving the net debt-to-equity ratio at 0.17.
- H2 EBITDA per watt is expected to hold near current levels on substantially higher volume, while the FY28 shift toward captive DCR cells is expected to lift margins.
External Ratings and H2 Priorities · Sameer Nagpal (CEO)
- Vikram Solar remained on BloombergNEF's Tier 1 list.
- India Ratings affirmed an IND A+ stable rating, and EcoVadis Platinum was retained for a second consecutive year.
- H2 priorities were converting the order book into revenue, scaling distribution, raising module-plant utilization and commissioning the cell fab with discipline.
In their words
Q2 volumes were lower, but we enter H2 with better unit economics, a broader customer base, and a strong order book.
So, it would not be right for us to quantify today with the capacities being discussed. But yes, with our own captive cells coming in, margins will almost double from the present DCR margins of the procured cells.
PowerHive has made up a plan of setting up 15 GWh of integrated cell BESS system in two phases.
To check next time
What management committed to on this call, or the dates they gave.
- Q3 FY27 volume around 1 GW, which management called a fair estimate.
- December 2026 first cell output, commissioning through March 2027 and Q4 FY27 ALMM List-II inspection.
- Conversion of the 8.2 GW order book into H2 revenue and volumes; 60%-70% execution is expected over 12-18 months.
- Higher DCR share in the order book next quarter as C&I DCR demand ramps after the December deadline.
- Q4 FY27 BESS first-container rollout and certifications, followed by Q1 FY28 commercial assembly operations.
- Conversion of capex-vendor and DCR-supplier advances into recoveries during Q3-Q4 FY27.
Transcript
Read along with the recording
The whole call, 284 lines from 13 speakers over 51:54. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 16 Nov 2026 | ₹139.92 | −2.73% | +0.58% |