Vikram Solar Q4 FY26 earnings call

Fri 8 May 2026VIKRAMSOLR

In brief

Vikram Solar Q4 FY26: record ₹4,800 cr FY revenue, 19% EBITDA margin; CEO Sameer Nagpal appointed; 12 GW wafer-ingot capex of ~₹3,700 cr approved

Management's tone
Confident
What was said
Leaned positive
Guidance
None given
Analyst pushback
Medium
Stock, next session
−4.67% (Nifty 50 −0.62%)
  • FY26 revenue ₹4,800 cr (+40% YoY), EBITDA ₹917 cr at 19% margin (+500 bps), PAT ₹470 cr at 10% margin; volumes 3.3 GW (+76%).
  • Q4 FY26 revenue ~₹1,450 cr (+31% QoQ), EBITDA ₹235 cr (16% margin), PAT ₹110 cr; quarterly production hit 1 GW and order inflow 1.9 GW.
  • Board approved 12 GW wafer-ingot facility (first 6 GW phase) at Gangaikondan with ~₹3,700 cr outlay; commissioning in FY29, taking Vikram to full ingot-to-module integration.
  • BESS target 15 GWh by FY30; first 5 GWh cell-to-pack to commission by March 2027, first phase 7.5 GWh cell manufacturing in FY29.
  • No long-term debt; working capital net debt ₹64 cr; net working capital cycle compressed from 82 days in FY25 to 44 days in FY26; net-debt-to-equity 0.03.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q4 FY26

This quarterA year agoLast quarterMargin
Revenue₹1,453 cr—+31.4%
EBITDA (excl. other income)₹235 cr—+17.7%16.1%
Net profit₹110 cr—+12.7%7.6%
EPS (₹)₹3.05—+12.5%

From the company's filed results for the quarter ended 31 Mar 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • Cell costs rose on silver inflation and removal of China's export VAT rebate, partly offsetting per-watt gains.
  • Q4 EBITDA per watt peaked at ₹2.35 but realization rose only INR0.60 vs INR0.80 cost rise (war-linked EVA and aluminium impact), compressing margin ~20 bps sequentially.
  • FY26 EBITDA margin expansion to 19% (+500 bps) driven by operating leverage as expanded capacity (Vallam 5 GW) came online and per-watt overhead fell 16% YoY.
  • FY26 volume growth 76% YoY (1.9 GW to 3.3 GW) was the primary revenue and EBITDA driver.
  • Mix shift to higher volumes with ~80% of order book carrying cell price pass-through clauses insulated P&L from input volatility.
  • Working capital cycle compression (82 to 44 days) released working capital; lease rental debited on Vallam equipment lease finance raised Q4 finance cost. (accounting)

The numbers management led with

  • Quarterly production: ~1 GW in Q4 FY26 — first time hitting 1 GW quarterly run rate
  • FY26 full-year revenue: ₹4,800 crore, up 40% YoY
  • FY26 shipments volume: 3.3 GW (+76% from 1.9 GW in FY25); first time crossing 3 GW shipment mark
  • FY26 EBITDA: ₹917 crore; margin 19% (+500 bps from 14% in FY25)
  • Order book: 8.2 GW as on 31 March 2026 (IPP 69%, C&I 13%, Government/EPC 18%)
  • FY27 production guidance: ~8 GW in FY27 (~2.4x FY26 volume)

Guidance

Guidance on this call

WhatForWhat management said
FY27 EBITDAFY27FY27 EBITDA range ₹1,500-1,600 cr, approximately 74% more than FY26
FY27 production (Solar PV modules)FY27Plan to deliver approximately 7.5 to 8 gigawatts of production in FY27
EBITDA per watt peak (non-DCR) (Solar PV modules)FY27Non-DCR volume should deliver an EBITDA per watt peak at INR1.75 to INR2 throughout FY27
EBITDA per watt peak (post cell integration) (Solar PV modules)FY28For FY28, expect to deliver about INR5 per watt peak on the 1.75-2 base as cell integration comes in
Wafer-Ingot Phase 1 capexFY29First phase of 6 GW wafer-ingot at Gangaikondan with expected outlay of approximately ₹3,700 crores, commissioning in FY29
Cell capex 12 GW (Solar PV modules)FY27Overall cell capex for 12 gigawatts at ₹5,400 crores; ~90% deployed in FY27, last 10% in FY28
BESS 5 GWh assembly capex (Battery Energy Storage (BESS))FY27Assembly for the 5 GWh would cost about INR150 crores, spent majorly in the current year
BESS cell manufacturing initial outlay FY27 (Battery Energy Storage (BESS))FY27BESS cell manufacturing land and initial expenses not more than ₹200 cr in FY27; construction starts October 2026
BESS capacity target (Battery Energy Storage (BESS))FY30Target 15 GWh of BESS capacity by FY30
Debt level at FY27 endFY27Closing debt for 31 March 27 can be considered at INR3,200 crores
Debt level at FY28 endFY28Debt at FY28 end expected at INR6,500-6,600 crores
Net working capital cycleFY26Net working capital cycle compressed to 44 days in FY26 from 82 days in FY25
Net-debt-to-equity guardrail at peak drawdownFY30Commit to net-debt-to-equity below 1.5 even at point of peak debt drawdown

The business

By business

Solar PV modules

Record Q4 production of ~1 GW with order inflow ~1.9 GW; capacity 9.5 GW today scaling to 15.5 GW as Gangaikondan 6 GW plant commissions in June 2026; FY26 volume 3.3 GW (+76% YoY); 9 GW TOPCon cell plant phased commissioning to March 2027.

FY26 revenue ₹4,800 cr · Q4 FY26 revenue ₹1,450 cr · FY26 volume 3.3 GW · Q4 FY26 production ~1 GW · Q4 FY26 order inflow ~1.9 GW · Order book 8.2 GW · FY27 production 7.5-8 GW target

Outlook: FY27 EBITDA ₹1,500-1,600 cr guidance (74% growth); EBITDA per watt peak ₹1.75-2 (non-DCR) FY27 and ~₹5 in FY28 with cell integration.

Battery Energy Storage (BESS)

Backward integration into BESS starting with 5 GWh cell-to-pack assembly by March 2027, then cell manufacturing 7.5 GWh phase 1 in FY29 and another 7.5 GWh phase 2 in FY30; management views storage as policy-anchored and margin-accretive.

BESS target 15 GWh by FY30 · 5 GWh cell-to-pack by March 2027 · BESS assembly capex ~₹150 cr

Outlook: Target 15 GWh BESS capacity by FY30 to convert intermittent solar into dispatchable power.

Wafer-Ingot (upstream)

New 12 GW wafer-ingot facility approved by Board; first 6 GW phase at Gangaikondan with ~₹3,700 cr outlay, commissioning targeted for FY29; next 6 GW to be approved in FY29, with thumb rule of ~₹600 cr per GW.

12 GW wafer-ingot facility approved · First 6 GW outlay ~₹3,700 cr · ~₹600 cr per GW rule of thumb

Outlook: Full ingot-to-module integration by FY29, taking Gangaikondan to a single integrated campus.

Balance sheet, capex and funding

  • No long-term debt on the books; working capital net debt just ₹64 cr; net-debt-to-equity 0.03.
  • Net working capital cycle compressed from 82 days in FY25 to 44 days in FY26 on tighter receivables and inventory discipline.
  • Cell capex for 12 GW at ~₹5,400 cr; ~90% to be deployed in FY27 with last tranche spilling to FY28 (10% cost increase vs earlier Thailand sourcing plan).
  • 6 GW wafer-ingot phase 1 capex ~₹3,700 cr approved by Board, commissioning FY29; next 6 GW to be Board-approved in FY29 at similar ~₹600 cr/GW outlay.
  • BESS: 5 GWh assembly capex ~₹150 cr mostly in FY27; cell manufacturing land and initial outlay not more than ₹200 cr in FY27, 24-month construction period starting October 2026.
  • Expected debt level ₹3,200 cr at 31 March 2027 and ₹6,500-6,600 cr at FY28 end; committed to interest and DSCR above 2.5x and net-debt-to-equity below 1.5x even at peak.

The industry, as management sees it

India's solar sector is in a structural reset — FY26 saw 45 GW additions (87% above FY25), with utility-scale at record 34 GW and rooftop at 8.5 GW. The cell-level DCR mandate effective June 2026 forces a shift from assembly to true manufacturing; management expects the industry to rationalise to 80-100 GW of sustainable integrated capacity from announced 300+ GW. BESS is positioned as the next policy-anchored growth frontier with CEA projecting 320 GWh needed by FY35.

Risks management named

  • EVA cost rose due to crude oil inflation; aluminium frames cost up from $3,100 to $3,600/ton — partially offset by cell price decline
  • US export market effectively zeroed out since November due to tariff/trade restrictions; 1 GW US order at risk
  • DCR transition creates near-term volume uncertainty while cell procurement agreements are being finalised
  • Silver prices elevated — industry-wide concern; LECO process in TOPCon Plus reduces silver consumption
  • Industry-wide module overcapacity: management expects sector to rationalise to 80-100 GW sustainable capacity from announced 300+ GW

Q&A

Q&A was active with 21 exchanges from 13 analysts covering capex phasing (cell ₹5,400 crore, BESS ₹150 crore, wafer-ingot ₹3,700 crore for first phase), margin dynamics (Q4 EBITDA ₹2.35/watt-peak, FY27 guidance ₹1.75-2 non-DCR and ₹2-2.5 DCR, FY28 improvement to ~₹5 post-integration), DCR transition strategy (2 GW Jupiter procurement deal, PM Surya Ghar entry, removal of rolling distribution order book), US export risks (1 GW order at risk, exploring North Africa cell sources), working capital management, and BESS policy tailwinds. Management gave direct answers throughout with no significant deflections — notably clarified that the industry standard technology is N-TOPCon not HJT, and that cell market supply-demand in FY27-28 remains balanced given ramp-up timelines. FY27 EBITDA guidance of ₹1,500-1,600 crore (74% growth) was the most material forward commitment.

Asked for a number, answered without one

  • 2 GW Jupiter cell procurement pricing/spread: CFO declined to share commercials, said only that EBITDA per watt peak expectation of the company is maintained.
  • Per-watt realization contraction vs RM inflation in gross margin: Gave Q3-vs-Q4 walk (realization +INR0.60, cost +INR0.80 per watt) but did not quantify full-year FY27 realization trajectory or breakup.
  • FY27-FY28 PAT/interest cost trajectory: Management called it a forward-looking statement and said interest is capitalised during capex period, not charged to P&L; no specific FY27/FY28 PAT given.
  • Non-DCR vs DCR order book mix at FY27/FY28 end: Sameer said non-DCR will operate only within grandfathered projects of 87 GW over next 2 years; rest moves to DCR; no explicit year-end mix given.

Every question, with its answer

  1. 1. DCR cell procurement

    Sahil Sheth, Anand Rathi Institutional Equities

    Question. On the 2 GW domestic cell procurement from Jupiter International — when will DCR module rollout begin from our manufacturing facilities?

    Answer, Ranjan Jindal, CFO. The agreement with Jupiter is phased to take care of DCR demand post the June 2026 deadline. Within FY27 the entire offtake will pan out, with a ballooned offtake in H2.

    Follow-up. On capex — now that we have our 9 GW cell facility, we are procuring machinery from China versus our earlier plan to import from Thailand. What is the capex differential, and can you outline the capex schedule for FY27 and FY28?

    Answer. There was a change in plan — a 10% cost increase. Overall cell capex for 12 GW would be ₹5,400 crore. Since commissioning is between December 2026 and March 2027, deployment will go in fully in the current year, barring the last 10% instalment spilling over to FY28.

  2. 2. BESS & wafer-ingot capex

    Sahil Sheth, Anand Rathi Institutional Equities

    Question. When does BESS capex start, and what are the phasing details for wafer-ingot capex?

    Answer, Ranjan Jindal, CFO. BESS assembly for 5 GWh costs ~₹150 crore, to be spent majorly in current year. Cell manufacturing construction starts October 2026 with 24-month build; current year will see land and initial expenses of not more than ₹200 crore. Wafer-ingot: first phase 6 GW commissioning March 2028; construction starts Q2-Q3; initial spending for supplier advances within ₹100 crore as land is already in place.

    Follow-up. Would the balance 6 GW of wafer-ingot incur similar capex per GW?

    Answer. Yes, the thumb rule of ~₹600 crore per GW applies. Board approval for the second 6 GW will be sought in the subsequent financial year.

  3. 3. Integration scope

    Ankur Gulati, Genuity Capital

    Question. Some peers are expanding vertically or horizontally. Any thoughts on forward integration or horizontal integration beyond current plans?

    Answer, Sameer Nagpal, CEO. At this point of time, we are completely focused on backward integration on the module and expanding into BESS. We are not thinking anything beyond.

    Follow-up. Can you double-click on BESS expansion plans?

    Answer. As Ranjan mentioned, we are beginning with BESS assembly and then backward integrating into cell manufacturing. He has already answered that question.

  4. 4. Raw material costs

    Anuj Kapil, Taurus Mutual Fund

    Question. What was the sequential movement in key raw material costs during Q4, especially cells, glass, EVA, backsheet, and aluminium frames? What is the current inventory holding period for critical raw materials?

    Answer, Ranjan Jindal, CFO. Crude oil increase impacted EVA cost; aluminium frame cost rose with aluminium from $3,100 to $3,600/ton. Partly compensated by fall in cell prices, so Q4 did not see much net impact. On inventory: 30 days at plant level plus ~60 days at vendor's and on-water level. Working capital cycle of 44 days is net of credit available from payables.

  5. 5. Order book composition

    Kaushik Doshi, ICICI Securities

    Question. Does the 1.9 GW order inflow include distribution orders? Why were distribution orders removed from the order book?

    Answer, Sameer Nagpal, CEO. Order inflow does not include distribution — that has been removed from the order booking format. Most of our distribution was in non-DCR segment with recurring order book arrangements. Now with transition to DCR and outsourced cell supplies, we have changed to spot buying by distributors instead of recurring order book.

    Follow-up. The 6 GW capacity addition at Gangaikondan — is it on track?

    Answer. Yes, it continues to commission within June and the schedule is intact.

  6. 6. BESS policy & localisation

    Akshay, UBS

    Question. In the presentation you highlight DCR mandates for BESS targeting 60% localisation. How would policy target this, and how much cell cost for BESS forms, and how much localisation can be achieved just through assembly (containers, electronics, PCS)?

    Answer, Rinal Shah, GM, Corporate Finance. Extremely optimistic on BESS policy mandate given grid stability needs. CEA and Ministry of Heavy Industries have given indicative numbers. Anticipating a similar Approved List of Battery Manufacturers (ALBM) policy. PLI Advanced Chemistry already exists. Government has laid out ₹18,000 crore outlay on viability gap funding with ~100 GWh BESS tenders already in RFP or bid submission stage. Next 2-3 years will see extremely positive policy movement.

  7. 7. Margin & realisation

    Praveen Sahay, PL Capital

    Question. Gross margin contracted and module realisation declined ~13% in INR terms. Can you segregate how much is realisation contraction versus RM inflation? Where do you see realisation in the coming year?

    Answer, Ranjan Jindal, CFO. On per watt-peak basis, Q4 realisations actually went up by ₹0.60. Costs rose by ₹0.80 due to geopolitical factors. The ₹0.20 incremental cost dented per-unit EBITDA — hence the slight percentage margin impact. Company focuses on per-EBITDA-watt-peak; some rationalisation expected in coming quarters but scale will increase absolute numbers.

    Follow-up. On the 2 GW procurement — is pricing finalised and spread shared with the company?

    Answer. Commercially unwise to share details, but commercials are arranged such that the EBITDA per watt-peak expectation of the company is maintained.

  8. 8. Order book & US exports

    Praveen Sahay, PL Capital

    Question. On the order book — 1 GW distribution and 1.5 GW C&I were removed. How confident are you of gaining back these numbers? What happened to the 0.6 GW US order?

    Answer, Sameer Nagpal / Rinal Shah, CEO / GM Corporate Finance. As mandate moves to DCR, non-DCR distribution and C&I will move to DCR — which is why rolling order books were removed. C&I large order book is switching to DCR and is under renegotiation; will be taken as fresh bookings if margin profile fits. Distribution remains strong with expanded network (110+ distributors, 550+ dealers/system integrators exclusive to Vikram Solar). The US project was deemed unviable by the IPP due to sunset of certain incentives in the US market — removed from order book.

    Follow-up. Is there any DCR volume in this quarter?

    Answer. Hardly any volume in Q4. FY27 will see DCR offtake come in as explained.

  9. 9. Debt levels & capex phasing

    Bala Krishna, Oman Investment Advisors

    Question. Earlier plan was ₹3,500 crore debt by end of FY27. With BESS and wafer-ingot postponed to FY29, will debt levels be similar by end of FY28?

    Answer, Ranjan Jindal, CFO. Original ₹3,500 crore debt plan was for entire 12 GW cell in place. We have now phased it into 9+3 GW. FY27 will also see outflows for BESS and wafer-ingot from internal accruals. Closing debt for 31 March 2027 expected at ₹3,200 crore. By end of FY28, with wafer-ingot capex phase, debt expected to remain at ₹6,500-6,600 crore.

    Follow-up. With ~₹150 crore interest cost now, FY27 outflow ~₹500 crore and FY28 ~₹800 crore — will bottomline remain staggered around ₹500 crore levels despite EBITDA growth?

    Answer. In the capex period, project interest is capitalised and not charged to P&L. With wafer-ingot commissioning in FY29 and cell in March 2027, the P&L will have impact only for the component of debt for assets already capitalised.

  10. 10. DCR vs non-DCR mix

    Bala Krishna, Oman Investment Advisors

    Question. How do you see the DCR vs non-DCR mix in the order book by end of FY27 and FY28?

    Answer, Sameer Nagpal, CEO. Non-DCR segment will operate in grandfathered 87 GW projects. How they get executed over the next 2 years will determine the non-DCR order book. Everything else will move to DCR.

  11. 11. FY27 production guidance

    Deepak Purswani, SVAN Investments

    Question. With module capacity ramp to 9.5 GW (going to 15.5 GW in 3-4 months), should FY27 production be close to 7.5-8 GW versus 3.2 GW this year? What is the sales strategy given the 8.2 GW order book?

    Answer, Ranjan Jindal, CFO. FY27 expected to produce ~8 GW collectively with the 6 GW module from Gangaikondan. Of this, 2 GW will be on DCR and 6 GW on non-DCR. Of the 8.2 GW order book as on 31 March 2026, 7.2 GW is domestic, of which 6 GW will be executed, leaving 1.2 GW order book for the rest of the year to take share of the 87 GW grandfathered non-DCR projects.

  12. 12. EBITDA per watt peak

    Bhavana Jain, Avagrah Capital Advisors

    Question. What is the EBITDA per watt peak we are making currently without captive cell? And after cell integration, what improvement is expected?

    Answer, Ranjan Jindal, CFO. Q4 EBITDA per watt peak was ₹2.35. For FY27, non-DCR volume should deliver ₹1.75-2 per watt peak on average. By FY28, with full integration, expect ~₹5 per watt peak (down from current ~₹6) due to capex depreciation — but this is on a stabilised basis post-industry rationalisation.

    Follow-up. Is this expectation after considering industry overcapacity and insufficient cell supply?

    Answer. Yes — on a country level with full integration by top 15-20 players, post stabilisation, EBITDA per watt peak can continue at these levels.

  13. 13. Capacity utilisation

    Bhavana Jain, Avagrah Capital Advisors

    Question. What utilisation levels do you expect for FY27 after the module and BESS facilities are completed?

    Answer, Rinal Shah, GM, Corporate Finance. For modules, expect ~65-70% average utilisation on nameplate. For cells, the number is higher at 70-75% on nameplate. These are on nameplate basis, not effective.

    Follow-up. On cell technology — competitors are using HJT and we are adopting XBC. Is there a profitability improvement from this technology choice, and does it require higher capex?

    Answer. The premise is incorrect. Industry dominant technology is N-Type TOPCon; HJT is used by one larger peer with limited capacity globally. Our 9 GW cell plant is N-TOPCon Plus with incremental processes raising efficiency to 25.4-25.5% vs industry baseline of 25.2% — more wattage per module and better realisations. Capex cost is in line with industry.

  14. 14. Silver consumption reduction

    Bhavana Jain, Avagrah Capital Advisors

    Question. What is the company's expected silver consumption reduction roadmap?

    Answer, Rinal Shah, GM, Corporate Finance. TOPCon Plus setup uses LECO process which reduces silver consumption due to thinner silver fingers. R&D and applied research projects on replacing/reducing silver are ongoing but too early to quantify commercially.

  15. 15. DCR market balance

    Dhruv Muchhal, HDFC AMC

    Question. Until utility-scale DCR norms start kicking in (likely FY28-29 when new cell capacity commissions), C&I and rooftop DCR vs available cell capacity in India seems balanced/oversupplied. Given brand power and scale, can you optimise better in this DCR cell market?

    Answer, Rinal Shah / Sameer Nagpal, GM, Corporate Finance / CEO. Post June 2026 enforcement, DCR demand expected at 20-25 GW in FY27. Against existing cell nameplate in ramp-up and stabilisation phase, supply is lower than nameplate even in FY27-28, so the market is well-balanced. On PM Surya Ghar: we have not participated so far because we had no DCR. With DCR cell availability through Jupiter procurement, our strong distribution channel can now capture this segment at better margins.

  16. 16. FY27 margin management

    Niyati Davda, Elios Financial Services

    Question. How is the company planning to handle FY27 with reduced margins and no captive cell?

    Answer, Rinal Shah, GM, Corporate Finance. FY27 execution plan: 75% non-DCR delivering ₹1.75-2 per watt peak; 25% DCR through Jupiter procurement delivering ₹2-2.5 per watt peak. These steady numbers at scale will yield phenomenal growth over previous fiscal.

    Follow-up. What differentiates Vikram Solar from other big peers?

    Answer. Over 20 years, deep industry knowledge translated into right capacities and technologies. Customer intimacy is very high; brand reliability and quality perception are very high. Backward integration being built will act as key enablers.

  17. 17. Interest cost increase

    Niyati Davda, Elios Financial Services

    Question. Even though debt is being reduced, why has interest expense increased sequentially?

    Answer, Ranjan Jindal, CFO. Term loan debt has come down. Q4 finance cost increase came from Vallam equipment lease rental (facility on lease finance basis now operational) plus increased working capital deployment for inventory.

  18. 18. US capacity & strategic focus

    Nidhi Shah, ICICI Securities

    Question. Initially there was talk of 5 GW additional module capacity (2 GW India, 3 GW US). Has this been scrapped in favour of backward integration? What specifically deterred US capacity?

    Answer, Rinal Shah, GM, Corporate Finance. For the US: high requirement for traceable supply down to quartz level is stringent; availability of skilled manpower in US is a challenge. India looks infinitely more attractive — capital and management bandwidth focused on scaling domestic business and backward integration.

    Follow-up. Since November, India exports to US have zeroed out. We have ~1 GW of US export orders — how secure are these? Where are we procuring cells from?

    Answer. Export order book is with reputed IPPs we have worked with before — long-term conversations. We still believe we will execute. Working on traceable compliant supply chain without prohibitive tariffs. Countries being explored: North Africa (has cell capacity without high tariffs), EU, Australia, Middle East — conversations are encouraging.

  19. 19. FY27 guidance

    Dhaval, Areeza Strategies

    Question. With this level of growth, what growth guidance can you give to investors?

    Answer, Ranjan Jindal, CFO. FY26 delivered 86% EBITDA jump. With new facility coming in, FY27 plan is ~7.5-8 GW production to deliver EBITDA of ₹1,500-1,600 crore, approximately 74% more than FY26.

  20. 20. BESS sizing multiplier

    Shashank Jha, Individual Investor

    Question. For 1 MW AC power, you need 1.5-1.6 GW solar modules due to DC-AC conversion. Does a similar multiplier apply for BESS?

    Answer, Rinal Shah, GM, Corporate Finance. Battery requirement depends on setup. Current tenders range from 2 to 6 hours of storage; C&I or data centre could be round-the-clock. On average, 80 GW of solar with storage would require about 320 GWh with 4 hours of storage — the DC block of BESS.

  21. 21. RM cost pass-through

    Vishad Kabra, Holani Venture Capital Fund

    Question. How are rising raw material costs (especially silver) impacting cost structure, and to what extent are you able to pass these increases to customers?

    Answer, Ranjan Jindal, CFO. MSAs allow 80% pass-through of cell cost and dollar appreciation to customers. With cell coming in and wafer-ingot later, market dynamics will determine pricing. Cannot comment on long-term terms in isolation.

    Partly answered.

What was said

Topic by topic, in the order it was spoken

Operating Environment & Energy Sovereignty · Gyanesh Chaudhary (CMD)

  • Geopolitical disruptions in West Asia have made energy dependence a structural (not cyclical) risk for import-led economies like India
  • Solar sits outside all geopolitical disruptions — security, economics, and policy are now aligned in its favour
  • India is the world's third-largest solar market by annual additions, projected to move to second within the calendar year
  • Former NITI Aayog CEO Amitabh Kant described India's import dependence as a national security crisis; called for non-fossil capacity to scale from 500 GW to 1,500 GW by 2030

Leadership Transition & Strategic Mandate · Gyanesh Chaudhary (CMD)

  • Sameer Nagpal appointed CEO — brings 35+ years of cross-sector leadership with a proven record of turnarounds and profitability focus
  • Mandate: drive operational discipline, strengthen execution rigour, align business for next growth phase
  • FY26 is the year of defining strategic decisions: manufacturing integration, leadership, and storage

Backward Integration Roadmap · Gyanesh Chaudhary (CMD)

  • India imports nearly all wafer and ingot from China — a supply chain vulnerability for every domestic manufacturer
  • Integration moves in three deliberate stages: modules first (done), then cells (in progress), then wafer and ingot
  • By end of roadmap, Vikram Solar will be fully integrated from ingot to module

Battery Energy Storage (BESS) Strategy · Gyanesh Chaudhary (CMD)

  • BESS is policy-anchored, margin-accretive, and converts intermittent solar into dispatchable power
  • Data centre and AI-led load growth making storage non-negotiable infrastructure
  • Target: 15 GWh BESS capacity by FY30 — positions Vikram Solar as one of the leading integrated solar platforms
  • Transforms company from product company to complete energy solution provider — solar plus storage as dispatchable power

Q4 FY26 Operational Performance · Sameer Nagpal (CEO)

  • Highest-ever quarterly production: ~1 GW (first time hitting 1 GW quarterly run rate)
  • Highest-ever quarterly order booking: ~1.9 GW
  • Highest-ever quarterly revenue: over ₹1,450 crore (+31% sequentially)
  • These records are early innings of a multi-year growth trajectory

Sector Demand & Market Context · Sameer Nagpal (CEO)

  • FY26: India added 45 GW solar — nearly double the 24 GW target, ~87% higher than FY25
  • Cumulative installations: 150 GW (53% of India's 283 GW non-fossil base)
  • CEA National Grid Action Plan projects peak demand rising from 289 GW today to 459 GW by FY36
  • Installed solar base must scale from 150 GW to 509 GW by FY36; BESS from below 1 GWh to 320 GWh by FY35
  • Sector expected to stabilise around 80-100 GW nameplate sustainable capacity held by a few full-stack players

Policy Framework: DCR Mandate · Sameer Nagpal (CEO)

  • ALMM and BCD provide necessary guardrails for domestic growth
  • Cell-level mandate effective June 2026 is a critical milestone forcing shift from assembly to true manufacturing
  • Wafer-ingot mandate forms a coherent industrial framework rewarding operational depth
  • Barriers of capital access, technology, execution capability, and customer intimacy mean only a few will sustain

Technology Platform & Capital Allocation Philosophy · Sameer Nagpal (CEO)

  • 20 years of technology pivots taught that wrong vintage of equipment costs are paid for entire asset life
  • Cell equipment orders placed for TOPCon Plus generation with efficiency enablers — delivers 25.4-25.5% efficiency vs industry baseline of 25.2%
  • Higher watt-peak per cell translates to better per-watt realisations over time
  • Next 3 GW of cell capacity will use superior technology with incremental efficiency in subsequent year

Project Execution: Vallam & Gangaikondan · Sameer Nagpal (CEO)

  • Vallam 5 GW facility: ideation to commissioning in under 9 months — among fastest greenfield builds of this scale in India
  • Gangaikondan 6 GW module facility: final stretch of completion, first module output on track for June 2026
  • 9 GW TOPCon cell facility: civil and PEB works on track for September 2026; cleanroom/MEP completion October; equipment installation October-November; first cell out December 2026
  • Production ramp-up through Q2 FY28

FY26 Full-Year Financial Results · Ranjan Jindal (CFO)

  • Record revenue: ₹4,800 crore, up 40% YoY
  • Sales volume: 3.3 GW (+76% from 1.9 GW in FY25) — first time crossing 3 GW shipment mark
  • EBITDA: ₹917 crore; margin expanded to 19% (+500 bps from 14% in FY25) — operating leverage from expanded capacity
  • PAT: ₹470 crore (10% PAT margin) — meaningful milestone to build on consistently

Q4 FY26 Financial Performance · Ranjan Jindal (CFO)

  • Revenue: ₹1,450 crore (+31% sequentially); EBITDA: ₹235 crore (16% margin); PAT: ₹110 crore
  • 1 GW quarterly run rate provides useful operating baseline going into FY27

Balance Sheet Strength · Ranjan Jindal (CFO)

  • Net working capital cycle compressed from 82 days in FY25 to 44 days in FY26
  • No long-term debt; working capital net debt at just ₹64 crore
  • Net debt-to-equity ratio of 0.03 — strong platform for next capex cycle

Order Book & Business Model · Ranjan Jindal (CFO)

  • Order book: 8.2 GW as on 31 March 2026 — mix: IPPs 69%, C&I 13%, Government and EPC 18%
  • Distribution channel: ~20% of FY26 volumes; distributor network expanded to 110+ distributors and 550+ exclusive dealers/system integrators
  • ~80% of order book carries cell price pass-through clauses — insulates P&L from input volatility
  • Per-watt overhead reduced 16% full-year as volumes scaled
  • Cumulative global module deployment crossed 10 GW (25 million+ modules); scaled from 5 GW to 10 GW in two years

FY26 Market Performance & Cyclical Dynamics · Ranjan Jindal (CFO)

  • Utility-scale projects led with record 34 GW additions in FY26; rooftop solar crossed 8.5 GW (powered by PM Surya Ghar Yojana)
  • FY26 faced strongest demand environment alongside cyclical supply-side pressures — a cycle scaled integrated manufacturers are built to absorb
  • Cell costs rose on higher silver prices and removal of China's export VAT rebate; domestic ecosystem scaling brings competitive pricing dynamics

DCR Market Opportunity & FY27 Strategy · Ranjan Jindal (CFO)

  • FY27 production: predominantly non-DCR (~75%), with DCR (~25%) enabled by 2 GW procurement agreement with Jupiter International
  • Strong demand runway: 80+ GW of grandfathered non-DCR demand over next two years; ~28 GW live utility-scale DCR tenders; ~25 GW inherent DCR from C&I, KUSUM, rooftop
  • Company proactively positioned for DCR opportunity including 2 GW cell procurement deal
  • PM Surya Ghar distribution channel now accessible with DCR cell availability — provides better margins than non-DCR

Integrated Capacity Roadmap · Ranjan Jindal (CFO)

  • Module: 9.5 GW today → 15.5 GW once Gangaikondan 6 GW commissions June 2026
  • Cell: 9 GW TOPCon on track for phased commissioning Q4 FY27; first cell December 2026 (~70% backward integration); additional 3 GW in FY28 completes full cell integration
  • Wafer/ingot: 12 GW facility — first 6 GW phase at Gangaikondan approved by Board; ~₹3,700 crore outlay; commissioning March 2028; second 6 GW to follow (Board approval in subsequent year)
  • BESS: 5 GWh cell-to-pack facility by March 2027; first phase 7.5 GWh battery cell manufacturing in FY29; second phase FY30 — total 15 GWh by FY30

Capital Discipline & Financing Framework · Ranjan Jindal (CFO)

  • Capex to be funded with disciplined mix of debt and equity; capital prudence non-negotiable
  • Interest and debt service coverage ratios maintained above 2.5; net debt-to-equity below 1.5 even at peak debt drawdown
  • Phasing of capex, sequencing of debt tranches, and build-up of internal accruals calibrated to stay within guardrails
  • Growth ambition will not come at cost of balance sheet discipline

In their words

Energy independence is sovereignty — this captures exactly the moment we are operating in.
Gyanesh Chaudhary (CMD, Vikram Solar)
What you are seeing this quarter is the early innings of a multi-year trajectory of strong growth for this company.
Sameer Nagpal (CEO, Vikram Solar)
Every key metric — revenue, volumes, EBITDA, PAT — has reached an all-time high.
Ranjan Jindal (CFO, Vikram Solar)

To check next time

What management committed to on this call, or the dates they gave.

  • Commissioning of Gangaikondan 6 GW module plant, targeted June 2026.
  • First cell output from 9 GW TOPCon plant at Gangaikondan, targeted end-December 2026 / early January 2027.
  • Siemens power infrastructure commissioning in November 2026 and utilities build-out in December 2026.
  • Debt level at 31 March 2027; management indicated ₹3,200 cr closing.
  • FY27 production and EBITDA run-rate vs 7.5-8 GW / ₹1,500-1,600 cr guidance.
  • DCR vs non-DCR order book mix shift post June 2026 cell-level mandate and execution of 2 GW Jupiter procurement.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Fri 8 May 2026₹214.74−4.67%−0.62%
5 sessions Thu 14 May 2026₹206.79−8.20%−2.62%
20 sessions Fri 5 Jun 2026₹213.04−5.42%−3.95%

From the close of Thu 7 May 2026, ₹225.25: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Vikram Solar's other calls

  • Q2 FY27Mon 16 Nov 2026Tone: Mixed
  • Q1 FY27Fri 7 Aug 2026Tone: Mixed
  • Q3 FY26Tue 20 Jan 2026Tone: Confident
  • Q2 FY26Fri 17 Oct 2025Tone: Confident
  • Q1 FY26Wed 10 Sept 2025Tone: Confident