Ahluwalia Cont Ind Q1 FY25 earnings call

Fri 16 Aug 2024AHLUCONT

In brief

Management's tone
Cautious
What was said
Even-handed
Guidance
Guidance held
Analyst pushback
Low
Stock, next session
+4.13% (Nifty 50 +1.65%)
  • Q1FY25 EBITDA margin collapsed to 6.58% (vs 10.83% YoY) on elections, monsoons, CSMT design revamp, and Rs 6.2 cr NCLT write-off; management still targets double-digit margin for full-year FY25 and 11% in H2.
  • Revenue growth guidance retained at 15-20% for FY25 and expected to continue in FY26; net order book at Rs 13,144 cr (30 Jun), proforma Rs 15,500 cr after post-quarter wins, with Rs 2,500-3,500 cr further inflow targeted.
  • Strategic pivot to private sector: ~40-50% of book today, long-term 50:50 target; couple of percentage points margin uplift cited from private mix vs government.
  • FY25 capex guided at ~Rs 175 cr (Rs 54 cr Q1 + Rs 120 cr balance); FY26 capex to taper to Rs 120-125 cr; balance sheet remains near-zero-debt with Rs 248 cr cash + Rs 456 cr bank balance.
  • Data centers explicitly de-prioritised (margins 'not commensurate'); hotel sector at only 1.5% of book; bidding stance deliberately conservative, not aggressive.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q1 FY25

This quarterA year agoLast quarterMargin
Revenue₹919 cr+20.4%−21.0%
EBITDA (excl. other income)₹60.4 cr−26.9%−79.8%6.6% (10.8% a year ago)
Net profit₹0 cr——0% (6.5% a year ago)
EPS (₹)₹4.56−38.5%−84.7%

From the company's filed results for the quarter ended 30 Jun 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

The numbers management led with

  • Net order book: Rs 13,143.72 crore as of 30 June 2024; proforma Rs 15,500 crore including post-quarter wins
  • FY25 order inflow YTD: Rs 4,945.54 crore (Rs 2,727.93 cr in Q1 + Rs 2,217.61 cr post-quarter)
  • FY25 capex: Rs 54 cr spent in Q1; Rs 120 cr more planned (total ~Rs 175 cr)

Guidance

Guidance on this call

WhatForWhat management saidOn the Q4 FY24 call
Revenue growthFY25 and FY2615-20% revenue growth for FY25, similar run rate expected to continue in FY26 (held)15-20% for FY25 and FY26
EBITDA marginFY25, FY26, medium-termDouble-digit (>10%) margin for full-year FY25; ~11% in H2 FY25; ~11% in FY26; 'double digit' medium term (FY26-FY27) (held)More than 10% for FY25 (revised down from earlier >11%); 9% called as the floor in Q4 FY24
Order inflowBalance of FY25Additional Rs 2,500-3,500 cr of inflows for balance of FY25; bid pipeline Rs 5,000-6,000 crINR2,500-INR3,000 crores incremental in FY25 on top of INR4,000 crores L1 conversion (FY25 total aspiration ~INR7,000 crores)
CapexFY25 and FY26~Rs 175 cr for FY25 (Rs 54 cr Q1 + Rs 120 cr balance); Rs 120-125 cr for FY26~INR110 crores for FY25
CSMT project revenueFY25 and FY26Rs 450-500 cr in FY25, ~Rs 1,000 cr in FY26 (~Rs 100 cr/month run rate)—
Gems & Jewellery project revenueFY25 and FY26Rs 125-150 cr in FY25, material in FY26—
Said on the Q4 FY24 call, not repeated on this one (1)
  • Private-sector order mix: Long-term target of 50:50 government-private mix (vs current 65:35)

Guided on earlier calls, and what was filed

WhatForGuidedFiled
Q1 FY25 EBITDA margin floorQ1 FY25at least 9% (on the Q4 FY24 call)6.6%, below the range
Consolidated revenue growthFY2515–20% (on the Q4 FY24 call)6.3%, below the range
Consolidated EBITDA marginFY25at least 10% (on the Q4 FY24 call)8.3%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

The industry, as management sees it

Management sees the broader construction industry moving towards more complex high-rise, EPC-style work with rising private-sector share; sees government infrastructure pace picking up post-elections but flags labour and skill shortage as a structural, perennial issue requiring collective ecosystem action (standardised design, labour escalation clauses).

Risks management named

  • Labour and skill shortage described as a 'perennial problem' that the industry must collectively address
  • Existing jobs without labour escalation clauses exposed to wage inflation; margin already impacted in Q1
  • State-government payment delays in Bihar medical colleges/hospitals; only ~10% of those jobs remain
  • CSTM project still subject to weather and design-change risk despite redesign being finalised
  • Surprise NCLT exposures on clients (Rs 6.2 cr written off in Q1) cannot be fully ruled out
  • Data center and hotel segments deprioritised but may still consume bandwidth opportunistically

Q&A

Q&A was dominated by two themes: (1) explaining the Q1 margin compression and the path back to double-digit margins, where management was consistent and detailed, attributing the gap to elections, CSTM redesign, monsoons, NCLT write-offs and elevated staff/subcontract costs, and reaffirming ~11% H2 margins; and (2) the strategic shift towards private sector and larger ticket sizes, where management was unambiguous. Pushback was minimal — analysts accepted the explanations, and the few hard data requests (working capital lines, fixed-price share, mobilization advance) were answered crisply. The only soft spots were on Emaar recovery timing (deferred) and the scope of further NCLT exposures (evasive).

Not answered directly

  • Emaar settlement receipt date
  • Scope of further NCLT write-offs

Every question, with its answer

  1. 1. Q1 margin walk

    Mohit Kumar, ICICI Securities

    Question. Q1 margin at 6.5% looks weak; what drove the compression and how do you see margins for the rest of the year given the earlier 11% guidance for FY25?

    Answer, Shobhit Uppal, Deputy Managing Director. Cited four reasons: (1) lower turnover in Q1 due to election-related labour disruption, with May and June running at ~40% pan-India labour; (2) CSTM project turnover was only ~Rs 30 cr vs plan because the client-mandated concept had to be revamped for local bylaws and greenfield tree-cutting issues; (3) June/July monsoon write-offs, especially in Mumbai; (4) higher staff cost from hiring for the order book plus Rs 6.20 cr of NCLT-driven write-offs on two clients. Maintained double-digit full-year margin and expects Q3-Q4 to be stronger as usual.

    Follow-up. What is your view on margins for the full fiscal year?

    Answer. Stated Q1 was flagged last quarter as election-impacted and Q2 will be monsoon-impacted; Q3 and Q4 traditionally see higher run rate and margins, so full-year double-digit margins are still expected. Q2 specifically expected to be muted.

  2. 2. Labour shortage

    Mohit Kumar, ICICI Securities

    Question. Are labour issues still continuing post-elections or have they eased?

    Answer, Shobhit Uppal, Deputy Managing Director. Elections did impact labour in a big way — May and June were running at ~40% pan-India labour; situation is now improving. However, labour/skill shortage is a 'perennial problem' with many projects launched; it is here to stay and the entire ecosystem will have to find ways to combat it.

  3. 3. Subcontractor costs

    Sunny Roy, Individual Investor

    Question. Subcontract work charges rose ~40% YoY against ~20% revenue growth — what drove the disproportionate increase?

    Answer, Shobhit Uppal, Deputy Managing Director. Subcontracting has two components: subcontract with material and pure labour (shuttering, bar-bending, stone contractors). Labour is part of the cost and with lower turnover, the per-unit subcontract cost looks higher. Q2 will also see elevated subcontract cost; should normalise in H2.

    Follow-up. Should we expect this to normalise going forward? And given labour issues, are double-digit EBITDA margins realistic?

    Answer. Yes, will normalise in H2; Q2 elevated. On Rs 4,500-5,000 cr of new wins priced with higher labour costs, those projects ramp up in Q3-Q4 and should support double-digit margins.

  4. 4. Bidding strategy

    Sunny Roy, Individual Investor

    Question. With order book at ~Rs 4,900 cr already, will bidding be aggressive for the balance of the year or conservative?

    Answer, Shobhit Uppal, Deputy Managing Director. 'We are not bidding aggressively. Even in this quarter, we have not bid aggressively.'

  5. 5. Q2 margin outlook

    Shravan, Dolat Capital

    Question. On Q2 — should we expect margin closer to 8-9% given the monsoon impact?

    Answer, Shobhit Uppal, Deputy Managing Director. Margin should go up vs Q1 because elections are over and labour is improving. CSTM should also pick up in September. There will be an increase in Q2 but not a substantial one; the substantial increase is in H2.

    Follow-up. So in H2 should we expect 10.5-11% margin, and can that run rate continue into FY26?

    Answer. Confirmed 11% margin in H2. Expects this to continue into FY26 because focus is shifting more to private sector where competition is less and rates are better.

  6. 6. Revenue guidance

    Shravan, Dolat Capital

    Question. Is FY25 revenue growth guidance maintained at ~20%? And similar run rate for FY26?

    Answer, Shobhit Uppal, Deputy Managing Director. Corrected to 15-20% for FY25; similar run rate can be maintained in FY26.

  7. 7. Order inflow pipeline

    Shravan, Dolat Capital

    Question. On inflow — with Rs 4,946 cr already booked, how much more can we expect and what is the bid pipeline?

    Answer, Shobhit Uppal, Deputy Managing Director. Additional Rs 2,500-3,500 cr of inflows expected for the balance of FY25; bid pipeline of Rs 5,000-6,000 cr.

  8. 8. Balance sheet items

    Shravan, Dolat Capital

    Question. Can you share balance-sheet working capital numbers — inventory, debtors, creditors, mobilization advance, unbilled revenue?

    Answer, Satbeer Singh, Chief Financial Officer. Debtors Rs 811 cr; retention Rs 327 cr (including non-current); mobilization advance Rs 541 cr; trade payables Rs 706 cr; inventory Rs 354 cr; unbilled revenue Rs 489 cr; gross debt Rs 100 cr; cash and cash equivalents Rs 248 cr; bank balance Rs 456 cr.

  9. 9. Gems & Jewellery project

    Vaibhav Shah, JM Financials

    Question. Update on big-ticket projects — when does the Gems & Jewellery project start and what revenue is targeted in FY25?

    Answer, Shobhit Uppal, Deputy Managing Director. Work will start in about 3 months; FY25 revenue target Rs 125-150 cr; should be a material number in FY26.

  10. 10. CSMT project ramp-up

    Vaibhav Shah, JM Financials

    Question. On CSMT — given muted Q1 and first two months of Q2, what is the FY25 and FY26 revenue target from this project?

    Answer, Shobhit Uppal, Deputy Managing Director. FY25 target Rs 450-500 cr; FY26 target ~Rs 1,000 cr. The Rs 100 cr/month run rate from H2 will be from FY26. The redesign was forced because the international concept design violated local bylaws; client has accepted the revamp and ground work has just begun, though June and July rains have hit. Margins are not impacted because specification changes are billed as extras.

    Follow-up. Does the redesign impact project cost or margin?

    Answer. No, optimal redesign preserves parameters; any specification changes will be paid by client as extra items.

  11. 11. Animal husbandry project

    Vaibhav Shah, JM Financials

    Question. On the animal husbandry project — execution was soft in Q1, will the previously guided Q1FY26 completion slip?

    Answer, Shobhit Uppal, Deputy Managing Director. ~90% of the area has been handed over (university buildings being vacated/dismantled), so progress is already picking up and will pick up substantially.

  12. 12. State payment delays

    Vaibhav Shah, JM Financials

    Question. Any payment challenges from particular state governments post-election?

    Answer, Shobhit Uppal, Deputy Managing Director. There were challenges, but movement has begun in Bihar with central funds flowing. Veterinary/BASU funding has not been an issue, but medical college/hospital payments were stuck. Expects stuck payments to start coming in within 1-1.5 months; only ~10% of Chakra and Nalanda jobs remain and should be completed this year.

  13. 13. Airport projects

    Vaibhav Shah, JM Financials

    Question. On Darbhanga and Varanasi airports recently won — when will work start?

    Answer, Shobhit Uppal, Deputy Managing Director. Design is underway; design team is in interaction with AI (Airports Authority). Expects to break ground in ~2 months.

  14. 14. Labour cost recovery

    Raj Shah, Marcellus Investment Managers

    Question. On labour shortage: how do you make up for the cost overrun on existing orders, and how is it priced into new bids?

    Answer, Shobhit Uppal, Deputy Managing Director. Some existing projects have labour escalation clauses that cover cost; others do not, and that has hit Q1 margins. For new bids, the company is extrapolating the past one year's labour cost increase into pricing.

    Follow-up. On Sion Hospital Mumbai — confirming you have bid for it; will it be a large contract above Rs 1,000 cr?

    Answer. Confirmed bidding for Sion Hospital Phase-2 (after winning Phase-1); described it as a 'large contract' without giving a number.

    Partly answered.

  15. 15. Public vs private margin

    Rishi Kothari, Pi Square Investments

    Question. What margin uplift comes from shifting from public to private sector contracts?

    Answer, Shobhit Uppal, Deputy Managing Director. 'A couple of percentage points' over the next year — government sector has increased competition while private sector contracts are more complex (high-rise) with limited competition and better rates.

    Follow-up. Does the company have the technology and capability to execute complex private contracts?

    Answer. Yes — 'we were already doing it. We have done it in the past. We are doing it now.'

  16. 16. Data centre exposure

    Rishi Kothari, Pi Square Investments

    Question. Are we involved in the data centre segment and if so, what is the approach?

    Answer, Shobhit Uppal, Deputy Managing Director. Confirmed working on data centres for Adani, Google, RBI and others but stated it is 'not a focus area' — margins are 'not commensurate' with bandwidth required. Will continue to take one-off jobs but not build capability.

    Follow-up. On private vs public mix — currently 40-50% private, is there a target to push it higher?

    Answer. Long-term target is 50:50 between public and private.

  17. 17. Fixed-price exposure

    Uttam Kumar Srimal, Axis Securities

    Question. What is the share of fixed-price contracts in the order book, and is the Rs 13,000 cr book inclusive of Rs 4,900 cr of new wins?

    Answer, Satbeer Singh, Chief Financial Officer. Fixed-price contracts are 24% of the order book. The Rs 13,144 cr is as of 30 June; including Rs 2,200 cr of post-quarter wins, total order book is ~Rs 15,500 cr.

    Follow-up. Any L1 status currently, and are new orders being bid at 11-12% EBITDA margin?

    Answer. No L1 status; recent bids have been primarily private sector. Yes, 11-12% EBITDA margin is the target on the last 3-4 months' bids.

  18. 18. Order book consolidation

    Prem Khurana, Anand Rathi

    Question. With two large >Rs 2,000 cr orders in the backlog, was scaling up average project size a conscious decision to address labour issues?

    Answer, Shobhit Uppal, Deputy Managing Director. Yes, this has been a conscious decision over the last 4-5 years. Company has built in-house EPC-style capabilities across multiple disciplines, enabling qualification for larger jobs in both public and private sectors.

    Follow-up. Do you build higher contingencies on larger jobs and is competition lower for them?

    Answer. Geographical footprint has been organic and planned. In every state (17 in total) and in clusters like NCR/Gurgaon within 15-20 km, multiple projects are run to hedge risk and spread overheads — citing ~20 million sq ft within a 20 km radius in NCR.

  19. 19. Capital allocation

    Prem Khurana, Anand Rathi

    Question. With Rs 700 cr+ cash and positive OCF, any thoughts on larger capital distribution to shareholders?

    Answer, Shobhit Uppal, Deputy Managing Director. The company is spending on mechanisation and digital transformation (SAP and other IT) to prepare for a 'quantum jump'. Will continue paying dividends but has not thought beyond that on capital distribution.

    Follow-up. Capex for the year and how much was already spent in Q1?

    Answer. Q1 capex Rs 54 cr; balance of Rs 120 cr planned, implying ~Rs 175 cr for FY25.

    Partly answered.

  20. 20. Emaar settlement

    Prem Khurana, Anand Rathi

    Question. Was the Emaar settlement amount expected in August received?

    Answer, Shobhit Uppal, Deputy Managing Director. Payment date is 31 August; 'not in a position to comment' but confirmed it is a 'signed and sealed agreement'.

    Not answered directly.

  21. 21. Hotel sector strategy

    Sunny Roy, Individual Investor

    Question. Hotels are only 1.5% / Rs 195 cr of the order book — is this a conscious deprioritisation?

    Answer, Shobhit Uppal, Deputy Managing Director. Yes — project sizes from hoteliers don't excite, and hoteliers 'cannibalise' these projects. Bandwidth is the constraint; not looking at this segment favourably.

    Follow-up. Given buoyancy in residential, can the 13.7% share go higher or is it being capped below 15%?

    Answer. Residential share will go up and cross 20%. Combined with the private-sector push, the target is 50:50 public:private over time.

  22. 22. Working capital

    Ketan Jain, Avendus Spark

    Question. With bigger ticket sizes, are you seeing any working capital issues or plans to address them?

    Answer, Shobhit Uppal, Deputy Managing Director. No working capital issues expected. Shift to private sector, blue-chip developers, RERA-mandated 3-3.5 year delivery timelines, and healthy reserves all support this. Net debt is effectively zero and focus is on reducing the small remaining debt, not increasing it.

  23. 23. Capex outlook

    Vaibhav Shah, JM Financials

    Question. On FY25 capex of ~Rs 175 cr — will FY26 capex grow further or come down?

    Answer, Shobhit Uppal, Deputy Managing Director. FY26 capex will come down to ~Rs 120-125 cr.

    Follow-up. Out of mobilization advance of ~Rs 540 cr, what portion is interest-bearing?

    Answer. 54% is interest-bearing.

  24. 24. Gems & Jewellery project funding

    Parikshit, HDFC Securities

    Question. On the Gems & Jewellery project — who is funding it and is financial closure achieved?

    Answer, Vikas Ahluwalia, Whole-Time Director. Modelled on the Bharat Diamond Bourse (BDB). It is an autonomous body under the Ministry of Economic Affairs, funded by a group of wealthy jewelers (largely Gujarat-based, some from South) with some GoI and state government equity; has a board with central and state nominees.

    Follow-up. So payments are not contingent on unit sales like at BDB?

    Answer. No, payments are 'dependent on the board how much board pays us' — i.e., not strictly tied to unit sales, but the board decides pay-outs.

    Partly answered.

  25. 25. South market ramp-up

    Parikshit, HDFC Securities

    Question. On southern markets — when will private order flow pick up given RERA is now in place?

    Answer, Shobhit Uppal, Deputy Managing Director. Recently bagged Birla Realty (Kumar Mangalam Birla's company) in the South; bidding for 3-4 other large private players and a couple of large private hospitals. Focus areas are Bangalore (regional office) and Hyderabad; will grow cautiously given past South experience.

    Follow-up. On margin recovery — historically 12-13%, now high single digit; what gives confidence that worst is behind?

    Answer. H2 is traditionally stronger in topline and margins. Q1 issues (elections, CSMT, monsoons) are largely in the rear-view for H2. Labour will remain a structural issue but the ecosystem (developers, clients, government) is now aligning — standardising design, agreeing to escalation clauses — which should support margins over time.

    Partly answered.

  26. 26. NCLT write-off

    Parikshit, HDFC Securities

    Question. On the Rs 6.2 cr NCLT write-off — what is the nature and are more one-off surprises likely?

    Answer, Shobhit Uppal, Deputy Managing Director. Two clients were taken to NCLT by creditors, forcing a provision. 'We can't really say' if more will come; some clients are expected to ultimately honour commitments but provisions had to be made. Said last quarter there should not be more surprises, but 'this is a surprise'.

    Not answered directly.

  27. 27. Emaar accounting

    Ketan Jain, Avendus Spark

    Question. Will the Emaar receivable received in FY25 be booked as other income or how is it recognised?

    Answer, Management. Emaar settlement was recognised as an exceptional gain in FY24. Rs 124 cr is currently reflecting as outstanding (including debtors). No additional items to be recognised in FY25 at present.

  28. 28. Industry growth opportunity

    Gaurav Gandhi, Glorytail Capital Management

    Question. On Make-in-India / state-of-the-art construction opportunity — how big is it and are you positioned for higher inflows than currently projected?

    Answer, Shobhit Uppal, Deputy Managing Director. Buildings are becoming more complex and the company is uniquely positioned given its track record on high-rises (e.g. 40-45 storey project in NCR/Gurgaon). On a higher-than-projected inflow scenario, the company is 'proceeding with caution' given the labour issue and the already-healthy order book.

    Follow-up. Is the India Jewellery Park project politically sensitive — could state government change slow execution?

    Answer. Vikas Ahluwalia: 'No, this is not a political project. It is an autonomous body, and largely the members of this body are private.' The project is expected to create ~40,000 jobs which is why it draws political attention.

  29. 29. State government project strategy

    Parvez Kazi, Individual Investor

    Question. Post-election, what is the thought process on taking state-government projects in Bihar or other states?

    Answer, Shobhit Uppal, Deputy Managing Director. Stays away from states at loggerheads with the centre and cash-strapped; hence no new Bengal projects. Bihar — was waiting and watching, now with the same party at centre and state, fund position is improving and the company is open to bidding. Assam remains a focus state with Rs 2,000+ cr of projects; fund position there is also fine.

    Follow-up. Views on bidding in Andhra Pradesh, especially the Amravati capital city project?

    Answer. Not a focus. Down South, focus is on the private sector and growth will be cautious given past experience; government projects down South are not a focus area.

  30. 30. Medium-term margin outlook

    Parvez Kazi, Individual Investor

    Question. Medium term — where do you expect EBITDA margins to settle in FY26 and FY27 once near-term issues normalise?

    Answer, Shobhit Uppal, Deputy Managing Director. 'Double digit.'

What was said

Topic by topic, in the order it was spoken

Q1FY25 Headline Results · Shobhit Uppal (Deputy Managing Director)

  • Turnover Rs 919.35 cr in Q1FY25 vs Rs 763.61 cr in Q1FY24, growth of 20.39% YoY
  • PAT at Rs 30.60 cr vs Rs 49.73 cr YoY; EPS Rs 4.57 vs Rs 7.42
  • EBITDA margin compressed to 6.58% (vs 10.83% YoY); PAT margin 3.33% (vs 6.51%)
  • Net order book of Rs 13,143.72 cr as of 30 June 2024, executable in 2.5-3 years
  • FY25 order inflow YTD: Rs 2,727.93 cr in Q1 + Rs 2,217.61 cr post-quarter = Rs 4,945.54 cr

In their words

Labor shortage is here to stay, so we will have to find out ways and means to combat this collectively. All the constituents of the ecosystems will have to come together to see how we can mitigate this problem.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)
We are not bidding aggressively. Even in this quarter, we have not bid aggressively.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)
It should, because in an answer to the earlier question, we are not bidding aggressively. Our focus, which I mentioned last time, has shifted more to the private sector.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Fri 16 Aug 2024₹1,320.40+4.13%+1.65%
5 sessions Thu 22 Aug 2024₹1,302.00+2.68%+2.77%
20 sessions Thu 12 Sept 2024₹1,178.30−7.08%+5.16%

From the close of Wed 14 Aug 2024, ₹1,268.05: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Ahluwalia Cont Ind's other calls

  • Q2 FY27Mon 16 Nov 2026Tone: Mixed
  • Q1 FY27Mon 17 Aug 2026Tone: Defensive
  • Q4 FY26Mon 1 Jun 2026Tone: Mixed
  • Q3 FY26Mon 16 Feb 2026Tone: Cautious
  • Q2 FY26Mon 17 Nov 2025Tone: Confident
  • Q1 FY26Mon 18 Aug 2025Tone: Confident
  • Q4 FY25Mon 2 Jun 2025Tone: Confident
  • Q3 FY25Wed 12 Feb 2025Tone: Cautious
  • Q4 FY24Thu 30 May 2024Tone: Cautious