Ahluwalia Cont Ind Q4 FY26 earnings call
In brief
FY26 revenue rose 11% to ₹4,565 cr, PAT up 31%; guides 15-20% FY27 revenue growth and double-digit margin, ₹21,096 cr order book.
- Management's tone
- Mixed
- What was said
- Leaned positive
- Guidance
- Guidance raised
- Analyst pushback
- Medium
- Stock, next session
- −3.58% (Nifty 50 −0.70%)
- Guided 15-20% revenue growth for FY27 versus 11.4% in FY26, with ₹21,096 cr order book providing visibility for 24-30 months.
- Targets double-digit EBITDA margin in FY27 versus 9.52% in FY26, citing 89% of order book having inbuilt escalation clauses.
- FY26 revenue grew 11.38% to ₹4,565.20 cr and PAT rose 31.17% to ₹264.32 cr; net worth crossed ₹2,000 cr.
- FY27 order inflow target ~₹8,000 cr; L1 in two projects worth ₹1,620.95 cr (RML Hospital Delhi, Odisha university).
- FY27 capex guided at ~₹300 cr, down from earlier ~₹500 cr guidance, as efficiency gains emerged.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q4 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹1,322 cr | +8.8% | +24.7% | |
| EBITDA (excl. other income) | ₹126 cr | +1.4% | +30.6% | 9.5% (10.2% a year ago) |
| Net profit | ₹82 cr | — | +51.7% | 6.2% (0% a year ago) |
| EPS (₹) | ₹24.48 | +96.8% | +203.3% |
From the company's filed results for the quarter ended 31 Mar 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
What moved the numbers, as management explained it
- Q4 FY26 hit by Bengal SIR, NCR labor exodus for elections and Assam cash crunch, leaving March nearly a write-off; NGT shutdown in January also cut execution. (one-off)
- War impact from end-February: LPG shortage, labor fleeing native places and supply chain delays (panels now 4+ months vs 2 months earlier) added to overheads and IDCs. (one-off)
- Built up staff and salary increments ahead of order book ramp-up, with revenue absorption delayed by disruptions; top line would have been higher absent these impacts.
- WPI-linked escalation lagged actual commodity inflation, partly compressing margin; private pass-through clauses covered cement/steel on private projects.
- Q4 EBITDA margin at 9.35% vs 10.17% in Q4 FY25; PAT margin 5.95% vs 6.74%, as volume and cost absorption did not keep pace with fixed-cost and IDC build-up.
The numbers management led with
- FY27 revenue growth guidance: 15–20%
- FY27 order inflow target: INR8,000 crores (including L1 of INR1,620.95 cr)
- FY27 capex: ~INR274 cr (revised down from prior INR500 cr); FY27 guided ~INR300 cr
- Cash and bank balance: INR817 crores as of 31 March 2026
- Net order book: INR21,096.31 crores executable over 24–30 months
- FY27 project execution targets: Central Vista ~INR1,000 cr; CSMT ~INR600 cr; Dahlias ~INR400 cr; IJPM ~INR100 cr
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| FY27 revenue growth | FY27 | 15% to 20% revenue growth in FY27 |
| FY27 EBITDA margin (double-digit) | FY27 | Double-digit EBITDA margin in FY27 (from 9.52% in FY26) |
| FY27 order inflow | FY27 | Order inflow target of about ₹8,000 cr in FY27 (including the L1 projects) |
| FY27 capex | FY27 | Capex of around ₹300 cr in FY27 |
| FY27 CSMT execution (CSMT project) | FY27 | Around ₹600 cr execution from CSMT in FY27 |
| FY27 Central Vista execution (Central Vista project) | FY27 | About ₹1,000 cr execution from Central Vista in FY27 |
| FY27 Dahlias execution (Dahlias project) | FY27 | About ₹400 cr execution from Dahlias in FY27 |
| FY27 IJPM execution (India Jewellery Park project) | FY27 | Modest target of about ₹100 cr from IJPM in FY27 |
| Central Vista monthly run rate (Central Vista project) | FY27 | Central Vista to log ₹100-150 cr turnover per month |
| Mobilization advance level | FY27 | Mobilization advance to stay at current level (~₹800 cr) in FY27 |
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| Q1 FY25 EBITDA margin floor | Q1 FY25 | at least 9% (on the Q4 FY24 call) | 6.6%, below the range |
| Consolidated revenue growth | FY25 | 15–20% (on the Q4 FY24 call) | 6.3%, below the range |
| Consolidated EBITDA margin | FY25 | at least 10% (on the Q4 FY24 call) | 8.3%, below the range |
| FY26 revenue growth | FY26 | 15% (on the Q4 FY25 call) | 35.9%, above the figure guided |
| FY26 revenue growth | FY26 | 15–20% (on the Q1 FY26 call) | 35.9%, above the range |
| Consolidated revenue growth | FY26 | 15–20% (on the Q2 FY26 call) | 35.9%, above the range |
| FY26 top line growth | FY26 | 10–15% (on the Q3 FY26 call) | 35.9%, above the range |
| Q4 FY26 revenue | Q4 FY26 | ₹1,400 cr (on the Q3 FY26 call) | ₹1,322 cr, below the figure guided |
| FY26 EBITDA margin | FY26 | at least 10% (on the Q3 FY26 call) | 9.4%, below the range |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
Balance sheet, capex and funding
- Cash and bank balance at ₹817 cr; company remains debt-free with net worth crossing ₹2,000 cr.
- Mobilization advance ₹802 cr (about 37% interest-bearing), guided to stay at similar level in FY27.
- Working capital days at 104 (vs 103 a year ago); management views this as the standard run rate.
- FY26 capex spent ₹274 cr (cut from earlier ~₹500 cr guidance on efficiency); FY27 capex guided at ~₹300 cr.
- Depreciation rose to ₹66-97 cr for FY26; Q4 FY26 depreciation around ₹29 cr, expected to scale with FY27 capex.
- Unbilled revenue ₹688 cr, retention money ₹450 cr, margin money ~₹200 cr; CSMT order value now shown as ₹2,076 cr ex-GST (vs ₹2,450 cr earlier).
The industry, as management sees it
Management sees the Indian building construction industry at an inflection point: order sizes have grown materially, timelines are squeezed, building complexity has risen (40–60 storey structures requiring 4–5 cranes per project), and labour shortage is now structural rather than seasonal. Industry-wide EBITDA margins have compressed from historical highs of 12–14% to the 9–10% range, with mechanisation and standardisation expected to drive gradual recovery rather than an immediate jump. NGT-driven NCR shutdowns and supply chain disruptions on MEP/switchgear are expected to persist in the near term.
Risks management named
- Prolonged war impact on commodity prices and rupee-dollar could pressure margins where WPI escalation lags
- NGT-driven NCR construction bans remain a recurring risk though partially mitigated by client labour cost support
- Structural labour shortage and skill deficit expected to persist for 3–4 years
- Central Vista and IJPM both dependent on single client and ongoing design changes
- Supply chain disruption on switchgear, panels, MEP and chillers extending project timelines
- Fixed-price portion of order book (~11%) exposed to commodity inflation
Q&A
Q&A was dominated by three themes: (1) margin trajectory and capex-to-EBITDA linkage, with analysts pressing on whether the INR500 cr+ cumulative capex would translate into a 10%+ EBITDA margin and questioning the absence of a buyback despite INR817 cr net cash; (2) execution ramp on flagship projects — Central Vista, CSMT, IJPM and Varanasi airport — with management confidently assigning INR1,000 cr / INR600 cr / INR400 cr FY27 targets; and (3) macro headwinds from the war (LPG, fuel, supply chain) and labour/NGT disruptions. Pushback was most intense on capital allocation (two separate buyback requests, both deflected) and on guidance sharpness for FY28. No questions on governance, accounting or related-party issues.
Not answered directly
- FY28 revenue and margin guidance
- Q4 FY25 order inflow comparison (deferred to offline)
- Maximum historical single-project write-off (deferred to CFO follow-up)
- Pre-investment glory days of 13–14% EBITDA margin
- Buyback or special dividend
Asked for a number, answered without one
- Q4 FY25 order inflow for comparison: CFO said he would need to check and get back; suggested the analyst reach out directly to him for the data.
- Mechanization capex IRR and EBITDA uplift: MD said it is difficult to give an absolute number; payback cited at 4-5 years with life of 4-5 years, but no specific IRR or margin delta was given; said the industry is changing too rapidly to attribute a precise EBITDA percentage to specific capex.
- IJPM execution quantum beyond FY27: MD said design changes are still happening, so the projection is kept conservative; would not comment further on project quantum.
Every question, with its answer
1. Order inflow and execution ramp
Shravan Shah, Dolat Capital
Question. You are L1 in two projects — can you specify? With INR21,000 cr order book plus INR1,600 cr L1, execution should ramp significantly in FY27–28. What kind of revenue growth can we look at for FY27 and FY28?
Answer, Shobhit Uppal, Deputy Managing Director. Confirmed order execution will ramp up. We are giving guidance of 15% to 20% in this year (FY27). On order inflow, target is about INR8,000 crores, including the L1. On FY28, we do not want to give guidance given war-related uncertainty.
Follow-up. Analyst pressed: even 15–20% seems lower, FY28 could be much higher?
Answer. Management reiterated FY27 guidance of 15–20% and declined to extend to FY28 citing uncertain macro environment, even while noting improved state-level political stability.
2. Margin trajectory
Shravan Shah, Dolat Capital
Question. FY26 full-year margin was 9.5% — should be at least 10%. How should we look at margins in H1 given commodity run-up due to the war?
Answer, Shobhit Uppal, Deputy Managing Director. Indicated double-digit margin is the target. Q4 was hit by elections in Bengal, Assam cash crunch, and labour flight from NCR (40–50% of projects) post SIR. Despite these headwinds, FY26 margin reached 9.5%, in line with prior guidance. We will cross into double digits in FY27.
3. Balance sheet data points
Shravan Shah, Dolat Capital
Question. Data points please — mobilization advance, retention money and unbilled revenue?
Answer, Satbeer Singh, Chief Financial Officer. Mobilization advance INR802 cr; retention INR450 cr; unbilled revenue INR688 cr.
Follow-up. On CSTM, Q3 order book vs current suggests INR470 cr execution; any adjustment? And execution outlook for FY27–28 across Indian Jewellery Park, Central Vista INR2,600 cr?
Answer. Management: CSMT design is now approved and execution has picked up speed. Central Vista (awarded 14 January) — design freezing underway, Nirman Bhawan demolished, excavation and concrete started; substantial revenue expected this year. IJPM execution will begin in last month of current quarter.
4. Capex, mechanisation and ROE
Lakshminarayanan K G, Tunga Investments
Question. Capex has stepped up but EBITDA expansion has not been commensurate — structural ROE under pressure. Is this lower asset turnover the new normal, or is the industry shifting where capex is needed just to stand still?
Answer, Shobhit Uppal, Deputy Managing Director. Acknowledged the inflection point. Individual order sizes have grown, timelines are squeezed and buildings are more complex, demanding higher mechanisation. Labour shortage is now year-round rather than seasonal. Top management decided a couple of years ago to invest in mechanisation; the full positive impact will be visible in coming years. Margins have already improved and will continue to improve. Stable state governments in Bihar, Bengal, Assam, NCR have removed prior payment bottlenecks, justifying both higher topline and margin guidance.
Follow-up. Will depreciation continue to meaningfully increase vs revenue growth, given the strong order book?
Answer. Management: FY27 capex on similar lines; revised down from INR500 cr guided earlier to INR274 cr. FY27 capex around INR300 cr; depreciation will increase on similar lines.
Partly answered.
5. Inflation pass-through and WPI
Lakshminarayanan K G, Tunga Investments
Question. With inflation up across the board and L1 projects with limited room, how do you ensure margins are protected given inability to renegotiate prices?
Answer, Shobhit Uppal, Deputy Managing Director. Most contracts have built-in escalation clauses — Central Vista has 10CC based on WPI covering labour and material. WPI movement has lagged actual metal inflation; industry has represented to government and ministry is reviewing. On private clients (DLF, Brigade, MAIA, Signature Global) cement, steel and raw material are pass-through. Adequately covered unless war is prolonged.
Follow-up. NCR pollution-control shutdowns and labour availability — what mitigation steps are being taken as order book doubles?
Answer. Management: NGT remains a risk but ecosystem is adapting. Clients now pay for idle labour during shutdowns to prevent flight. Central Vista is NGT-insulated and will contribute during shutdown months. Mist sprayers deployed on site to mitigate pollution controls.
6. Execution ramp drivers
Keshav Garg, Counter Cyclical PMS
Question. Order book has doubled in 2 years but revenue CAGR is <9%. What has changed to justify nearly double the growth rate going forward?
Answer, Shobhit Uppal, Deputy Managing Director. Slow-moving projects like CSMT (largest order till recently) are now picking up speed. Stable state governments in Bengal, Assam, Bihar will accelerate execution. Varanasi airport is targeted ahead of schedule (Jan 2027 vs June 2027), Darbhanga to close this year, Kota to break ground in 2 months. Central Vista will log INR100–150 cr per month.
Follow-up. You had earlier said private sector share going up would lift margins; order book is now 60%+ private — can we expect that margin uplift?
Answer. Management: We will be near or hit double-digit margins. Private sector shift has already taken EBITDA from 8.3% to 9.5%. Going forward will be well into double digits. Acknowledged glory days of 13–14% unlikely in short term due to industry-wide factors beyond control.
7. Capital allocation and buyback
Keshav Garg, Counter Cyclical PMS
Question. What is net cash? Share price has compounded at only 4% CAGR over 18 years with no significant dividend. With comfortable net cash, should the company do a buyback?
Answer, Shobhit Uppal, Deputy Managing Director. CFO Satbeer Singh: cash and bank balance INR817 cr. Uppal: industry is cyclical, war has hit 3 months after a high — better to keep a war chest as past downturn taught. Share buyback is not in the offing; not even crossed our mind.
Follow-up. Are we planning a precast facility in NCR for labour substitution?
Answer. Management: Internally debating precast, pre-engineered buildings and MEP methods. Need greater standardisation. In active talks with large clients. Not a short-term solution; visible in 2–3 years.
8. Macro headwinds and guidance risk
Amit Khetan, Laburnum Capital
Question. To what extent are macro headwinds factored into the 15–20% growth and double-digit margin guidance? What could cause under-delivery?
Answer, Shobhit Uppal, Deputy Managing Director. Factored in political instability which now looks like a thing of the past. The only derisker is prolonged war impact — India's trade gap widening and rupee-dollar impact, beyond our control. Otherwise do not see any reason not to meet guidance.
Follow-up. How exactly does the war impact our business — direct or indirect?
Answer. Management: Direct impact via LPG cylinder availability for labour who fled native places — labour is the key resource. Indirect via fuel-driven inflation. Supply chain badly disrupted (switchgear, electrical panel delivery doubled to 4+ months), raising overheads and IDCs.
9. Order inflow mix
Parvez Qazi, Nuvama Group
Question. Of the INR8,000 cr FY27 inflow target, what is the split between private and government? Will we continue to stay away from private residential, focusing on commercial/institutional?
Answer, Shobhit Uppal, Deputy Managing Director. Split will be half and half tentatively. In NCR residential is not a focus, but in southern and western India we are open to residential orders with stable clients.
Follow-up. What is the quantum of fixed-price orders in the order book? And how is competitive intensity given the volatility?
Answer. Management: 11% of order book is fixed price. On competitive intensity, the last quarter saw a pause as ecosystem waits to see how war plays out. Not prudent to predict trajectory over next couple of months.
10. Margin confidence and order book mix
Vaibhav Shah, JM Financial
Question. What gives confidence in double-digit FY27 margin despite raw material and labour headwinds? Is it the order book mix?
Answer, Shobhit Uppal, Deputy Managing Director. Yes — mix of order book in private/public, geographic spread, and 89% of book has escalation clauses. Most large orders (Central Vista, DLF) have majority of volatile materials covered.
Follow-up. Top 3 project execution targets in FY27 — CSMT, IJPM, Central Vista?
Answer. Management: CSMT ~INR600 cr; Central Vista ~INR1,000 cr; IJPM modest at ~INR100 cr (designing still underway). Dahlias ~INR400 cr.
11. Depreciation, working capital and payments
Vaibhav Shah, JM Financial
Question. Q4 depreciation was ~INR29 cr — is this the run rate? Working capital days were 103 last quarter, now 104 — should we see reduction in FY27? And any payment challenges in particular states?
Answer, Satbeer Singh, Chief Financial Officer. CFO: Depreciation on similar lines — FY26 INR66–97 cr, will be proportionate to INR250–300 cr FY27 capex. Working capital standard at 104 days; will remain similar.
Follow-up. With state elections largely done, should labour improve vs last year? And any payment challenges in particular states?
Answer. Management: Last 3 months particularly bad for labour; things will improve. Labour shortage is here to stay for 3–4 years. No payment challenges currently — Assam had issues pre-election but uptick post-election.
12. Pipeline impact from war
Mahesh Patil, ICICI Securities
Question. Are the war-related uncertainties impacting our pipeline? Are new bids being given out?
Answer, Shobhit Uppal, Deputy Managing Director. Pipeline is impacted, but we are not that affected — we are well stocked. Biding our time, only picking up contracts with existing or well-established clients. Overall pipeline stalled as everyone waits on war.
Follow-up. What was Q4 FY26 order inflow for comparison with prior quarters?
Answer. CFO: Q4 FY26 order inflow INR4,300 cr. Q4 FY25 comparison to be provided offline.
13. Residential execution
Salil Desai, Marcellus Investment Managers
Question. On execution in residential real estate, projects like Signature Global and Whiteland haven't seen much progress in 3–4 quarters. Broader sector issue or project-specific?
Answer, Shobhit Uppal, Deputy Managing Director. Both projects have picked up in real earnest. Whiteland: NDMA code changes caused redesign — now behind, foundation and concrete casting started. Signature Global: work started on all 8 towers, 5 million sq ft built-up. Prices have plateaued and war has muted sentiment, but no reason to believe clients are slowing our specific projects.
14. Procurement and supply chain edge
Keshav Garg, Counter Cyclical PMS
Question. Do we enjoy any procurement advantage over competition given our scale? Better credit terms with vendors?
Answer, Shobhit Uppal, Deputy Managing Director. Yes, we feel we are handling supply chain issues well. Pointed to Varanasi airport being targeted for January 2027 completion (vs June 2027 stipulated) as evidence.
Follow-up. Top 2–3 competitors? Will bidding intensity cool down given peers have overflowing order books?
Answer. Management: L&T (B&F), Nagarjuna, Shapoorji, Kalpataru, Tata Projects are the 4–5 who bid alongside us. We are very choosy, biding our time, doing due diligence, looking to increase margin profile.
15. Client credit risk management
Keshav Garg, Counter Cyclical PMS
Question. What is strategy if a client delays releasing funds after milestone completion? Stop work, deploy own capital, or wait? What is the maximum single-project hit taken historically?
Answer, Shobhit Uppal, Deputy Managing Director. Choice begins at bid stage — customer profile, due diligence, go/no-go criteria. Once won, endeavour to work at steady pace, in constant dialogue with client. Slow down if financial position deteriorates. Maximum hits historically on Jaypee, Assotech, HDIL — data can be provided offline. Mitigation has included taking real estate inventory from troubled clients.
Partly answered.
16. Gross margin drivers and escalation lag
Shubham Harne, Purnartha Investment Advisors
Question. Gross margin during the quarter was relatively low — how much is inflationary? And what is the time lag for recovering inflationary cost via escalation clauses? Did you take employee increments in Q4 this year too?
Answer, Shobhit Uppal, Deputy Managing Director. Built up costs for higher order book — increased staff and salary enhancements. War from February, elections, and NGT in January all hit Q4. Inflation played a part but most of it is covered by escalation. Time lag is generally one quarter on WPI; private sector pass-through for cement/steel/grit/sand is month-on-month. Confirmed Q4 increments taken. On CSMT value decrease, CFO clarified INR2,450 cr was inclusive of GST — ex-GST INR2,076 cr.
17. Capex IRR and mechanisation payback
Madhur Rathi, Counter Cyclical Investments
Question. What IRR or payback do we expect from mechanisation capex? How should the INR500 cr+ cumulative capex flow to margin over time?
Answer, Shobhit Uppal, Deputy Managing Director. Management: IRR enhancement of 7–10% on hiring cost savings. Payback 4–5 years aligned to equipment life. Cannot put a fixed EBITDA-per-INR-of-capex yardstick — buildings are 40–60 storeys requiring 4–5 cranes each (15 tower cranes at Aerocity), passenger hoists at INR50–70 lakh each. True benefits will accrue as industry matures over 4–5 years with greater standardisation and off-site construction.
Follow-up. So should investors expect industry consolidation and some margin improvement over the medium term?
Answer. Management: Over the long term, yes — all steps toward mechanisation, digital transformation are for long-term efficiency. No immediate EBITDA-step-up metric available.
Partly answered.
18. Bidding discipline and margin thresholds
Lakshminarayanan K G, Tunga Investments
Question. Order book has 2x'd with meaningful visibility — are we walking away from low-margin work? What margin threshold are we applying? How is the sales team being recalibrated?
Answer, Shobhit Uppal, Deputy Managing Director. Tendering departments have common metrics; go/no-go decided by regional head and then escalated to top management. Walking away from projects with existing clients where we don't want to overexpose. When bidding, we have increased our costing profile by a couple of percentage points and built in higher profit margins depending on project and competition.
Follow-up. How are you tempering expectations and improving guidance sharpness given complexity and external factors?
Answer. Management: We've always been conservative in guidance and have achieved it despite headwinds. Most past headwinds (elections, design delays, state instability) seem covered. Mixed order profile, fast-moving projects like Central Vista, and CSMT picking up underpin guidance. Acknowledged: if this call was 3 months ago, would have given 20% growth without blinking — scenario has now changed. Nature of industry exposes us to disruption.
19. L1 project details and pipeline
Shravan Shah, Dolat Capital
Question. Can you specify the two L1 projects? When is LOA likely? Is pipeline INR7,000–8,000 cr or higher?
Answer, Shobhit Uppal, Deputy Managing Director. L1 projects are RML Hospital in Delhi and a university project of Odisha Government in Bhubaneswar. Cannot give LOA date. Rebidding/cancellation is always a possibility. Pipeline is about INR8,000 cr. On margins, articulated that sensitivity is high — 1% margin swing equals 12–18% PAT variation. Agreed risks are largely a thing of the past (war aside) and is confident of meeting projections.
20. Monsoon impact
Ankit Jambusaria, Individual Investor
Question. News of poor monsoon this year — will it impact our business?
Answer, Shobhit Uppal, Deputy Managing Director. Don't think so unless broader macro impact. Trickle-down to existing projects minimal.
Follow-up. Is Central Vista execution comparatively smoother given the higher scale? Any unexpected variables?
Answer. Management: Not impacted by NGT, government is aggressive on timeline (houses Finance and Defence ministries), money is not a problem. Complex buildings but EPC end-to-end with most activities in-house gives greater monthly control.
21. Competitive moat from capex
Ankit Jambusaria, Individual Investor
Question. Does the capex for tall buildings and mechanisation give us competitive advantage in margins or client preference, especially for premium residential?
Answer, Shobhit Uppal, Deputy Managing Director. Yes — entry barriers raised due to need for heavy mechanisation, stronger balance sheet, and pedigree. In private sector, only 4–5 companies meet criteria. Public sector has defined criteria; private is choice of developer based on delivery track record.
22. Mobilization advance composition
Vaibhav Shah, JM Financial
Question. Of mobilization advance of INR802 cr, what is the interest-bearing portion? Will this number stay constant? And what is margin money as of March '26?
Answer, Satbeer Singh, Chief Financial Officer. CFO: 37% is interest-bearing. Since 38% of order book is government, mobilization advance is expected to remain at similar level. Margin money ~INR200 cr.
23. IJPM delay reasons
Ankit Jambusaria, Individual Investor
Question. India Jewellery Park has been delayed for various reasons — design, client decision-making, India-US trade deal? Is execution starting this quarter? Any other client uncertainty?
Answer, Vikas Ahluwalia, Director. Vikas Ahluwalia: Delay is administrative. SIR-related agency changes now built in. Excavation started, all licenses applied. Expecting to start work soon after Mumbai monsoon. Client (quota government agency under Ministry of Commerce) has verbally confirmed alignment. Some administrative aligning underway with Maharashtra government land allotment.
Follow-up. Q-on-Q pattern — is FY27 15–20% growth uniform or back-loaded to H2 given disruptions?
Answer. Management: H2 always substantially higher. Q1 exceptionally slow due to elections, labour flight, and Eid (70% of skilled workforce Muslim, especially carpenters and bar benders). Q2 onwards numbers will ramp up significantly.
What was said
Topic by topic, in the order it was spoken
Q4 and FY26 Financial Performance · Shobhit Uppal (Deputy MD)
- Q4 FY26 turnover INR1,322.30 cr (+8.76% YoY); PAT INR80.14 cr (-3.63% YoY) on margin compression
- Q4 FY26 EBITDA margin 9.35% vs 10.17% YoY; PAT margin 5.95% vs 6.74%
- FY26 turnover INR4,565.20 cr (+11.38%); PAT INR264.32 cr (+31.17%); EPS INR39.46 vs INR30.08
- FY26 EBITDA margin expanded 118 bps to 9.52%; PAT margin 5.70% vs 4.85% YoY
- Net worth crossed INR2,000 cr as on 31 March 2026
Order Book and Order Inflow · Shobhit Uppal (Deputy MD)
- Net order book of INR21,096.31 cr with 24–30 month execution horizon
- FY26 order inflow INR10,257.39 cr — pipeline described as doubled over two years
- Currently L1 in two projects aggregating INR1,620.95 cr
- 11% of order book is on fixed-price terms; 89% has escalation clauses built in
- Mobilization advance INR802 cr; retention INR450 cr; unbilled revenue INR688 cr
FY27 Guidance Setup · Shobhit Uppal (Deputy MD)
- FY27 revenue growth guidance of 15–20%, up from 10–15% historical band
- FY27 EBITDA margin to cross 10% vs 9.52% in FY26
- FY27 order inflow target of INR8,000 cr including L1 conversion
- FY27 capex guided at ~INR300 cr (revised down from INR500 cr guided earlier)
In their words
3 months ago, we were thinking that we were riding wave and all of a sudden, the war hit and the future is now quite uncertain. So, during such time, it's always better to have a war chest with you, which — this is what our past experience has taught us. During the last downturn, when a lot of our peers fell by the wayside, we could survive the downturn. So, at the moment, the share buyback is not in the offing. That's not even crossed our mind.
The glory days of 13% to 14% are or the teens, so to say, are — I don't think there are too many factors which are beyond our control. So I don't think in the short term, we can — we will be getting there.
While we are aspiring or aspirational to make buildings at par with those being made or having been made earlier in the developed part of the globe. But the skill levels don't exist. So I think be it the government or the developers all the contractors, they are realizing this now. Hence, more and more mechanization is happening. But it will take time.
To check next time
What management committed to on this call, or the dates they gave.
- Q1 FY27 execution pace given Eid and election-related labor disruption; H1 typically slower than H2.
- Order inflow progress against the FY27 target of ~₹8,000 cr; L1 conversion of RML Hospital (Delhi) and Odisha university projects (~₹1,620.95 cr).
- Movement of FY27 EBITDA margin from 9.52% (FY26) toward the double-digit guidance.
- Central Vista ramp-up toward the ₹100-150 cr/month run rate, with design freeze and demolition of Nirman Bhawan already done.
- FY27 capex deployment at the guided ~₹300 cr level vs the FY26 actual of ₹274 cr.
- Receipt of WPI-based escalation recoveries vs actual commodity inflation; impact of any further war-related disruptions.
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 1 Jun 2026 | ₹763.65 | −3.58% | −0.70% |
| 5 sessions Fri 5 Jun 2026 | ₹792.95 | +0.12% | −0.77% |
| 20 sessions Mon 29 Jun 2026 | ₹871.05 | +9.98% | +1.69% |
From the close of Fri 29 May 2026, ₹792.00: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
Ahluwalia Cont Ind's other calls
- Q2 FY27Mon 16 Nov 2026Tone: Mixed
- Q1 FY27Mon 17 Aug 2026Tone: Defensive
- Q3 FY26Mon 16 Feb 2026Tone: Cautious
- Q2 FY26Mon 17 Nov 2025Tone: Confident
- Q1 FY26Mon 18 Aug 2025Tone: Confident
- Q4 FY25Mon 2 Jun 2025Tone: Confident
- Q3 FY25Wed 12 Feb 2025Tone: Cautious
- Q1 FY25Fri 16 Aug 2024Tone: Cautious
- Q4 FY24Thu 30 May 2024Tone: Cautious