Ahluwalia Cont Ind Q1 FY26 earnings call

Mon 18 Aug 2025AHLUCONT

In brief

Q1 FY26: revenue ₹1,004.88 cr (+9.3%), PAT +67%; guides 15-20% FY26 growth, double-digit margin; order book ₹16,582 cr.

Management's tone
Confident
What was said
Leaned positive
Guidance
Guidance held
Analyst pushback
Medium
Stock, next session
+0.33% (Nifty 50 +1.00%)
  • Q1 FY26 revenue ₹1,004.88 cr (+9.3% YoY), PAT ₹51.11 cr (+67% YoY); EBITDA margin expanded to 8.59% from 6.58% YoY.
  • Reiterated FY26 revenue growth of 15-20% and double-digit EBITDA margin; expects H2 to drive the bulk of performance.
  • Order book stands at ₹16,582 cr (2-2.5 years execution); FY26 inflow of ₹3,889 cr so far; L1 at ₹1,796 cr.
  • FY26 capex raised to ~₹500 cr (from ₹200 cr earlier), Q1 spend ₹62 cr; FY27 capex guided ~₹200 cr.
  • Private-sector share now 63% of order book (55% item-rate); balance sheet net cash with ₹920 cr cash and only ₹2 cr debt.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q1 FY26

This quarterA year agoLast quarterMargin
Revenue₹1,005 cr+9.3%−17.4%
EBITDA (excl. other income)₹86.3 cr+42.9%−30.3%8.6% (6.6% a year ago)
Net profit₹0 cr——0% (0% a year ago)
EPS (₹)₹7.64+67.5%−38.6%

From the company's filed results for the quarter ended 30 Jun 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • EBITDA margin expanded 201 bps YoY to 8.59% from 6.58%; PAT up 67% on mix shift to higher-margin private-sector orders and improved operating leverage.
  • Q1 is structurally a slow quarter for construction; H2 typically outperforms on labour availability post-monsoon, capping Q1 run-rate as a full-year proxy. (one-off)
  • CSMT project progress improved with design clearances; run-rate targeting ₹60-70 cr/month supports FY26 ₹400+ cr revenue.
  • Order book at ₹16,582 cr (up from ₹15,775 cr at FY25-end); FY26 inflow already ₹3,889 cr with L1 of ₹1,796 cr awaiting conversion.
  • FY26 capex stepped up to ~₹500 cr (vs prior ~₹200 cr) for high-rise shuttering and crane fleet; Q1 spend ₹62 cr.

The numbers management led with

  • Net order book as of call date: Rs. 18,671 crores (vs Rs. 16,582 cr at 30 June 2025)
  • Order inflow FY26-to-date: Rs. 3,889.06 crores
  • Cash and liquid investments: Rs. 920 crores
  • Total borrowings: Rs. 2 crores (effectively debt-free)

Guidance

Guidance on this call

WhatForWhat management saidFiled
FY26 revenue growthFY26FY26 revenue growth guided at 15-20%35.9%, above the range
FY26 EBITDA marginFY26double-digit EBITDA margin in FY26—
FY26 order inflowFY26FY26 order inflow of about ₹8,000 cr—
FY26 capexFY26FY26 capex of about ₹500 cr—
FY27 capexFY27FY27 capex of about ₹200 cr—
CSMT FY26 revenueFY26CSMT to deliver ₹400+ cr revenue in FY26—
CSMT FY27 revenueFY27CSMT FY27 revenue will increase from FY26—
FY27 revenue growthFY27FY27 revenue growth of 15-20% possible—
FY27 EBITDA marginFY27FY27 EBITDA margin expected double-digit—

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

What changed since the Mon 2 Jun 2025 call

WhatOn the Mon 2 Jun 2025 callOn this call
FY26 revenue growth guidance (raised)~15% YoY growth in FY2615% to 20% growth in FY26
FY26 capex guidance (raised)~Rs. 200 cr in FY26~Rs. 500 cr in FY26
FY26 order inflow target (held)Rs. 7,000-8,000 cr targeted in FY26~Rs. 8,000 cr
CSMT FY26 revenue guidance (held)Rs. 400-500 cr in FY26Rs. 400+ cr in FY26; to increase in FY27
Private-sector order book share (achieved)private-sector focus 60:40 (vs 50:50 earlier)63% of order book is private sector
Interest-bearing mobilization advance (achieved)40% of total (from 58% last year)35% of mobilization advance
FY27 revenue trajectory (restated)potentially ~Rs. 6,000 cr (~30% growth) in an ideal scenario with no disruption15% to 20% growth next year also possible
FY27 capex outlook (new)not discussed~Rs. 200 cr in FY27

Guided on earlier calls, and what was filed

WhatForGuidedFiled
Q1 FY25 EBITDA margin floorQ1 FY25at least 9% (on the Q4 FY24 call)6.6%, below the range
Consolidated revenue growthFY2515–20% (on the Q4 FY24 call)6.3%, below the range
Consolidated EBITDA marginFY25at least 10% (on the Q4 FY24 call)8.3%, below the range
FY26 revenue growthFY2615% (on the Q4 FY25 call)35.9%, above the figure guided

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

Balance sheet, capex and funding

  • Net cash position: ₹920 cr cash and equivalents vs only ₹2 cr borrowings.
  • Q1 FY26 capex ₹62 cr; FY26 guidance raised to ~₹500 cr (vs prior ~₹200 cr); FY27 guidance ~₹200 cr.
  • Mobilization advance ₹675 cr; interest-bearing share cut to 35% of total (vs 40% last year).
  • Working capital: retention ₹397 cr, trade receivables ₹623 cr, unbilled revenue ₹557 cr, inventory ₹380 cr, trade payables ₹821 cr.

The industry, as management sees it

Management believes the broader construction industry performs materially better in H2 once monsoon ends and labour shortage season passes; they are observing pricing plateau (not decline) in residential, with no slowdown in projects being executed on the ground in their client set. Government sector competition has intensified as qualification criteria have been diluted, while private sector has fewer qualified bidders for marquee contracts.

Risks management named

  • Q1 and Q2 are seasonally weaker due to monsoon; H1 typically below H2
  • CSMT is a complex environment with clearance dependencies that have historically slowed billing
  • Residential sector showing pricing plateau; company deliberately not adding new residential
  • Government sector qualification criteria have been diluted, intensifying competition
  • Interest-bearing mobilization advance component at 35% of total Rs. 675 cr

Q&A

Q&A was dominated by project-level execution updates (CSMT, The Dahlias, Gems & Jewellery) and reaffirmation of FY26 guidance on revenue (15–20%) and EBITDA margin (double-digit). Vaibhav Shah's framing of Q1 as showing 'margin softness' drew the sharpest pushback from Shobhit Uppal, who countered with QoQ EBITDA growth and peer comparison. The most material new data points came from Satbeer Singh on capex, balance-sheet items, and the near-debt-free cash position. The order book reconciliation with Salil Desai was a minor governance moment that got resolved cleanly. No major surprises; tone broadly confident with mild defensiveness on Q1 optics.

Not answered directly

  • Item-rate vs EPC margin differential — management declined to give a generic number, deflected to sector-level commentary
  • Annual run rate for Gems & Jewellery Park post-commencement — declined to commit till project takes off

Asked for a number, answered without one

  • Gems & Jewellery Park annual run rate: We would not like to comment on that at this point in time... it would not be prudent for us to commit to that as of now, till the project really takes off.
  • Item rate vs EPC margin differential: I think it would not be, again prudent for me to put a general number that way. Gave qualitative example instead: on private-sector EPC, margins at par with item rate; lower only due to govt competitive intensity.

Every question, with its answer

  1. 1. CSMT and India Jewellery Park execution

    Mohit, ICICI Securities

    Question. Can you provide an update on the progress of the CST (Chhatrapati Shivaji Maharaj Terminus) and India Jewellery Park projects? How do you see their contribution to the topline in this fiscal and next fiscal?

    Answer, Vikas Ahluwalia, Director. On CST: progress is better than the last two quarters — design clearances are largely in place. Work done at site is about 17–20% built, with significant unbilled work in progress. Management is targeting a run rate of Rs. 60–70 cr per month, though complexity of the railway environment remains a constraint. On India Jewellery Park: client has now received environmental clearance in writing; certain compliances remain. Ground-breaking expected within two months after the Mumbai monsoon settles.

    Follow-up. And the Gurgaon project (The Dahlias from DLF) — when does work commence? Is Rs. 500 cr/yr revenue from FY27 a fair expectation?

    Answer. Vikas confirmed The Dahlias is roughly a Rs. 2,000 cr project with a 40-month timeline — Rs. 500 cr/yr is the right order of magnitude. Total built-up area is 7.3 million sq ft across eight towers. Client is handling D-wall and excavation; Ahluwalia expects to break ground from its side in September 2025 as handovers begin.

  2. 2. FY26 margin and revenue guidance

    Vaibhav Shah, JM Financial

    Question. We have seen some softness in margins in Q1. You are targeting double-digit margins for the full year — can we expect improvement from Q2 itself or only in H2? What is the FY26 revenue growth guidance?

    Answer, Shobhit Uppal, Deputy Managing Director. Pushed back on the 'softness' framing: pointed to 42.7% QoQ EBITDA growth and 67% PAT growth, saying Q1 seasonally is slow for all construction firms. Stated FY26 double-digit EBITDA margin guidance is intact and well on track. Revenue guidance maintained at 15–20%. Said Q2 will likely be similar to Q1; Q3 and Q4 are where margins take off once monsoon ends and labour normalises.

    Follow-up. Sticking with earlier CSMT guidance of Rs. 400–500 cr and Gems & Jewellery of ~Rs. 150 cr for FY26? And on Chapra project scope increase and Bihar Animal University execution?

    Answer. CSMT: Rs. 400+ cr reaffirmed. Gems & Jewellery: deliberately kept low as client clearances pending — but pipeline has enough to deliver 15–20% growth regardless. Chapra: scope increased by Rs. 160 cr, funds now flowing, completion expected this FY. Bihar Animal University: Rs. 50 cr+ billed in July alone; project is racing and will complete this fiscal.

    Partly answered.

  3. 3. L1 pipeline, order intake, DLF relationship, capex, balance sheet

    Parvez Qazi, Nuvama Group

    Question. On the L1 projects (MIDC and Bhubaneswar University from prior call) — by when should we see progress? Order intake has been strong in the first five months; full-year should match last year's Rs. 8,000 cr? And on The Dahlias — scope for more work from DLF? Lastly, capex and balance sheet position.

    Answer, Shobhit Uppal / Satbeer Singh, Deputy Managing Director / Chief Financial Officer. Both L1 projects expected to convert this quarter. FY26 order inflow target reiterated at ~Rs. 8,000 cr. On DLF: now described as 'DLF's premier contractor'; gross exposure Rs. 5,500 cr; Arbour project substantially complete by Feb–Mar 2026; expects more work. CFO Satbeer Singh: FY26 capex ~Rs. 500 cr (Q1 actual Rs. 62 cr); borrowings Rs. 2 cr; cash and liquid investments Rs. 920 cr.

  4. 4. Project-level margins, client concentration, monsoon impact

    Amit Khetan, Laburnum Capital

    Question. On marquee projects like The Dahlias or CSMT — do these come at company-level margins or do you bid more aggressively to win them? On single-client exposure, with Rs. 5,500 cr exposure to DLF, where is your comfort limit? And on Q1 unseasonal rains — what was the execution impact?

    Answer, Shobhit Uppal, Deputy Managing Director. On margins: private sector carries higher margins because competitive intensity is lower; CSMT (government) is lower-margin despite being prestigious. On DLF concentration: Rs. 5,500–6,000 cr is acceptable as DLF is the 'premier developer' — most organised and cash-rich; aims to maintain similar level going forward. On Q1 rains: management says these were factored into projections; H2 typically outperforms H1 once monsoon ends.

  5. 5. Residential de-risking, item-rate vs EPC mix, contract-type margins

    Lakshmi Narayan, Tunga Investments

    Question. Given talk of slowdown in residential offtake in NCR, especially high-end — how are you de-risking given the order book mix is tilting residential? Also, what is the item-rate vs EPC mix and the margin differential?

    Answer, Shobhit Uppal, Deputy Managing Director. Not seeing slowdown on the ground with current clients; residential is ~40% of order book. Has slowed down intake in residential — 'refusing a job a week' in the segment. Mix today: 55% item-rate, 45% EPC; flipped vs last year. Private-sector share 63% of order book (conscious 2-year pivot). On EPC vs item-rate margin gap: declined to give a generic number; said the gap is driven by sector (private vs government) rather than contract type — on private-sector EPC, margins can be at par with item rate.

    Partly answered.

  6. 6. Margin trajectory, capex, balance sheet, bid pipeline, CSMT ramp, FY27 outlook

    Shravan Shah, Dolat Capital

    Question. On margins: can Q2 itself start showing 10% EBITDA margin, with Q3/Q4 at 11%+? Can FY27 also be double-digit or 11%? What is the bid pipeline value? Balance sheet data points — inventory, receivables, payables, mobilization, retention, unbilled revenue? Full-year and next-year capex? Depreciation trajectory? CSMT next-year potential? Can FY27 topline growth be 15%?

    Answer, Shobhit Uppal / Satbeer Singh, Deputy Managing Director / Chief Financial Officer. Shobhit: Q2 will be similar to Q1 due to unusually heavy NCR rains in July/Aug; Q3/Q4 are the margin-acceleration quarters. FY27 double-digit margin guidance reiterated. On private side, ~Rs. 1,000 cr under negotiation, Rs. 5,000 cr bid pipeline; virtually no unopened government bids. CFO: retention Rs. 397 cr, debtors Rs. 623 cr, mobilization Rs. 675 cr (35% interest-bearing), trade payables Rs. 821 cr, inventory Rs. 380 cr, unbilled revenue Rs. 557 cr. FY26 capex Rs. 500 cr, FY27 ~Rs. 200 cr. Depreciation to step up from Q3/Q4 once rest of capex deployed. CSMT revenue to increase in FY27 as higher-value items kick in. FY27 15–20% topline growth 'possible' — order book of ~Rs. 18,000 cr provides visibility.

  7. 7. Order book reconciliation

    Salil Desai, Marcellus Investment Managers

    Question. On the presentation, the unexecuted order book figure refers to 31 March 2025 — should it be read as 30 June 2025, or is there a different number? Concerned about possible order cancellation since math doesn't tie.

    Answer, Shobhit Uppal / Vikas Ahluwalia, Deputy Managing Director / Director. Slide #3 figure of Rs. 16,582 cr is as of 30 June 2025. Slide #13 of Rs. 2,089 cr is fresh order inflow added; can be added to get the July-end unexecuted value. Vikas clarified there has been no order cancellation. As of call date, total order book stands at Rs. 18,671 cr.

  8. 8. Birla Trimaya project scope and future Birla relationship

    Lakshmi Narayan, Tunga Investments

    Question. On Birla Trimaya in Bangalore (~Rs. 325 cr) — is the company developing all towers? Given multiple Birla projects nationwide, are you better positioned to bid for more?

    Answer, Shobhit Uppal, Deputy Managing Director. Doing Phase-I and Phase-II of Trimaya. Have bid for Birla projects in other parts of the country in the past. Have consciously refused a Birla job in Gurgaon as part of the step-back from new residential — will revisit after Trimaya reaches substantial completion.

  9. 9. Competitive intensity — public vs private sector

    Parvez Qazi, Nuvama Group

    Question. On competitive intensity given refocus toward retail and traditional commercial — how is competition there, and the difference between public and private sector projects?

    Answer, Shobhit Uppal, Deputy Managing Director. Public sector continues to be extremely competitive — government bidding has been substantially reduced on the company's side; will still chase large marquee government jobs where intensity is lower. Private sector: only a handful of players are invited by large developers — this is where the strategic focus remains.

What was said

Topic by topic, in the order it was spoken

Q1 FY26 Financial Performance · Shobhit Uppal (Deputy Managing Director)

  • Q1FY26 turnover at Rs. 1,004.88 cr, up 9.3% YoY from Rs. 919.35 cr in Q1FY25
  • PAT at Rs. 51.11 cr vs Rs. 30.60 cr in Q1FY25, a 67.03% YoY jump; EPS Rs. 7.63 vs Rs. 4.57
  • EBITDA margin expanded to 8.59% in Q1FY26 from 6.58% in Q1FY25; PAT margin 5.01% vs 3.29%
  • Net order book as on 30 June 2025 stands at Rs. 16,582.09 cr, executable over the next 2–2.5 years
  • FY26-to-date order inflow at Rs. 3,889.06 cr; L1 on two projects aggregating Rs. 1,796 cr

In their words

This is very funny. When succeeding quarter to preceding quarter, we show an increase, then you compare with a corresponding quarter. When corresponding quarter, we show an increase, then you compare with a preceding quarter.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)
There is DLF and then there are others. So and even in the past, we've worked with them and we feel they are the most organized and cash rich of all developers.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)
We are now DLF's premier contractor. We are doing projects worth nearly Rs. 5,500 crores with them, totally gross value I'm talking about.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)

To check next time

What management committed to on this call, or the dates they gave.

  • Conversion of two L1 projects worth ₹1,796 cr expected this quarter.
  • DLF Dahlias project (₹2,000 cr, ~₹500 cr/yr) to break ground from September.
  • Notice to proceed from Gems & Jewellery Park client; site-breaking expected in ~2 months.
  • Q2 FY26 EBITDA margin trajectory given rainfall impact on NCR and other sites.
  • CSMT run-rate progress toward ₹60-70 cr/month and ₹400+ cr FY26 revenue.
  • FY26 capex run rate after Q1 ₹62 cr spend, tracking to ~₹500 cr full-year target.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Mon 18 Aug 2025₹953.00+0.33%+1.00%
5 sessions Fri 22 Aug 2025₹932.00−1.88%+0.97%
20 sessions Mon 15 Sept 2025₹933.45−1.73%+1.78%

From the close of Thu 14 Aug 2025, ₹949.90: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Ahluwalia Cont Ind's other calls

  • Q2 FY27Mon 16 Nov 2026Tone: Mixed
  • Q1 FY27Mon 17 Aug 2026Tone: Defensive
  • Q4 FY26Mon 1 Jun 2026Tone: Mixed
  • Q3 FY26Mon 16 Feb 2026Tone: Cautious
  • Q2 FY26Mon 17 Nov 2025Tone: Confident
  • Q4 FY25Mon 2 Jun 2025Tone: Confident
  • Q3 FY25Wed 12 Feb 2025Tone: Cautious
  • Q1 FY25Fri 16 Aug 2024Tone: Cautious
  • Q4 FY24Thu 30 May 2024Tone: Cautious