In brief

Management's tone
Cautious
What was said
Mixed
Guidance
Guidance cut
Analyst pushback
Medium
Stock, next session
−3.10% (Nifty 50 −0.12%)
  • FY25 revenue growth cut to 8.5-9%; FY26 guided to 15%+ (vs 20% earlier) on NGT and CSMT drag
  • FY26 EBITDA margin guided to exceed 10% on operating leverage as slow projects clear
  • Order book Rs 16,258 cr at 31-Dec-24 (3-yr cover); FY25 inflow Rs 7,794 cr, FY26 targeted similar
  • CSMT FY26 revenue target Rs 750 cr; Q4 FY25 only Rs 80-100 cr on design delay
  • Variable/fixed price contract mix at 87/13; SAP go-live in a month as part of digital push

An AI read of the company's transcript · the filing

The numbers

The quarter, Q3 FY25

This quarterA year agoLast quarterMargin
Revenue₹952 cr−7.3%−5.9%
EBITDA (excl. other income)₹84.4 cr−24.2%+15.0%8.9% (10.9% a year ago)
Net profit₹0 cr——0% (6.8% a year ago)
EPS (₹)₹7.39−29.6%+28.1%

From the company's filed results for the quarter ended 31 Dec 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

The numbers management led with

  • Net order book: Rs 16,258.44 crores as on 31-Dec-2024 (3-year execution)
  • FY25 order inflow: Rs 7,794.37 crores (target similar in FY26)
  • Fixed vs variable price contract mix: 13% fixed price / 87% variable price
  • FY26 overall bid pipeline: ~Rs 25,000 crores across residential, healthcare, commercial

Guidance

Guidance on this call

FY25 revenue growth guided to 8.5-9% (vs prior ~10%). FY26 revenue growth guided to 15%+ (vs prior ~20%). FY26 EBITDA margin guided to exceed 10% (double-digit). FY25 order inflow target ~Rs 7,800 cr (similar expected in FY26). Q4 FY25 margin ~10%. FY25 CSMT revenue Rs 80-100 cr in Q4; FY26 Rs 750 cr. Gem & Jewellery Park FY26 ~Rs 500 cr. FY26 capex ~Rs 125 cr vs Rs 175 cr planned in Q4 FY25.

Said on the Q1 FY25 call, not repeated on this one (6)
  • Revenue growth: 15-20% revenue growth for FY25, similar run rate expected to continue in FY26
  • EBITDA margin: Double-digit (>10%) margin for full-year FY25; ~11% in H2 FY25; ~11% in FY26; 'double digit' medium term (FY26-FY27)
  • Order inflow: Additional Rs 2,500-3,500 cr of inflows for balance of FY25; bid pipeline Rs 5,000-6,000 cr
  • Capex: ~Rs 175 cr for FY25 (Rs 54 cr Q1 + Rs 120 cr balance); Rs 120-125 cr for FY26
  • CSMT project revenue: Rs 450-500 cr in FY25, ~Rs 1,000 cr in FY26 (~Rs 100 cr/month run rate)
  • Gems & Jewellery project revenue: Rs 125-150 cr in FY25, material in FY26

Guided on earlier calls, and what was filed

WhatForGuidedFiled
Q1 FY25 EBITDA margin floorQ1 FY25at least 9% (on the Q4 FY24 call)6.6%, below the range
Consolidated revenue growthFY2515–20% (on the Q4 FY24 call)6.3%, below the range
Consolidated EBITDA marginFY25at least 10% (on the Q4 FY24 call)8.3%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

The industry, as management sees it

Management believes NGT disruptions should be better handled next year with the same party (BJP) in power at Centre and NCR states, and industry representations gaining traction. Labour shortage viewed as a structural issue requiring government-led upskilling.

Risks management named

  • NGT/GRAP-driven work stoppages likely to recur every Oct-Jan in NCR
  • Sustained labour shortage and rising wage costs; mechanisation only a partial offset
  • CSMT execution risk — project is live station with heritage infrastructure integration
  • Higher working-capital intensity from mechanisation and EPC shift
  • Delays in handing over work fronts by private clients (DXP, Signature Global)

Q&A

Q&A was dominated by discussion of the FY25 guidance cut (8.5-9% vs earlier ~10%) and FY26 revision (15%+ vs earlier 20%), driven by NGT impact on NCR and CSMT design delays. Multiple analysts (Shravan Shah, Mohit Kumar, Vaibhav Shah) probed on whether NGT disruptions would recur next year; management maintained a confident FY26 recovery narrative anchored on margin expansion to double-digits and order book visibility. Project-level execution queries on CSMT, Gem & Jewellery, DLF and airports received fairly detailed responses, while working capital and capex questions were answered with specific figures by the CFO.

Not answered directly

  • Recurrence of NGT disruption in FY26 winter
  • Cash flow from operations for 9 months (deferred)

Every question, with its answer

  1. 1. Revenue guidance FY25/FY26

    Shravan Shah, Dolat Capital

    Question. 9-month revenue growth is 7.1% vs earlier 15% guidance for FY25. How to think about Q4 growth and FY26 — was 20% earlier, can we look at 25% now?

    Answer, Shobhit Uppal, Deputy Managing Director. Order book is healthy but NGT hit NCR hard — 33% of order book is in NCR. FY25 growth will be ~8.5-9%. Q4 is typically strongest. FY26 guidance is 15%+ — conservative stance reiterated.

    Follow-up. Even next year margins only 10% max — can we clock 10.5-11%?

    Answer. Compares Ahluwalia QoQ margin expansion: only mid-cap peer (+15% EBITDA, +28% net profit) besides L&T. Hopeful on last quarter and FY26 margin expansion.

  2. 2. Order inflow pipeline

    Shravan Shah, Dolat Capital

    Question. Are we L1 in any projects and how much more order inflow in Q4 and FY26?

    Answer, Shobhit Uppal, Deputy Managing Director. Bids quoted for a few government and private projects but government bids not yet opened; private negotiations ongoing. Some inflow expected in Q4. FY26 target similar to FY25 (~Rs 7,800 cr).

    Partly answered.

  3. 3. Working capital and balance sheet

    Shravan Shah, Dolat Capital

    Question. Balance sheet numbers — inventory, receivables, payables, debt, cash, retention, mobilization, unbilled revenue?

    Answer, Satbeer Singh, Chief Financial Officer. Cash Rs 246 cr + bank Rs 489 cr. Retention Rs 351 cr. Mobilization Rs 621 cr. Unbilled revenue Rs 572 cr. Inventory Rs 324 cr (incl Rs 36 cr real estate). Trade receivables Rs 882 cr. Debtors Rs 772 cr.

  4. 4. Margin levers FY26

    Mohit Kumar, ICICI Securities

    Question. What are the levers for margin expansion next year given NGT/GRAP will be a regular feature?

    Answer, Shobhit Uppal, Deputy Managing Director. CSMT design issues resolving by Q4; slow-moving projects finishing; staff cost ratio will fall as turnover picks up. On NGT, with BJP in power across NCR, expects more concrete measures; this year was exceptionally bad.

    Follow-up. Is there cost escalation due to NGT or just revenue loss — any contractual recourse?

    Answer. Some clients compensating idle labour. No specific escalation clauses beyond standard indexation. Industry and government stakeholders working on granular measures.

  5. 5. Labour availability and cost

    Rajat, iThought PMS

    Question. What is the labour availability situation and why have labour costs risen faster than revenues?

    Answer, Shobhit Uppal, Deputy Managing Director. Labour remains in short supply — government needs to upskill and make profession more attractive. Labour cost spike primarily due to idle labour on NCR projects hit by NGT, not labour shortage per se.

    Follow-up. Finance cost up sharply — any particular reason?

    Answer. Mainly interest-bearing mobilization advance; CSMT slow execution means lower mobilization recoveries.

  6. 6. FY26 margin outlook

    Rajat, iThought PMS

    Question. Will margins be hit again next year due to NGT?

    Answer, Shobhit Uppal, Deputy Managing Director. No — margins should improve as slow-moving projects clear and larger projects take off. No further expense additions expected; NGT period Oct-Jan should be handled better next year.

    Follow-up. What is the cash flow from operations for 9 months? Drivers of FY26 order inflow bullishness?

    Answer. Cash flow number not immediately available; aggregate cash + bank ~Rs 730 cr. Inflow run-rate of Rs 7,800 cr expected to continue; Bihar elections and Assam activity are tailwinds. Private mix to be maintained at 50:50.

    Not answered directly.

  7. 7. Larger project economics

    Amit Khetan, Laburnum Capital

    Question. Do larger projects (>Rs 1,000 cr) come with better margins or working capital terms?

    Answer, Shobhit Uppal, Deputy Managing Director. Conventional logic says yes, but short-term no — larger projects are more complex with shrinking timelines and dwindling labour skill. Long-term margins from scale projects will be higher. Working capital is more intensive due to EPC and mechanisation; will raise entry barriers.

    Follow-up. What organisational changes are needed as order book scales up? And fixed vs variable rate mix?

    Answer. SAP go-live in ~1 month; digital transformation and AI-led analytics underway; succession planning at all levels. Fixed price contracts are 13% of order book, variable 87%. All government contracts have WPI/labour index-based escalation except one NBCC fixed-price project.

  8. 8. FY26 margin target

    Vaibhav Shah, JM Financial

    Question. Will FY26 margin be closer to 10% or 10.5-11%? And what is driving Q4 pickup given January was NGT-hit?

    Answer, Shobhit Uppal, Deputy Managing Director. FY26 margin should exceed 10%. From 3-4 February post-NGT lift, considerable production upswing across NCR. Some clients paid for idle labour retention. Q4 margin ~10% expected.

    Follow-up. When does Gem & Jewellery work start? And what is the revised CSMT FY25 revenue?

    Answer. Gem & Jewellery: notice to proceed in 1-2 months; ground work starts April. CSMT FY25 revenue Rs 80-100 cr in Q4 only. FY26 CSMT target Rs 750 cr; Gem & Jewellery ~Rs 500 cr.

  9. 9. Project risk comparison

    Vaibhav Shah, JM Financial

    Question. Could Gem & Jewellery face similar design delays as CSMT? And interest cost outlook?

    Answer, Shobhit Uppal, Deputy Managing Director. Gem & Jewellery is much less complex than CSMT; large offices/workspaces rather than live station. Expect fewer problems. Q4 interest cost similar at Rs 14-15 cr.

  10. 10. Debt and capex

    Shravan Shah, Dolat Capital

    Question. What is the gross debt level? How much capex in 9 months and Q4?

    Answer, Satbeer Singh, Chief Financial Officer. Net working capital debt Rs 5.93 cr; total including term loan Rs 11 cr. 9-month capex Rs 154 cr; Q4 capex Rs 175 cr.

    Follow-up. Next year capex similar? And bid pipeline value for government+private projects?

    Answer. FY26 capex ~Rs 125 cr — lower as CAPEX already incurred on CSMT/DLF. Bid pipeline for projects undecided ~Rs 5,500 cr; further ~Rs 3,000 cr to be bid by March.

  11. 11. Project execution status

    Shravan Shah, Dolat Capital

    Question. What is the execution status of the airport projects and Signature Global Business Park? Should FY26 growth be >20%?

    Answer, Shobhit Uppal, Deputy Managing Director. Airport execution started: Varanasi Rs 40 cr, Darbhanga Rs 20 cr. Signature Global — only 10% of site handed over. Confident on 15%+ FY26 growth and double-digit margins; 'we are always conservative'.

    Follow-up. Was the Maharatna last installment of Rs 56 cr received?

    Answer. Yes, received.

  12. 12. CSMT completion vs revenue recognition

    Samir Jain, Unknown

    Question. Railway authorities cited CSMT at 15% completion vs our booked revenue — what explains the gap?

    Answer, Vikas Ahluwalia, Director. 15% would equate to ~Rs 270 cr; agreed billed figure ~Rs 150-160 cr; rest is work done but unbilled — 5,000-6,000 MT of structural steel is fabricated off-site and not yet billed. Work-in-progress includes ground preparation on 100-year-old services.

    Follow-up. Is there a minimum threshold for revenue recognition — booked at 5% completion or stage-wise?

    Answer. Revenue is booked when client passes bill; no minimum threshold. EPC contracts have stage-wise payments and mathematical formula-based recognition.

    Partly answered.

  13. 13. Subcontracting cost analysis

    Samir Jain, Unknown

    Question. Subcontracting cost fell to ~28% this quarter vs ~31-32% earlier — counterintuitive given labour shortage. Why?

    Answer, Shobhit Uppal, Deputy Managing Director. Subcontracting includes petty contracting, labour supply and material-bearing work (lift, escalator, AC). Quarter-to-quarter mix shifts based on outsourced works with material being higher or lower in a given period. Look at combined labour + material subcontracting for true comparison.

  14. 14. NGT timeline and intensity

    Hetan Jain, Avendus Park

    Question. When was the NGT ban implemented this year? How does it compare to last year?

    Answer, Shobhit Uppal, Deputy Managing Director. NGT ban started end-October/November around Diwali, continued till first week of February. GRAP guidelines trigger automatically at AQI thresholds — crossing 300 halts all construction. This year was worse than last year due to multiple stoppages and supply-chain logjams.

    Follow-up. Any segment flavour for the Rs 5,000 cr bid pipeline? Any slowdown in state payments?

    Answer. Bid pipeline is across residential, commercial and healthcare. No material slowdown in state payments — Bengal slow-moving projects over; Bihar improved under BJP-JDU; Assam continues fine.

  15. 15. Project execution and pipeline

    Vasudev Ganatra, Nuvama Wealth

    Question. Status of DLF Arbour and Tata Memorial projects? Bid pipeline segments for FY26?

    Answer, Shobhit Uppal, Deputy Managing Director. DLF Arbour well underway; compensated labour during NGT; ~4,000 cubic metres concrete in Feb; total billing >Rs 200 cr. Tata Memorial: Rs 110 cr executed. FY26 bid pipeline ~Rs 25,000 cr across residential, healthcare and commercial.

  16. 16. Mobilization advance structure

    Vaibhav Shah, JM Financial

    Question. Of mobilization advance of Rs 621 cr, how much is interest-bearing? Will this reduce next year?

    Answer, Shobhit Uppal, Deputy Managing Director. 43% of mobilization is interest-bearing. Mobilization expected to remain in similar range; policy shift to interest-free advances in private sector — airport projects funded from internal accruals. Working to reduce finance cost.

    Follow-up. When will DXP and Signature Global residential projects (Rs 1,100 cr each) start?

    Answer. Q1 FY26 — work-front handovers currently only 5-10%.

What was said

Topic by topic, in the order it was spoken

Q3 & 9M FY25 Financial Performance · Shobhit Uppal (Deputy Managing Director)

  • Q3 FY25 turnover Rs 951.95 cr vs Rs 1,026.47 cr in Q3 FY24, a 7.26% YoY decline
  • Q3 FY25 PAT Rs 49.39 cr vs Rs 70.66 cr in Q3 FY24, a 30.10% YoY decline
  • Q3 FY25 EPS Rs 7.37 vs Rs 10.55; EBITDA margin 8.86% vs 10.90%; PAT margin 5.11% vs 6.82%
  • 9M FY25 turnover Rs 2,882.79 cr vs Rs 2,691.64 cr (+7.1% YoY); 9M PAT Rs 118.35 cr vs Rs 175.69 cr
  • 9M FY25 EBITDA margin 7.57% vs 10.56%; PAT margin 4.05% vs 6.47% — margin compression attributed to NGT disruptions
  • Order book Rs 16,258.44 cr (31-Dec-24); FY25 order inflow Rs 7,794.37 cr

NGT/GRAP Disruption and NCR Exposure · Shobhit Uppal (Deputy Managing Director)

  • NGT bans from end-October through first week of February disrupted NCR; impact was in fits-and-starts due to Supreme Court involvement
  • 33% of order book is in NCR region — disproportionately exposed to NGT action
  • Some clients (e.g., DLF) compensated idle labour to retain them onsite
  • Management hopes for more concrete industry-government measures before next winter; no specific cost escalation clauses beyond standard indexation
  • Staff expenses ran high (~9% of revenue) due to idle capacity from NGT and slow-moving projects

CSMT and Gem & Jewellery Park Project Updates · Shobhit Uppal (Deputy Managing Director) and Vikas Ahluwalia (Director)

  • CSMT design issues largely resolved; approvals expected by end of Q4 FY25 with steady execution from April
  • CSMT Q4 FY25 revenue now guided to Rs 80-100 cr (vs Rs 300 cr full-year target earlier); FY26 target Rs 750 cr
  • Gem & Jewellery Park: notice to proceed expected in 1-2 months; FY26 revenue ~Rs 500 cr after design/approval phase
  • CSMT complexity driven by live-station integration with 100-year-old infrastructure and relatively new nodal PMC
  • Gem & Jewellery Park is less complex than CSMT — fewer design delays expected

DLF Arbour and Airport Projects · Shobhit Uppal (Deputy Managing Director)

  • DLF Arbour resumed strongly post-NGT lift; ~4,000 cubic metres of concrete in Feb; cumulative billing >Rs 200 cr
  • DLF compensated labour during NGT ban enabling quick restart
  • Varanasi airport execution at ~Rs 40 cr; Darbhanga airport ~Rs 20 cr; both underway
  • DXP (Rs 1,100 cr) and Signature Global projects: only 5-10% work fronts handed over — true ramp in Q1 FY26

Margin Levers and FY26 Outlook · Shobhit Uppal (Deputy Managing Director)

  • FY26 EBITDA margin guided to exceed 10% as slow-moving projects finish and larger projects (CSMT, Gem & Jewellery) ramp
  • Staff cost ratio expected to decline as turnover grows on existing headcount base
  • Management believes it is the only mid-cap peer (besides L&T) with QoQ EBITDA margin expansion in Q3 (+15%)
  • Maharatna last installment of Rs 56 cr has been received
  • Polly: management positions FY26 as a margin-led recovery year on operating leverage

In their words

You know me, we are always conservative. Yes. Otherwise you hold us. That is why I am confident that our margins will also go up and we will be having double-digit margins next year.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts India Limited)
We may, if you compare our results, if you compare the quarter-on-quarter results of Ahluwalia with our peers, if you leave L&T aside, we are the only Company other than Larson and Toubro where our EBITDA margin has grown quarter-on-quarter. We have grown at 15%, whereas in most of the other construction companies, there has been a degrowth in the EBITDA margin.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts India Limited)
I think it should exceed 10%.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts India Limited)

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Wed 12 Feb 2025₹705.65−3.10%−0.12%
5 sessions Tue 18 Feb 2025₹634.20−12.91%−0.55%
20 sessions Wed 12 Mar 2025₹730.65+0.33%−2.61%

From the close of Tue 11 Feb 2025, ₹728.25: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Ahluwalia Cont Ind's other calls

  • Q2 FY27Mon 16 Nov 2026Tone: Mixed
  • Q1 FY27Mon 17 Aug 2026Tone: Defensive
  • Q4 FY26Mon 1 Jun 2026Tone: Mixed
  • Q3 FY26Mon 16 Feb 2026Tone: Cautious
  • Q2 FY26Mon 17 Nov 2025Tone: Confident
  • Q1 FY26Mon 18 Aug 2025Tone: Confident
  • Q4 FY25Mon 2 Jun 2025Tone: Confident
  • Q1 FY25Fri 16 Aug 2024Tone: Cautious
  • Q4 FY24Thu 30 May 2024Tone: Cautious