Ahluwalia Cont Ind Q1 FY27 earnings call

Mon 17 Aug 202616:00 ISTAHLUCONT

In brief

Q1 FY27 PAT plunges 77.65% YoY to ₹11.42 cr as EBITDA margin halves to 4.29% on labour cost shock

Management's tone
Defensive
What was said
Leaned negative
Guidance
Guidance cut
Analyst pushback
High
Stock, next session
−10.85% (Nifty 50 −0.55%)
  • PAT fell 77.65% YoY to ₹11.42 cr and EBITDA margin halved to 4.29% from 8.59% on revenue of ₹1,125.81 cr (+12.03%).
  • AIIMS Jammu bill finalised ₹29 cr lower (2.6% EBITDA hit); company to pursue arbitration.
  • NCR labour costs jumped 35-40% on government mandate, hitting 50% of portfolio; ~1.5% company-level EBITDA hit.
  • FY27 revenue growth guidance maintained at 12-15%; double-digit EBITDA margin explicitly ruled out.
  • FY27 capex guidance cut to ₹220-250 cr (from ₹300 cr); order inflow target lowered to ~₹4,000-5,000 cr from ₹8,000 cr.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q1 FY27

This quarterA year agoLast quarterMargin
Revenue₹1,126 cr+12.0%−14.9%
EBITDA (excl. other income)₹48.3 cr−44.1%−61.5%4.3% (8.6% a year ago)
Net profit₹10.4 cr—−87.3%0.9% (0% a year ago)
EPS (₹)₹3.10−59.4%−87.3%

From the company's filed results for the quarter ended 30 Jun 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • PAT: said ₹11.42 cr; filed ₹10.39 cr. Material gap; management did not address discrepancy with filed consolidated PAT of ₹10.39 cr.
  • EPS: said ₹1.70; filed ₹3.10. Large mismatch with filed EPS despite matching revenue; share count or basis differs; management did not explain.

What moved the numbers, as management explained it

  • AIIMS Jammu bill finalisation reduced billing by ₹29 cr, shaving 2.6% off EBITDA; one-off, going to arbitration. (one-off)
  • Government-mandated 35-40% labour cost hike in NCR (50% of portfolio) drove ~1.5% company-level EBITDA hit; seen as new normal.
  • SIR drives and elections in West Bengal and Assam reduced turnover and pushed up IDC costs; one-off, now recovering. (one-off)
  • Staff costs rose as company ramped up headcount for enlarged project portfolio (Central Vista, Dahlias, DLF Downtown).
  • Steel, panels, switchgear supply chains disrupted by war; delivery time extended from 4-6 weeks to 3-4 months.

The numbers management led with

  • Net order book: INR20,663.52 crore executable over 3–3.5 years
  • AIIMS Jammu final-bill adjustment: INR29 crore reduction with a 2.6 percentage-point EBITDA impact
  • Order inflow: INR4,000–5,000 crore for FY27, reduced from INR8,000 crore
  • Capex: INR220–250 crore in FY27, reduced from INR300 crore; Q2 FY27 capex INR60 crore

Guidance

Guidance on this call

WhatForWhat management said
Top-line growthFY27top-line growth of about 12% to 15%
EBITDA margin (rules out double-digit)FY27Ruling out double-digit EBITDA margin for FY27
FY27 capexFY27full year capex ₹220-250 cr
FY27 order inflowFY27order inflow of ~₹4,000-5,000 cr for FY27
Central Vista billingFY27Central Vista billing ₹700 cr in FY27
Central Vista billingFY28Central Vista billing ~₹1,000 cr in FY28
CST billingFY27CST billing ₹400-450 cr in FY27
CST billingFY28CST billing ~₹700 cr in FY28
Gems and Jewellery Park billingFY27Gems and Jewellery Park billing ~₹100 cr in FY27
Gems and Jewellery Park billingFY28Gems and Jewellery Park billing ~₹450 cr in FY28
Dahlias monthly billingFY27Dahlias billing ₹30-35 cr per month
DLF Downtown monthly billingFY27DLF Downtown billing ₹25-30 cr per month
Central Vista monthly billingFY27Central Vista billing ~₹60 cr per month

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY26 revenue growthFY2615% (on the Q4 FY25 call)35.9%, above the figure guided
FY26 revenue growthFY2615–20% (on the Q1 FY26 call)35.9%, above the range
Consolidated revenue growthFY2615–20% (on the Q2 FY26 call)35.9%, above the range
FY26 top line growthFY2610–15% (on the Q3 FY26 call)35.9%, above the range
Q4 FY26 revenueQ4 FY26₹1,400 cr (on the Q3 FY26 call)₹1,322 cr, below the figure guided
FY26 EBITDA marginFY26at least 10% (on the Q3 FY26 call)9.4%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

Balance sheet, capex and funding

  • Trade payable ₹776 cr; trade receivable ₹632 cr; retention ₹401 cr.
  • Inventory incl. real estate ₹391 cr; mobilization advance ₹924 cr (31% interest-bearing at ~8%); unbilled revenue ₹946 cr.
  • Cash and bank balance ₹920 cr; gross debt ~₹2.28 cr (essentially debt-free).
  • Q1 capex spent ₹60 cr; FY27 capex guidance cut to ₹220-250 cr from ₹300 cr.
  • Working capital cycle at 119 days; expected to ease as Assam receivables start coming in.
  • Quarterly finance cost rose to ~₹15-16 cr on Central Vista mobilization; expected to recur.

The industry, as management sees it

Management sees construction execution as increasingly difficult because skilled-labour scarcity, wage inflation, project complexity, material-supply disruption, regulatory action and elections are occurring more frequently. The company expects these conditions to require higher risk-adjusted bids and greater investment in machinery, digitisation and execution efficiency.

Risks management named

  • AIIMS Jammu bill value fell INR29 crore; arbitration recovery and timing remain uncertain.
  • NCR labour rates rose 35–40% and form a higher cost base, without universal escalation.
  • NGT restrictions could affect NCR projects, but the EBITDA impact is not yet quantifiable.
  • Material prices and war-related supply delays remain volatile; switchgear lead times lengthened.
  • Elections and SIR work delayed approvals and payments in Assam and constrained West Bengal execution.
  • Client design changes and staged approvals delayed project starts and increased IDC.

Q&A

Q&A was dominated by the Q1 margin decline, the permanence of labour inflation, the absence of universal escalation rights and uncertainty around NGT. Shravan Shah and Parikshit Kandpal pressed repeatedly on quantification and timing, while Sandip Sabharwal's exchange with management over prior-call awareness and guidance credibility produced the call's strongest pushback. Management remained more forthcoming on project billing and working-capital fixes than on FY27 margin normalisation and FY28 double-digit margins.

Not answered directly

  • Q2 and Q3 FY27 margin normalisation
  • NGT EBITDA impact
  • Client labour-cost compensation
  • FY28 double-digit EBITDA margin
  • Order-book labour escalation coverage
  • Working-capital day trajectory
  • Haryana wage-policy motivation

Asked for a number, answered without one

  • NGT impact on EBITDA: we can't quantify the impact on our EBITDA of the NGT -- potential NGT impact.
  • Order book with labour escalation clause: We don't have that data as of now, but you can reach out to Satbeer, we will get back to you on that.
  • Timing of client compensation for labour cost: it is not possible for us to put a date as to when we will be compensated, whether it will be in Q2

Every question, with its answer

  1. 1. EBITDA margin bridge

    Shravan Shah, Dolat Capital

    Question. Why was EBITDA margin historically low, and was the INR29 crore AIIMS Jammu reduction booked in raw-material cost, causing a 2.6% impact?

    Answer, Shobhit Uppal, Deputy Managing Director. The AIIMS Jammu final bill was frozen at INR29 crore below the previous billing value, while project costs remained. This reduced receivables and EBITDA by 2.6 percentage points, and the company will pursue arbitration.

    Follow-up. Were the West Bengal and Assam disruptions and labour or staff-cost increases also known at the previous call and responsible for the Q1 decline?

    Answer. Management said the labour increase was not known at the prior call. Some contracts lack escalation clauses, claims have been submitted, and the impact was especially severe because nearly 50% of the order book is in NCR.

  2. 2. FY27 margin outlook

    Shravan Shah, Dolat Capital

    Question. Can Q2 margins be estimated, and is a return to double-digit EBITDA margin possible from Q3 despite the labour increase and potential NGT disruption?

    Answer, Shobhit Uppal, Deputy Managing Director. Management expects some client compensation to begin over the next two quarters but said timing and amount remain uncertain. Potential NGT action in Delhi and Haryana was not yet in writing, and management could not quantify its EBITDA impact or commit to Q3 double-digit margins.

    Follow-up. What is the maximum reasonable margin for the full year, or could double-digit margins return from Q1 FY28?

    Answer. Management ruled out a double-digit EBITDA margin for FY27, citing black-swan events. It hopes to return toward prior-year margins over the next three quarters, but said the unquantified NGT impact remains a material rider.

    Not answered directly.

  3. 3. Revenue growth

    Shravan Shah, Dolat Capital

    Question. Does the disruption change the previously expected 15–20% revenue growth for this year or FY28?

    Answer, Shobhit Uppal, Deputy Managing Director. Management retained FY27 revenue-growth guidance of approximately 12–15% and expects margins to be around the historical levels seen over the past couple of years once project execution ramps up.

  4. 4. Balance sheet and working capital

    Shravan Shah, Dolat Capital

    Question. Please provide the quarter-end trade-payable, retention, inventory, mobilisation, unbilled-revenue, debt and cash balances.

    Answer, Management. Management reported trade payables of INR776 crore, retention of INR401 crore, inventory including real estate of INR391 crore, mobilisation of INR924 crore, unbilled revenue of INR946 crore, gross debt of INR2.28 crore and cash and bank balances of INR920 crore.

  5. 5. Finance cost

    Vaibhav Shah, JM Financial

    Question. Why did finance cost rise sharply, will INR15–16 crore recur, and how much of the INR924 crore mobilisation advance bears interest at what rate?

    Answer, Management. Finance cost increased because a mobilisation advance was availed for the new Central Vista project. Management expects a similar quarterly cost, with 31% of the INR924 crore mobilisation advance interest-bearing at an average rate of about 8%.

  6. 6. Gems and Jewellery Park

    Vaibhav Shah, JM Financial

    Question. When will the Gems and Jewellery Park begin, and what billing can be expected in FY27 and FY28?

    Answer, Shobhit Uppal, Deputy Managing Director. Client-driven design changes delayed ground work until Q3 FY27. Management expects about INR100 crore of billing in FY27 and around INR450 crore in FY28, with a 3.5-year completion schedule.

    Follow-up. What will FY28 billing be and what is the project completion timeframe?

    Answer. FY28 billing is expected at about INR450 crore, and the project is scheduled for completion over 3.5 years.

  7. 7. CST execution

    Vaibhav Shah, JM Financial

    Question. How will CST revenue progress, why is it below the earlier INR600 crore target, and are there project-specific execution issues?

    Answer, Shobhit Uppal, Deputy Managing Director. Management expects INR400–450 crore in FY27 and about INR700 crore in FY28. It still hopes to cross INR500 crore this year. Staged client approvals and traffic-dependent station-area blocks prevent a faster ramp-up.

    Follow-up. Is the shortfall due to a project-specific problem?

    Answer. The project has two parts: platform and station work, where blocks depend on traffic availability, and new buildings where client approvals are released in stages. This sequencing, rather than a single project failure, is slowing execution.

  8. 8. Central Vista progress

    Vaibhav Shah, JM Financial

    Question. What is the Central Vista execution status and expected billing in FY27 and FY28?

    Answer, Shobhit Uppal, Deputy Managing Director. Nirman Bhawan has been demolished, foundation casting has started and structural-steel work was expected to begin in September. Udyog Bhawan was 90% demolished, with foundation work expected to start within a month. Billing is targeted at INR700 crore in FY27 and INR1,000 crore in FY28.

    Follow-up. When will the first building and the full project be completed?

    Answer. The building replacing Nirman Bhawan represents about 50% of the job and is targeted for commissioning by the end of FY28. The entire project is expected to be completed in FY29.

  9. 9. Revenue guidance and NGT

    Vaibhav Shah, JM Financial

    Question. Does the 12–15% revenue-growth range represent a reduction from the prior 15% guidance, and could growth exceed 15% if NGT disruption is limited?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said the prior target was 15% and that it is sticking to it; the 12–15% range reflects uncertainty over NGT. If the disruption is limited, revenue growth could exceed 15%.

    Follow-up. If NGT disruption is similar to last year, could growth cross 15%?

    Answer. Management said yes, growth could cross 15% under that scenario.

  10. 10. Guidance credibility

    Sandip Sabharwal, asksandipsabharwal.com

    Question. The previous call occurred during the quarter, so why was the labour impact not flagged, and how relevant is management guidance when actual outcomes have diverged materially?

    Answer, Shobhit Uppal, Deputy Managing Director. Management disputed the premise, said the call only gives the information then available and argued that the unusually severe labour shortage was difficult to predict. The response became defensive, repeatedly asking for more specific evidence and accusing the analyst of implying that information was concealed.

    Follow-up. The analyst asked when the labour increase began and whether it applied for the full quarter; management said it was an ongoing market-driven increase, particularly acute over the last two months.

    Answer. Management attributed the impact to festival-related labour scarcity and demand-supply conditions, saying 50–60% of total labour and up to 80% of skilled labour was Muslim. It said government increases of 35–40% compounded a shortage that was difficult to forecast.

    Not answered directly.

  11. 11. Labour contract protections

    Vishal Periwal, PL Capital

    Question. Is the labour increase a statutory or change-in-law event that can be passed to customers, and how severe is the on-site labour shortage?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said it is not categorised as a statutory increase, although specific statutory components such as PF changes would be recoverable. Projects, particularly in NCR, were operating at only 40–50% labour strength, and clients were reviewing compensation claims even where escalation clauses were absent.

  12. 12. Employee-cost accounting

    Vishal Periwal, PL Capital

    Question. How is direct labour reflected in employee cost versus subcontractor or labour-supplier costs?

    Answer, Satbeer Singh, Chief Financial Officer. Labour employed directly by the company is included in employee cost, while contractor and labour-supplier labour is included in subcontractor or labour costs.

  13. 13. Staff cost normalisation

    Vishal Periwal, PL Capital

    Question. Was the higher employee cost a one-off such as bonuses, or will it recur as turnover grows?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said it was not a one-off charge. Staffing had already been ramped for Central Vista, DLF Dahlias and DLF Downtown, and the higher cost should rationalise as those large projects contribute more turnover.

  14. 14. L1 orders and conversion

    Shravan Shah, Dolat Capital

    Question. What happened to the previously disclosed Odisha Government University and Delhi hospital L1 orders, and is the RML hospital still L1?

    Answer, Shobhit Uppal, Deputy Managing Director. The university L1 fell through because the company refused to extend bid validity for a fixed-price contract amid rising costs. RML remains L1, has not become a work order, and is separate from the INR512.81 crore inflow already booked; its value is about INR500 crore.

  15. 15. Order inflow and bid discipline

    Shravan Shah, Dolat Capital

    Question. Is the prior INR8,000 crore FY27 order-inflow guidance intact, what is the bid pipeline, and what portion of the order book is fixed-price?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said it is no longer pursuing INR8,000 crore aggressively because material and labour volatility remains high. At least INR4,000–5,000 crore of inflows is achievable, the visible bid pipeline is about INR5,000–6,000 crore, and bids will incorporate current ground realities rather than be priced aggressively.

    Follow-up. What is the fixed-price share of the order book?

    Answer. Management confirmed that fixed-price contracts represent 10.34% of the order book.

  16. 16. Capex and working capital

    Shravan Shah, Dolat Capital

    Question. What capex is planned for Q2 and FY27, and how will working capital move from the current level?

    Answer, Management. Q2 FY27 capex was reduced to INR60 crore and FY27 capex to INR220–250 crore from INR300 crore. The working-capital response was unclear but suggested the current quarter would be lower before returning toward the previous quarter's level.

    Not answered directly.

  17. 17. Input-cost inflation

    Parvez Qazi, Nuvama Group

    Question. How have commodity and supply-chain volatility, project design changes and IDC costs affected execution, and what billing is expected from the major NCR projects?

    Answer, Shobhit Uppal, Deputy Managing Director. War-related supply disruption raised material prices and extended switchgear delivery from 4–6 weeks to 3–4 months. Design changes and labour shortages also reduced DLF Dahlias execution. Management targets monthly billing of INR30–35 crore from Dahlias, close to INR60 crore from Central Vista and INR25–30 crore from DLF Downtown.

  18. 18. Project collections

    Parvez Qazi, Nuvama Group

    Question. How do collections compare with six months earlier across central and state government projects?

    Answer, Shobhit Uppal, Deputy Managing Director. Central government payments were described as generally satisfactory, except for a Himachal Central University project where certified bills had been unpaid for five months. Assam election delays were easing and large dues had begun arriving; West Bengal and Assam disruptions also constrained execution.

  19. 19. Bid risk management

    Parvez Qazi, Nuvama Group

    Question. How is management incorporating labour, safety and execution volatility into future project bids?

    Answer, Shobhit Uppal, Deputy Managing Director. Future bids will incorporate observed cost inflation. Shuttering and related inputs have been repriced, staff costs above 5% are treated as the new normal, and the safety budget has risen from about 1% to nearly 3%. Management believes higher risk-adjusted bids will support historical margins.

  20. 20. AIIMS Jammu arbitration

    Jainam Shah, Equirus Securities

    Question. Does the AIIMS Jammu amount remain embedded in unbilled revenue, inventory or another asset, or is there potential for a further earnings hit?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said the project is closed, the INR29 crore has not been recognised as revenue and no related asset remains. It indicated there should be no further P&L impact from the finalisation.

  21. 21. Depreciation and FY28 margin

    Parth Thakkar, JM Financial

    Question. Is the higher depreciation recurring, and can EBITDA margin return to double digits in FY28?

    Answer, Management. Depreciation is expected to remain elevated following higher capex over the past two to three years. On FY28 margins, Shobhit Uppal said double digits remain an aspiration, but NGT, labour, elections and other recurring disruptions make a firm prediction difficult.

    Not answered directly.

  22. 22. Escalation-clause exposure

    Mahesh Patil, ICICI Securities

    Question. What percentage of the order book has a labour-cost escalation clause, particularly in NCR?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said the data was not currently available and directed the analyst to contact the CFO. Satbeer Singh said the analyst could send the question by email.

    Not answered directly.

  23. 23. Labour cost base

    Shubham Harne, Purnartha Investment Advisers

    Question. For how much of Q1 was the company exposed to higher labour costs, and does the increase establish a permanent new cost base?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said the higher labour cost affected the whole quarter and is unlikely to reverse because market labour prices do not normally fall once increased.

    Follow-up. Does that mean the entire quarter carried a permanently higher labour-cost base?

    Answer. Management confirmed that the higher rate had become the new base.

  24. 24. NGT disruption

    Shubham Harne, Purnartha Investment Advisers

    Question. How will potential NGT restrictions affect Central Vista, and can labour be moved from other NCR projects?

    Answer, Management. Management expects the impact on Central Vista to be limited, if any, because special permissions are being sought and work has not stopped. The main issue may be inward material movement, and management confirmed labour would be shifted from other NCR projects where possible.

    Not answered directly.

  25. 25. EBITDA margin bridge

    Shubham Harne, Purnartha Investment Advisers

    Question. Aside from the 2.6% AIIMS impact, were labour and staff costs the only other major margin pressures, and which material costs are pass-throughs?

    Answer, Management. Management identified higher labour and staffing costs as the other major pressures. Volatile inputs such as cement and steel are generally pass-through items, while the more persistent impact is labour-related.

  26. 26. Escalation timing

    Shubham Harne, Purnartha Investment Advisers

    Question. What is the typical lag before private and government customers pass through higher material costs?

    Answer, Management. Private contracts generally compensate increases over a base price with each bill after roughly a 30-day lag. Government contracts use quarterly WPI-linked escalation bills based on the published index.

  27. 27. Client compensation

    Vaibhav Shah, JM Financial

    Question. For the approximately 90% of the book without fixed-price exposure, are clients contractually obliged to compensate the higher labour cost?

    Answer, Shobhit Uppal, Deputy Managing Director. Management clarified that variable pricing does not automatically imply labour escalation. For NCR clients without an escalation clause, compensation is not a strict contractual entitlement; discussions cover both the impact already incurred and options for the balance of the work.

    Not answered directly.

  28. 28. Delay penalties

    Madhur Rathi, Counter Cyclical Investments

    Question. Despite the order book doubling, should investors worry about delay penalties if labour, NGT and other execution issues persist?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said Ahluwalia has not paid any customer penalty to date and that extensions of time have generally been granted where delays were outside its control. It cited growing project complexity, recurring client design changes, labour shortages, NGT and elections as industry-wide execution factors.

    Follow-up. Given the order book, why have margins not expanded, and are peers converting the same conditions more successfully?

    Answer. Management attributed the margin decline to labour shortages, greater project complexity, higher staffing and IDC costs. It said comparisons should use a longer period because B. L. Kashyap has a much smaller base.

    Partly answered.

  29. 29. Order-book mix and margins

    Madhur Rathi, Counter Cyclical Investments

    Question. If the private-sector order mix is already high, why have margins not returned to the earlier low-teen levels?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said newer conditions, particularly labour shortages, project complexity, higher staffing costs and IDC, have emerged over the last several years. These factors are now being incorporated into future bids.

  30. 30. Capital allocation

    Madhur Rathi, Counter Cyclical Investments

    Question. With surplus cash, low dividend yield and long-term share-price underperformance, why is the company not conducting share buybacks?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said buybacks are not on the agenda. Cash is intended for growth, digitisation, efficiency, machinery investment to mitigate labour shortages and navigating sector volatility.

  31. 31. NCR labour economics

    Parikshit Kandpal, HDFC Securities

    Question. How much labour is deployed in NCR, what proportion is skilled versus minimum-wage labour, and what was the company's Q1 EBITDA impact from the labour increase?

    Answer, Shobhit Uppal, Deputy Managing Director. Management estimated 10,000–12,000 workers, with 70% skilled. The project-level impact can range from 2% to 5% of turnover where materials are supplied by the client, while the Q1 company-level impact was about 1.5% of EBITDA.

    Follow-up. What is the permanent hit if clients provide no escalation, and can productivity gains or completion incentives offset it?

    Answer. Management estimated an ongoing hit of about 1% where there is no escalation. Some large developers have introduced incentives linked to progress and timely completion, which may partly offset the higher cost.

    Not answered directly.

  32. 32. Haryana labour policy

    Parikshit Kandpal, HDFC Securities

    Question. Why did Haryana increase labour pricing, could other states follow, and how should the broader margin exposure be assessed?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said it could not establish the government's motivation. It noted that 90% of Haryana's RMC plants had reportedly been shut down, but did not link that action definitively to wages. It believes the labour increase is politically unlikely to be reversed and that scarce, lower-skilled labour is reducing productivity.

    Follow-up. Does the impact arise from minimum-wage regulation or market pricing for skilled labour?

    Answer. Management said the 35–40% wage increase is only part of the issue; the larger problem is severe skilled-labour scarcity and the productivity required for increasingly complex buildings.

    Not answered directly.

  33. 33. Migrant labour

    Parikshit Kandpal, HDFC Securities

    Question. Can labour be brought in from other states, or is the wage issue specific to workers domiciled in Haryana?

    Answer, Shobhit Uppal, Deputy Managing Director. Management said the workers are migrant labour from Bihar, Bengal, Odisha and Madhya Pradesh, not Haryana-domiciled labour. The issue therefore reflects where the work is performed and prevailing market conditions rather than worker domicile.

What was said

Topic by topic, in the order it was spoken

Q1 Financial Performance · Shobhit Uppal (Deputy Managing Director)

  • Turnover increased 12.03% year over year to INR1,125.81 crore, while PAT declined 77.65% to INR11.42 crore.
  • EPS declined to INR1.70 from INR7.63 in 1QFY26.
  • EBITDA margin fell to 4.29% from 8.59%, and PAT margin declined to 1% from 5.01%.
  • West Bengal and Assam election-related work disruption reduced execution and increased IDC costs.

EBITDA Margin Pressure · Shobhit Uppal (Deputy Managing Director)

  • The final AIIMS Jammu bill was reduced by INR29 crore, shaving 2.6 percentage points from EBITDA margin.
  • The company considers the AIIMS Jammu reduction a dispute and intends to begin arbitration.
  • NCR represents nearly 50% of the portfolio, where labour rates increased approximately 35–40%.
  • Several large contracts lack labour-escalation clauses, leaving recovery dependent on client claims and negotiations.
  • The employee base was increased to mobilise a larger project portfolio, creating a higher recurring staff-cost base.

Order Book and Inflows · Shobhit Uppal (Deputy Managing Director)

  • Net order book at 30 June 2026 was INR20,663.52 crore, executable over the next 3–3.5 years.
  • Order inflow through 30 June 2026, and available as of the call, was INR512.81 crore.
  • Management said the large order book allows greater selectivity in pursuing new work.
  • Management remained ready to receive questions after presenting the initial highlights.

In their words

this financial year, we are ruling out having a double-digit EBITDA margin.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)
This is a cause of dispute, and now that the bill has been finalised, the dispute will be raised through an arbitration process.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)
all that share buyback is not really on the agenda for us. It's not a part of our plan.
Shobhit Uppal (Deputy Managing Director, Ahluwalia Contracts)

To check next time

What management committed to on this call, or the dates they gave.

  • Whether client compensation for higher labour costs starts flowing in over the next two quarters as guided.
  • Quantification of NGT impact on NCR project execution and margins.
  • Central Vista billing ramp to targeted ~₹60 cr per month.
  • Dahlias billing ramp to targeted ₹30-35 cr per month.
  • Conversion of L1 RML order (~₹500 cr) into a work order.
  • Progress on arbitration to recover the ₹29 cr AIIMS Jammu bill cut.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Tue 18 Aug 2026₹707.70−10.85%−0.55%
5 sessions Mon 24 Aug 2026₹649.60−18.17%−0.28%
20 sessions Tue 15 Sept 2026₹585.85−26.20%−4.81%

From the close of Mon 17 Aug 2026, ₹793.85: the call began at 16:00 IST, after the market closed, so that day's close is the base. Adjusted daily closes; the move includes everything else that happened in those sessions.

Ahluwalia Cont Ind's other calls

  • Q2 FY27Mon 16 Nov 2026Tone: Mixed
  • Q4 FY26Mon 1 Jun 2026Tone: Mixed
  • Q3 FY26Mon 16 Feb 2026Tone: Cautious
  • Q2 FY26Mon 17 Nov 2025Tone: Confident
  • Q1 FY26Mon 18 Aug 2025Tone: Confident
  • Q4 FY25Mon 2 Jun 2025Tone: Confident
  • Q3 FY25Wed 12 Feb 2025Tone: Cautious
  • Q1 FY25Fri 16 Aug 2024Tone: Cautious