Electrosteel Castings Q4 FY24 earnings call
In brief
ECL Q4 FY24: PAT up 154% YoY to Rs.227 cr; EBITDA margin expands 495 bps to 17%; guides 1 mt capacity by FY27
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- First guidance issued
- Analyst pushback
- Medium
- Stock, next session
- −2.98% (Nifty 50 +0.22%)
- Q4 FY24 consolidated PAT grew 154% YoY to Rs. 227 cr; EBITDA margin expanded 495 bps to 17% on total income of Rs. 2,039 cr.
- Q4 included ~Rs. 60 cr Khardah plant renovation expense and a 15-day shutdown, with 53 days of shutdown for FY24 in total.
- Capex of Rs. 390 cr spent out of Rs. 650 cr plan; new capacity up by Sept-Oct 2025, taking total to ~9 lakh TPA.
- Board approved 1 lakh tonne Srikalahasthi expansion (Rs. 64 cr capex, 15 months) and 500-acre land acquisition in Odisha for new DI plant.
- Guides FY25 volume of 8.5 lakh tonnes, FY26 at 9 lakh tonnes, FY27 at 1 million tonnes; EBITDA margin sustained at 17-18%.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q4 FY24
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹2,004 cr | +7.0% | +7.2% | |
| EBITDA (excl. other income) | ₹311 cr | +61.5% | −23.4% | 15.5% (10.3% a year ago) |
| Net profit | ₹227 cr | +153.9% | −13.8% | 11.3% (4.8% a year ago) |
| EPS (₹) | ₹3.71 | +147.3% | −16.1% |
From the company's filed results for the quarter ended 31 Mar 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
Where management's figures differ from the filing
- EBITDA (Q4 FY24): said Consolidated EBITDA Rs. 346 cr, margin 17% (includes other income); filed EBITDA excl. other income Rs. 311.28 cr, margin 15.5%. Management's Rs. 346 cr EBITDA includes other income of Rs. 34.30 cr; the filed figure excludes it, which is why margins differ by ~150 bps.
What moved the numbers, as management explained it
- Khardah plant renovation/repair expense of ~Rs. 60 cr booked in Q4 (Rs. 13 cr in Q3, balance in Q4) depressed EBITDA; 15-day Q4 shutdown cut capacity utilisation to 93%. (one-off)
- Coal and iron ore costs rose 8-10% in Q4 vs Q3 on raw material booked through production, lifting other expenses sequentially.
- Tax reversal of Rs. 36.5 cr for earlier years after a High Court order lifted Q4 PAT — not a recurring item. (one-off)
- Fuel surcharge provision of Rs. 14 cr at Srikalahasthi in Q4 raised other expenses; pending settlement by government/court in FY25. (one-off)
- Unrealised profit on intra-group stock with subsidiaries is eliminated in consolidated accounts per Ind AS, causing the subsidiary P&L to look weaker than standalone on a sequential basis. (accounting)
The numbers management led with
- FY25 volume guidance: ~8.5 lakh tonnes of FY25
- Capacity roadmap: 9 lakh TPA by FY26 and 1 million TPA (10 lakh) by FY27
- Srikalahasthi brownfield expansion: Additional 1 lakh tonne DI pipe capacity at Rs ~64 cr CAPEX; 15-month execution timeline
- Odisha Greenfield land: 500 acres being acquired in Odisha with government support for new DI pipe & fittings plant
- Order book: ~6 lakh tonnes / 9-10 months visibility; Rs 4,500–5,000 cr value
Guidance
Guidance on this call
| What | For | What management said | Filed |
|---|---|---|---|
| EBITDA margin | FY25 | Confident of maintaining EBITDA in the range of 17% to 18% for FY25. | 14.2%, below the range |
| DI pipe volume | FY25 | Expect to close FY25 with output of 8,50,000 tonnes of pipe. | — |
| DI pipe volume | FY26 | FY26 will see 9 lakh tonnes of volume. | — |
| DI pipe volume / capacity | FY27 | FY27 will be at 1 million tonnes of capacity. | — |
| FY25 capex (ex-Odisha) | FY25 | FY25 capex is around Rs. 200 to 225 crores maximum, apart from Odisha. | — |
| Srikalahasthi capacity addition | FY25-FY26 | Board approved 1 lakh tonne DI pipe capacity addition at Srikalahasthi; capex ~Rs. 64 cr, up in 15 months. | — |
| Order book visibility | FY25 | Order book visibility of 9 to 10 months, ~6 lakh tonnes, value around Rs. 4,500-5,000 crores. | — |
| Long-term debt free | FY25 | Company will be long-term debt free in FY25; borrowings for Odisha will be decided later. | — |
| Two-year debt repayment commitment | FY25-FY26 | Company has to pay Rs. 330 crores of debt over the next two years per bank commitments. | — |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
Ductile Iron (DI) pipes and fittings
Q4 consolidated total income Rs. 2,039 cr (+6.8% YoY), EBITDA Rs. 346 cr (~+51% YoY, margin 17%), PAT Rs. 227 cr (+154% YoY); standalone DI pipe sales 1,96,000 tonnes in Q4 and 7.47 lakh tonnes in FY24.
Q4 consolidated total income Rs. 2,039 cr (+6.8% YoY) · Q4 consolidated EBITDA Rs. 346 cr (~+51% YoY) · Q4 consolidated EBITDA margin 17% (+495 bps YoY) · Q4 consolidated PAT Rs. 227 cr (+154% YoY) · Q4 consolidated PAT margin 11.1% (+645 bps YoY) · Q4 standalone DI pipe sales 1,96,000 tonnes · FY24 standalone DI pipe sales 7.47 lakh tonnes · FY24 consolidated total income Rs. 7,580 cr · FY24 consolidated EBITDA Rs. 1,281 cr (+56%) · FY24 consolidated PAT Rs. 740 cr (+134%) · FY24 EPS Rs. 12.30 · EBITDA per tonne Rs. 15,000-16,000 · Average realisation Rs. 74,000-75,000 per tonne (FY24)
Outlook: Volume 8.5 lakh tonnes in FY25, 9 lakh tonnes in FY26 and 1 million tonnes in FY27; total capacity to reach 1 million TPA after Srikalahasthi (+1 lakh tonne, 15 months) and Odisha greenfield.
Balance sheet, capex and funding
- Standalone gross debt Rs. 2,010 cr; net debt Rs. 1,523 cr with net debt/equity 0.31:1 as of 31-Mar-2024.
- Consolidated gross debt reduced to Rs. 1,722 cr from Rs. 2,266 cr; consolidated net debt/equity 0.34:1.
- Capex spent Rs. 390 cr of the Rs. 650 cr plan; new 9 lakh TPA capacity operational by Sept-Oct 2025.
- FY25 capex guided at Rs. 200-225 cr (ex-Odisha); Rs. 64 cr for Srikalahasthi +1 lakh tonne expansion (15 months).
- Plans to be long-term debt free by FY25 end; Odisha project borrowings to be decided later.
- Committed debt repayment of Rs. 330 cr over the next two years; land and Srikalahasthi capex funded from internal accruals.
The industry, as management sees it
Management views domestic DI pipe demand as structurally ahead of supply for the next 2-3 years despite industry capacity additions; expects the current Jal Jeevan Mission cycle (Rs 3.1 lakh cr of Rs 3.6 lakh cr already deployed) to continue in the post-election budget and anticipates demand shifting back to ductile pipes from alternate types once DI supply catches up. Industry capacity estimated at ~46–48 lakh tonnes in FY25 rising to ~57 lakh tonnes in FY26.
Risks management named
- Parbatpur coal block recovery timing uncertain; next Delhi HC hearing on the 25th; past projections proved wrong
- US export market not expected to see material growth in current environment
- Q4 raw material (coal, iron ore) costs up 8–10% YoY
- Fuel surcharge provision of Rs 14 cr at Srikalahasthi in Q4 may or may not need to be paid — government/court to decide
- Railway arbitration award (Rs 252 cr) under challenge in divisional bench; outcome pending
Q&A
Q&A was dominated by three threads: (i) demand-supply dynamics for DI pipes and management's confidence in the multi-year gap persisting despite industry capacity additions by Jai Balaji, Tata Steel and Shyam Metallic's; (ii) the new capacity roadmap (Srikalahasthi brownfield + 500-acre Odisha Greenfield) where management gave volume and margin guidance but deflected on Odisha CAPEX size, land cost and product mix; (iii) Khardah shutdown explanation, EBITDA per tonne sustainability and the Rs 60 cr renovation cost. Pushback was highest on Parbatpur coal block (Saloni Hemnani), US export realisation (Jojo Shaju) and fuel-surcharge provisioning (Saket Kapoor) — all three received evasive/deferred answers. The 1 million tonne capacity milestone by FY27 and 17–18% EBITDA margin band for FY25 were the standout specific commitments.
Not answered directly
- Odisha Greenfield CAPEX size and capacity
- Odisha land acquisition cost
- Parbatpur coal block recovery quantum
- US export realisation and growth outlook
- New product additions beyond DI pipes
- Funding mechanism for Odisha project (QIP/debt)
Asked for a number, answered without one
- Odisha plant volume and capex: Management said the Odisha project is still on the drawing board; the Board has not finalised it, so they declined to share numbers and will update once approved.
- Cost of 500-acre Odisha land: Management said final negotiations with the vendor are ongoing and within 15 days the deal will be closed; declined to give a number citing vendor restrictions.
- Parbatpur coal block recovery: Management said past projections on this matter had proved wrong; the matter is moving forward with the next Delhi High Court hearing on the 25th, but no quantification was given.
- US market exports volume and realisation: Management said US contributes ~10% of ECL's exports but declined to give a specific volume growth, saying the US outlook is not very positive, and refused to quantify US realisation citing competitor presence on the call.
Every question, with its answer
1. Subsidiary performance and IndAS adjustments
Vikas Singh, PhillipCapital
Question. Q4 standalone vs consolidated — subsidiary performance appears to have declined sequentially with higher other expenses. Is this a one-off and will subsidiaries bounce back next quarter?
Answer, Gaurav Somani, General Manager Finance. Consolidated EBITDA at Rs 346 cr is actually higher than standalone Rs 319 cr. On the sequential decline, when the company sells to subsidiaries there is an adjustment of unrealised profit on the stock lying there as per IndAS accounting norms.
Follow-up. Can you give the timeframe for the 9 lakh tonne capacity addition and what volume we should build into FY25 estimates?
Answer. Uddhav Kejriwal: We expect to conclude FY25 at 8,50,000 tonnes, FY26 at 9 lakh tonnes and FY27 at 1 million tonnes.
2. EBITDA per tonne sustainability and Odisha funding
Vikas Singh, PhillipCapital
Question. FY24 blended EBITDA was closer to Rs 17,000 per tonne. Is this a sustainable run rate, lower, or should we expect something higher?
Answer, Ashutosh Agarwal, Whole Time Director & CFO. Management is slightly confident about 17% margin and will chase a better percentage; the company can do better than 17–18%. On Odisha land, internal accruals are available and the company will not borrow for that; Srikalahasthi 1 lakh tonne expansion requires only balancing equipment so capex is nominal. Debt commitments to bankers will be met first.
Partly answered.
3. Industry demand-supply dynamics
Gunit Singh, Counter Cyclical PMS
Question. Competitors like Jai Balaji and Tata Steel are also adding capacity. What is the current overall demand and supply in India for DI pipes and the installed industry capacity?
Answer, Umang Kejriwal, Managing Director. Currently industry players are unable to meet demand; new capacity is coming up and the budget post-elections is expected to maintain this trajectory. Ashutosh Agarwal quantified industry capacity at ~46–48 lakh tonnes in FY25 and ~57 lakh tonnes in FY26.
Follow-up. Are you not concerned about overcrowding as all players add capacity? Will demand still be ahead of supply going forward?
Answer. Ashutosh Agarwal: Board's capacity decision was taken after proper due diligence on domestic and international demand forecast.
4. FY25 volume and EBITDA guidance
Gunit Singh, Counter Cyclical PMS
Question. Post Jal Jeevan Mission completion in 3-4 years, what would drive DI pipe demand? What is FY25 volume and EBITDA guidance and are you confident of holding the Q4 EBITDA margin?
Answer, Uddhav Kejriwal, Whole Time Director. Umang Kejriwal: With India's GDP growing ~7%, the scenario looks alright; once ductile pipe supply is met, demand will convert back from other pipe types. Uddhav Kejriwal: FY25 production and sales targeted at 8,50,000 tonnes; confident of maintaining EBITDA in the 17–18% range. FY24 closed at 7,50,000 tonnes.
5. Export mix and outlook
Aryan Sharma, B&K Securities
Question. Exports fell from 17% to 15% of total volumes in FY24. Reasons, expected future mix and demand regions?
Answer, Umang Kejriwal, Managing Director. Management plans domestic vs export allocation period-to-period based on which demand to meet first; quarter-on-quarter export share should not be over-interpreted.
Follow-up. CAPEX plans for FY25 and FY26 — total amount including Odisha land and the capacity addition from Odisha?
Answer. Ashutosh Agarwal: Odisha CAPEX will be phased; details on drawing-board stage; debt-equity plan will clarify in 1-2 months. FY25 CAPEX (ex-Odisha) is around Rs 200–225 cr maximum.
Not answered directly.
6. Srikalahasthi expansion
Rakesh Roy, Omkara Capital
Question. In which plant is the 1 lakh tonne capacity addition happening and what is the post-expansion capacity at Srikalahasthi?
Answer, Ashutosh Agarwal, Whole Time Director & CFO. Srikalahasthi unit in South India near Tirupati. Current ~5,50,000 tonnes; post expansion it will be 6.5 lakh tonnes.
Follow-up. Once demand-supply gap is filled in 2-3 years (Shyam Metallic and others coming in), how do you maintain growth and market share?
Answer. Umang Kejriwal: Forecast is that demand-supply will not equalise in two years; we will have demand in the market.
7. Product portfolio diversification
Rakesh Roy, Omkara Capital
Question. Any plans to add a new product beyond DI pipes in the next 1-3 years?
Answer, Umang Kejriwal, Managing Director. Discussions are ongoing but nothing concrete to share; will announce when firmed up, as was done with Srikalahasthi expansion and Odisha project.
Not answered directly.
8. Capacity timeline and order book
Kuber Chauhan, Anand Rathi
Question. When will 1 million tonne capacity come online and what is the current order book in volume and value terms?
Answer, Uddhav Kejriwal, Whole Time Director. 1 million tonne capacity by FY26-27. Order book visibility of 9-10 months, equivalent to ~6 lakh tonnes. Gaurav Somani: Order book value around Rs 4,500 cr.
9. OPVC vs DI pipe competition
Dey, Niveshaay Investment Advisory
Question. On OPVC pipes competition in 100-200 mm diameters — what industry size/opportunity might OPVC take from DI pipes?
Answer, Umang Kejriwal, Managing Director. Multiple pipe types exist (ductile, steel, plastics); while DI supply is constrained, we will not take share from other pipes — once DI supply is met we can start taking share again.
Follow-up. Any volume/CAPEX guidance for the Odisha plant?
Answer. Not worked out in detail; will share once firmed up rather than change numbers later.
Not answered directly.
10. FY25 volume guidance reconciliation
Dey, Niveshaay Investment Advisory
Question. FY25 capacity add ~9 lakh tonnes — but the PPT says volumes of ~8.95 lakh. Which is correct?
Answer, Gaurav Somani, General Manager Finance. 8.95 lakh tonnes is the total capacity which will be operational only by end of calendar year; benefit is for part of the year, translating to ~8.5 lakh tonnes on an annual basis for FY26.
11. Odisha Greenfield sizing
Kirtan Mehta, BOB Capital Markets
Question. On the Odisha plant, even if details aren't ready, can you share a typical Greenfield size that is economically feasible and the per-lakh-tonne CAPEX involved?
Answer, Umang Kejriwal, Managing Director. Asked to wait for next quarter; nothing Board-confirmed can be discussed today.
Not answered directly.
12. Capacity reconciliation
Saloni Hemnani, Molecule Ventures PMS
Question. Existing capacity in PPT is 7.4 lakh TPA but results mention 5.5 lakh TPA at Srikalahasthi, which seems to add up to 8.5 lakh. What is the correct existing capacity?
Answer, Gaurav Somani, General Manager Finance. 5.5 lakh TPA at Srikalahasthi is the post-expansion figure; CAPEX is in advanced stage and the plant will be at 5.5 lakh by end of Q3 of this financial year — ahead of original schedule.
Follow-up. Update on Parbatpur coal block — any rough figure on recovery of land component or overall expenditure?
Answer. Ashutosh Agarwal / Umang Kejriwal: Next Delhi HC hearing scheduled on 25th; matter is moving forward; past projections on this have proved wrong so no quantification given; recovery will happen.
Not answered directly.
13. US export volumes, growth and realisation
Jojo Shaju, Alpha Invesco Research Services
Question. On exports, how much volume goes to the USA, what is the YoY volume growth, demand outlook and realisation from the US market?
Answer, Gaurav Somani, General Manager Finance. US contributes ~10% of ECL's exports. Ashutosh Agarwal: Not expecting a great increase in US market given present situation. Uddhav Kejriwal: Won't quantify US-specific realisation due to competitive sensitivity; FY24 average realisation was Rs 74,000–75,000 per tonne.
Follow-up. Why Odisha as the location for the new plant — any specific advantage? And is the Odisha capacity targeted at exports or domestic?
Answer. Umang Kejriwal: Port is 167 km away, major raw materials within a few hundred km; Odisha's development track record gave confidence. Both domestic and export markets will be accessible.
Not answered directly.
14. Coking coal procurement and inventory
Jojo Shaju, Alpha Invesco Research Services
Question. Coking coal purchase strategy — what % hedged, inventory levels kept, and buying strategy?
Answer, Uddhav Kejriwal, Whole Time Director. Coal is largely imported from Australia; ideal inventory is 3–4 months. Buying strategy looks at plant needs, shipping schedules and timing windows to capture price fluctuations; calls have largely gone right for the company.
15. EBITDA per tonne and QoQ margin walk
Pramod Jain, Interglobe Finance
Question. EBITDA per tonne this quarter and EBITDA margin estimate for next year? Why is EBITDA down QoQ apart from Rs 60 cr OPEX?
Answer, Uddhav Kejriwal, Whole Time Director. EBITDA per tonne is Rs 15,000–16,000 and expected to be maintained. QoQ decline driven by Khardah shutdown expenditure (~Rs 60–62 cr in Q4) and 8–10% YoY increase in coal and iron ore costs booked through Q4 production. Ashutosh Agarwal added that Khardah plant was shut for 15 days in Q4.
16. Odisha land cost, tax reversal, JJM outlay
Miraj Shah, Arihant Capital
Question. On the 500-acre Odisha land — how much will be spent given internal accruals funding? What is the one-time tax item of Rs 36.5 cr on consolidated? And how much has been spent under Jal Jeevan Mission so far and how much more in the budget?
Answer, Ashutosh Agarwal, Whole Time Director & CFO. Land deal negotiations in final stages, expected to conclude in 15 days; rough estimate not advisable due to vendor restrictions. Rs 36.5 cr item is reversal of an earlier-year tax provision per a High Court order. Umang Kejriwal: ~Rs 3.1 lakh cr of the Rs 3.6 lakh cr Jal Jeevan Mission has been spent and more than Rs 50,000 cr is expected in the current budget.
Partly answered.
17. Long-term debt-free commitment
Subash, Value Investments
Question. In the Q2 call you mentioned long-term debt-free by FY25 end — is that intact given Srikalahasthi expansion and Odisha land acquisition?
Answer, Ashutosh Agarwal, Whole Time Director & CFO. Company will not increase debt for the current Srikalahasthi expansion or Odisha land acquisition. Will be long-term debt-free in FY25; any borrowing for Odisha project will be decided later.
Follow-up. Order book visibility — earlier said 6 months, now 10 months. Correct figure and value?
Answer. Ashutosh Agarwal: 9-10 months visibility; Rs 4,500–5,000 cr value. Srikalahasthi has 350 acres of land with further scope for expansion.
18. Capacity position, fuel surcharge provision, fixed asset loss
Saket Kapoor, Kapoor Company
Question. Capacity at Khardah + Srikalahasthi as on 31 Mar 2024 and is FY25 guidance of 8.5 lakh post Khardah shutdown? Why did other expenses rise QoQ by ~Rs 30 cr after netting Rs 60 cr shutdown cost?
Answer, Ashutosh Agarwal, Whole Time Director & CFO. Combined capacity at 31 Mar 2024 was ~7.75 lakh tonnes; FY25 guidance of 8.5 lakh tonnes includes ~75,000 tonne debottlenecking from Khardah renovation. QoQ other expense increase explained by Rs 14 cr fuel surcharge provision at Srikalahasthi (and partly at Khardah) made for accurate shareholder reporting; expected to reverse or be paid based on government/court outcome. Loss on fixed assets of Rs 26 cr in cash flow relates to pipe moulds discarded annually during production.
Follow-up. Can the QIP option be kept open for Odisha CAPEX funding given strong equity market and growth visibility?
Answer. Umang Kejriwal: We will first decide on funding approach; all options including shareholder route remain open.
19. Debt repayment schedule and railway arbitration liability
Radha, B&K Securities
Question. Quantify the debt repayment schedule for next two years and what will the remaining profits be used for? Also clarify the Rs 250 cr 'other financial liabilities' item on consolidated balance sheet.
Answer, Ashutosh Agarwal, Whole Time Director & CFO. Rs 330 cr of debt repayment scheduled over the next two years. Balance of cash flow will go towards CAPEX already shared. The Rs 250 cr item relates to a railway arbitration case won by ECL at High Court single-bench level; ECL deposited Rs 252 cr with bank against bank guarantee submitted to Calcutta HC; matter now before divisional bench.
20. Overseas/export market posture
Shailesh, Unknown
Question. You have strong accreditations in MENA and Africa but don't sound very positive on exports. What is restricting more catering to overseas demand when profitability is better there?
Answer, Umang Kejriwal, Managing Director. Clarified that he is bullish on exports; only meant that the mix between export and domestic is decided period-to-period.
21. Khardah shutdown cost and post-renovation efficiency
Dipesh Sancheti, Mayankar Finance
Question. On the Khardah shutdown — was the Rs 60–62 cr cost split quarter-wise or fully in Q4? What capacity gain should we expect and what was Q4 utilisation at the plant?
Answer, Ashutosh Agarwal, Whole Time Director & CFO. Rs 13 cr booked in Q3 (bills received in Q3); balance booked in Q4 (bills received in Q4). Renovation will improve plant efficiency, productivity and ultimately capacity. Q4 capacity utilisation at Khardah was 93% given the 15-day shutdown.
What was said
Topic by topic, in the order it was spoken
MD Opening Remarks — Sector Optimism · Umang Kejriwal (MD)
- MD framed the business as 'right place, right time' after years of waiting for the water-pipe demand cycle to turn
- Said management is 'so optimistic as we are now about the future' on the back of visible water-sector demand
- Handed over to CFO Ashutosh Agarwal for detailed results commentary
Q4 FY24 Consolidated Results · Ashutosh Agarwal (CFO)
- Consolidated total income up 6.8% YoY to Rs 2,039 cr
- Consolidated EBITDA up ~51% YoY to Rs 346 cr; margin expanded 495 bps YoY to 17%
- Consolidated PAT up 154% to Rs 227 cr; margin expanded 645 bps YoY to 11.1%
- Q4 includes Rs ~60 cr of renovation/repair at Khardah plant and 53-day shutdown impact
Q4 FY24 Standalone Results · Ashutosh Agarwal (CFO)
- Standalone DI pipe sales of 1,96,000 tonnes in Q4
- Standalone total income Rs 1,812 cr; EBITDA up 36.7% YoY to Rs 319 cr
- Standalone EBITDA margin expanded 453 bps YoY to 17.6%; PAT up 116% to Rs 219 cr (margin 12.1%)
- Q4 absorbed ~Rs 60 cr Khardah renovation cost; benefit to accrue in subsequent years via productivity/efficiency gains
FY24 Full-Year Performance · Ashutosh Agarwal (CFO)
- Consolidated FY24 total income Rs 7,580 cr; EBITDA Rs 1,281 cr (up 56%); margin 17%; PAT Rs 740 cr (up 134%); margin 9.8%; EPS Rs 12.30
- Standalone FY24 DI pipe sales 7.47 lakh tonnes; total income Rs 7,044 cr; EBITDA Rs 1,246 cr (up 52.1%); margin 17.7%; PAT Rs 736 cr (up 120%); margin 10.4%
CAPEX Update and Capacity Roadmap · Ashutosh Agarwal (CFO)
- Rs 390 cr spent of Rs 650 cr CAPEX plan as on 31 Mar 2024; new capacity on track for Sept–Oct 2025 commissioning
- Total company capacity to reach ~9 lakh TPA post-expansion, retaining domestic DI pipe leadership
- Srikalahasthi capacity to rise by 1 lakh tonnes at Rs ~64 cr CAPEX; 15-month timeline
- 500-acre land in Odisha being acquired with government support for new DI pipe & fittings unit
Debt and Balance Sheet · Ashutosh Agarwal (CFO)
- Standalone gross debt down to Rs 2,010 cr; net debt Rs 1,523 cr; net debt-to-equity 0.31x as on 31 Mar 2024
- Consolidated gross debt reduced from Rs 2,266 cr to Rs 1,722 cr; net debt-to-equity 0.34x
- Net debt reduction to continue; banker commitments will be met before Odisha land acquisition
In their words
today we can confidently say yes, we are at the right time at the right place. And yes things look all right for the future.
we expect to close FY 24-25 with an output of 8,50,000 tonnes ... and yes, we are confident of maintaining EBITDA in the range of 17% to 18%.
I don't know what I said to make you feel that we are not bullish in the overseas market. ... let me correct myself, we are bullish.
To check next time
What management committed to on this call, or the dates they gave.
- Progress against 8.5 lakh tonne volume target for FY25 (commitment reiterated on this call).
- Srikalahasthi capacity reaching 5.5 lakh TPA by Q3 FY25 (Ashutosh said they are ahead of schedule).
- Whether Khardah plant efficiency gains flow through to margins and capacity post the Rs. 60 cr renovation.
- Status of Odisha 500-acre land deal expected to close within 15 days of the call and any further project details.
- Outcome of Parbatpur coal block Delhi High Court hearing scheduled for the 25th.
- Whether fuel surcharge provisions of Rs. 14 cr (Srikalahasthi) reverse or are paid out in FY25.
Transcript
No transcript is filed yet. Companies usually file one within a week of the call.
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 13 May 2024 | ₹165.90 | −2.98% | +0.22% |
| 5 sessions Fri 17 May 2024 | ₹174.05 | +1.78% | +1.86% |
| 20 sessions Fri 7 Jun 2024 | ₹164.25 | −3.95% | +5.60% |
From the close of Fri 10 May 2024, ₹171.00: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
Electrosteel Castings's other calls
- Q2 FY27Fri 13 Nov 2026Tone: Mixed
- Q1 FY27Fri 7 Aug 2026Tone: Cautious
- Q4 FY26Mon 18 May 2026Tone: Cautious
- Q3 FY26Tue 10 Feb 2026Not read
- Q3 FY26Fri 6 Feb 2026Not read
- Q2 FY26Mon 10 Nov 2025Tone: Mixed
- Q1 FY26Wed 6 Aug 2025Not read
- Q4 FY25Mon 12 May 2025Tone: Mixed
- Q2 FY25Wed 30 Oct 2024Tone: Mixed
- Q1 FY25Thu 1 Aug 2024Tone: Confident