Godawari Pow & Isp Q2 FY27 earnings call

Mon 16 Nov 202612:00 ISTGPIL

In brief

FY27 mining and pellet output guidance was cut; management expects captive-ore-led margin recovery from Q4 FY27.

Management's tone
Mixed
What was said
Mixed
Guidance
Guidance cut
Analyst pushback
High
Stock, next session
+1.50% (Nifty 50 +0.58%)
  • FY27 iron ore mining guidance was cut to 2.5 million ton from 3.4 million ton, and pellet guidance to 3.5 million from 4.4 million ton.
  • Q2 FY27 revenue rose 25% Y-o-Y to INR1,632 crores, while H1 FY27 revenue rose 29% to INR3,382 crores.
  • Q2 EBITDA and PAT margins were 12% and 5.2%, versus H1 FY27 margins of 15.7% and 9.1%.
  • Margins were expected to recover from Q4 FY27, with regulatory permission for additional overburden-dumping land awaited shortly.
  • Management kept the 20 gigawatt BESS line on track for June-July 2027, with the first container due by early Q2 FY28.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY27

This quarterA year agoLast quarterMargin
Revenue₹1,632 cr+24.8%−6.8%
EBITDA (excl. other income)₹174 cr−33.2%−48.0%10.6% (19.9% a year ago)
Net profit₹84.7 cr−47.6%−61.8%5.2% (12.4% a year ago)
EPS (₹)₹1.38−47.5%−61.6%

From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Q2 FY27 EBITDA margin: said 12%; filed 10.6% EBITDA margin excluding other income. Management's 12% included other income; the filed metric excludes ₹23.28 cr of other income.

What moved the numbers, as management explained it

  • Higher market iron-ore fines cost roughly INR3,000-INR3,500 extra per ton versus captive sourcing, while zero high-grade merchant sales removed about INR1,000 on prior volumes.
  • Coal costs in DRI rose about INR1,000-INR1,500 and power costs by INR0.50-INR0.75 because of the war; management also cited higher finished-product prices.
  • The temporary closure of the 2 million ton pellet plant for uneconomical operations reduced Q2 pellet output sequentially.
  • High-grade merchant pellet sales were zero for months, removing an INR1,000-plus premium while captive ore was used in steelmaking instead.
  • Ferroalloy output was hit by lower captive power generation from adverse weather, while galvanized fabricated products were disrupted by seasonal heavy rains.
  • Steel melting capacity rose from 5.25 lakh to 5.75 lakh metric ton, enabling almost 100% captive sponge-iron use and higher value addition.

The numbers management led with

  • FY27 iron ore mining guidance: 2.5 million tonnes for FY27, revised down from 3.4 million tonnes
  • FY27 pellet production guidance: 3.5 million tonnes for FY27, revised down from 4.4 million tonnes
  • CRM and container-line capex: About INR500 crore for the CRM project plus INR100 crore for a container line; 31.45 acres allotted at AURIC Bidkin
  • BESS credit facilities: INR2,795 crore sanctioned: INR700 crore term loan, INR100 crore working-capital limit and nearly INR2,000 crore non-fund-based limit

Guidance

Guidance on this call

WhatForWhat management said
Iron ore mining production guidanceFY27FY27 iron ore mining production guidance was revised to 2.5 million ton from 3.4 million ton.
Iron ore pellet production guidance (Iron ore pellets)FY27FY27 iron ore pellet production guidance was revised to 3.5 million ton from 4.4 million ton.
EBITDA and PAT margin recoveryQ4 FY27EBITDA and PAT margins were expected to recover from Q4 FY27.
Vision 2030 target of 4x revenue growthFY26-FY30Vision 2030 target of 4x revenue growth.
Vision 2030 target of 3x EBITDA growthFY26-FY30Vision 2030 target of 3x EBITDA growth.
Vision 2030 target of 3x PAT growthFY26-FY30Vision 2030 target of 3x PAT growth.
Beneficiation plant commissioning (Iron ore mining)Q3 FY27The beneficiation plant was targeted for commissioning in Q3 FY27.
20 gigawatt BESS project commissioningFY28The 20 gigawatt BESS line was expected to commission by June-July 2027, with the first container by early Q2 FY28.
3 gigawatt BESS project commissioningFY28Q&A targeted the 3 gigawatt line for December 2027, while prepared remarks said March 2028.
0.7 million ton CRM complex commissioning (Cold-rolled steel)FY28CRM commissioning was envisaged for December 2027 but might stretch to March 2028.
Container line commissioning (Container manufacturing)FY27The container line was expected to commission by March 2027.
100 megawatt solar project commissioning (Captive power and solar)Q3 FY27The 100 megawatt solar project was expected to commission by December 2026.
BESS margin—Long-term BESS margin was expected to be 5%-7%.
Capex for the 3 gigawatt BESS project—Approved capex for the 3 gigawatt BESS project was INR135 crores.
Capex for container manufacturing line—Approved capex for the container manufacturing line was INR100 crores from internal accrual.

What changed since the Mon 10 Aug 2026 call

WhatOn the Mon 10 Aug 2026 callOn this call
FY27 iron ore mining production (cut)FY27 iron ore mining guidance maintained at 3.4mt, with full ramp from Q4 FY27/Q1 FY28.FY27 guidance was revised to 2.5 million ton; Q4 FY27 improvement is now expected to be slight.
FY27 pellet production (cut)FY27 pellet guidance was likely cut from 4.0mt after the 2mt plant shutdown.FY27 pellet guidance was revised to 3.5 million ton from 4.4 million ton.
CRM complex capex (cut)Capex for the shifted 0.7mt CRM complex was raised to INR1,100cr.CFO described the base CRM project at around INR500 crores; a separate container line adds INR100 crores.
CRM complex commissioning (delayed)CRM complex commissioning was targeted for Dec-2027.December '27 is envisaged, but management said commissioning might stretch to March '28.
Integrated steel plant (held)The 1mt integrated steel plant was put on hold indefinitely pending water allocation.The steel plant remains on hold, pending approvals especially on water, with no current plans.
BESS funding (new)No incremental debt was required for the current capex pipeline.Financial closure was completed with INR2,795 crores of sanctioned facilities, including INR700 crores of BESS term debt.
DR-grade pellet exports (not repeated)Pursue DR-grade pellet exports once 100% captive ore sourcing is achieved in FY28.Not mentioned
Captive power expansion baseline (restated)Expand captive solar from 165MW to 290MW; operationalise 45MW storage by Q3 FY27.Expand captive power from 190 megawatt to 290 megawatt; 45 megawatt BESS is expected by December 2026.

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY26 EBITDA marginFY26at least 20% (on the Q4 FY25 call)22.9%, within the range
FY26 revenue growthFY265–7% (on the Q4 FY25 call)0.1%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Iron ore mining

H1 mining fell Y-o-Y because overburden-dumping space constrained output. FY27 guidance was cut to 2.5 million ton; Q4 FY27 should bring slight improvement before a fuller ramp. It also approved INR100 crores for 50 EV dumpers.

FY27 guidance 2.5 million ton · Prior FY27 guidance 3.4 million ton · Q1 FY28 ramp 70%-80% of capacity · EV dumper capex INR100 crores · EV dumper deployment 50 numbers · Boria Tibu current capacity 0.7 million ton · Boria Tibu FY31 capacity target 4 million ton

Outlook: Q3 FY27 approvals should enable slight Q4 FY27 growth and close to 70%-80% of mining capacity from Q1 FY28. Boria Tibu is targeted at full 0.7 million ton from FY28 and 4 million ton by FY31.

Galvanized fabricated products

H1 production declined Y-o-Y because heavy rains caused seasonal disruption.

Iron ore pellets

Q2 output fell sequentially after the temporary closure of the 2 million ton pellet plant for uneconomical operations. Merchant high-grade pellet sales were zero, while captive production supported steelmaking.

2 million ton pellet plant closure · FY27 guidance 3.5 million ton · Prior FY27 guidance 4.4 million ton · Earlier high-grade merchant sales 50,000 tons to 1 lakh tons · High-grade selling-price premium INR1,000-plus · Current pellet price INR10,500

Outlook: Merchant high-grade sales should resume from Q4 FY27 with an INR1,000-plus premium; pellet volumes are expected to rise substantially from Q1 FY28.

Ferroalloys

Q2 production was affected by lower captive power generation caused by adverse weather, but ferroalloys had achieved over 50% of the FY27 annual target.

Over 50% of FY27 annual target achieved

Outlook: Production across other key segments remained on track for FY27.

Steel, sponge iron and billets

The DRI-to-billet-to-wire-rod chain ran at desired capacity apart from energy costs; sponge iron and rolled products supported value-added sales. Steel melting capacity is now 5.75 lakh metric ton.

Steel melting capacity from 5.25 lakh metric ton · Expanded steel melting capacity 5.75 lakh metric ton · Almost 100% captive sponge iron use · DRI production about 1.5 lakh tons · Over 50% of FY27 annual target achieved

Outlook: International iron ore was expected to average around $90 per ton near term, with downside risk. Domestic crude steel output rose 2.9% Y-o-Y and finished steel consumption 7.6% in H1 FY27.

CRM and container manufacturing

The 0.7 million ton CRM complex was shifted to Maharashtra; 31.45 acres at AURIC Bidkin were allotted and the lease executed. A separate INR100 crores container line was approved alongside the complex.

CRM complex capacity 0.7 million ton · AURIC Bidkin land allotment 31.45 acres · Container line capex INR100 crores

Outlook: Construction awaits EC; CRM commissioning is envisaged for December 2027 but may stretch to March 2028. The container line is targeted for March 2027.

Battery energy storage systems

The 20 gigawatt line had secured technology, supply and long-term sale arrangements, with machinery supply started. A 3 gigawatt small-storage line was approved for 261 kilowatt-hour and 418 kilowatt-hour containers.

20 gigawatt BESS line · 3 gigawatt BESS line · 261 kilowatt-hour container · 418 kilowatt-hour container · INR135 crores capex · BESS margin 5%-7% · First-year output 5 gigawatt · Expected own consumption at least 40%-50%

Outlook: The first container from the 20 gigawatt line is due by June-July 2027; the 3 gigawatt line is expected in December 2027, versus March 2028 in prepared remarks. Management also expects 5%-7% margins.

Captive power and solar

Captive power capacity is being expanded from 190 megawatt to 290 megawatt. A 25 megawatt solar plant was commissioned in May '26; 100 megawatt solar and 45 megawatt BESS projects remain under implementation.

Captive power capacity 190 megawatt · Captive power capacity target 290 megawatt · 25 megawatt solar plant · May '26 solar commissioning · 100 megawatt solar project · 45 megawatt BESS project · INR26 crores SolarCraft investment · 26% SolarCraft stake · 50 megawatt SolarCraft project

Outlook: The 100 megawatt solar project and 45 megawatt BESS were expected to commission by December 2026, after a two-month delay for solar.

Balance sheet, capex and funding

  • Financial closure: INR2,795 crores sanctioned, including INR700 crores BESS term debt, INR100 crores working-capital limit and almost INR2,000 crores non-fund-based limits.
  • Management said funded facilities were only about INR800 crores; the balance was mainly supply-chain financing backed by guarantees.
  • Around INR900 crores of free cash flow was reported as of the call, and management did not foresee cash crunches.
  • CFO described the base CRM capex as around INR500 crores and later as INR550 crores.
  • Approved commitments included INR100 crores for a container line, INR135 crores for 3 gigawatt BESS, INR100 crores for 50 EV dumpers and INR26 crores for SolarCraft.
  • INR120 crores of inter-corporate loans were outstanding at 12%-15% interest and were expected to be returned within 9-12 months; no new corporate loans were planned.

The industry, as management sees it

Benchmark iron ore was around $90-$92 per tonne and was expected to average near $90 in the near term, with downside from weak Chinese demand and incremental low-cost supply. Indian crude-steel output rose 2.9% and finished-steel consumption increased 7.6% in H1 FY27, while announced BESS capacity looked large but typically required 18-24 months to execute.

Risks management named

  • Tree-cutting and overburden-dumping approvals remain pending after repeated delays
  • High purchased iron ore, coal and power costs pressure near-term margins
  • Q3 FY27 margins are expected to remain close to Q2 levels
  • CRM construction awaits environmental clearance and may slip to March 2028
  • BESS overcapacity, unproven utilization and lack of tender wins create execution risk
  • Steel plant remains on hold pending water-related approvals

Q&A

Analysts concentrated on approval timing, margin normalization, capex funding and the commercial execution of BESS. Approval confidence and the BESS margin discrepancy drew the sharpest pushback, with management reaffirming most timelines while correcting its margin range. No formal order wins or contracted BESS offtake were disclosed, leaving execution and utilization as the main open questions.

Not answered directly

  • Contingency plan for delayed mine approvals
  • Return hurdles and debt limits for new capex
  • Final BESS ownership and offtake model
  • Net cash trajectory through FY28-FY29

Asked for a number, answered without one

  • Pellet realization decline: Management said iron ore was the major impact and gave cost and price points, but did not quantify the percentage split.
  • EBITDA loss attribution: Management gave per-ton cost movements and rough coal and power amounts, but called the total impact substantial without an exact EBITDA split.
  • BESS project IRR: Management gave turnover of about INR13,000 crores, annual EBITDA of about INR600 crores at 15GW and 3-3.5-year payback, but did not state an IRR.
  • Net cash and debt outlook: Management broke the INR2,795 crores into funded and non-funded limits but gave no FY28 or FY29 net-cash projection.
  • Debt and return hurdles: Management cited free cash flow and tied-up project funding but set out no quantitative debt limit or return hurdle.
  • Q3 FY27 margin level: Management said Q3 would be similar to Q2, with marginal improvement in Q4 and a return to normal from Q1.

Every question, with its answer

  1. 1. Margins, approvals and capex funding

    Sucrit D. Patil, Eyesight Fintrade Private Limited

    Question. Q2 operating margins fell from 20% to 11%-12% due to purchased iron ore while mine approvals were pending and higher coal costs. How will management manage further regulatory delays and back up plans for CRM and BESS projects, and what return hurdles or debt limits will constrain heavy capex if steel prices stay weak?

    Answer, Abhishek Agrawal and Sanjay Bothra, Executive Director and Chief Financial Officer. Abhishek Agrawal attributed the margin decline to higher purchased iron ore and energy costs, said tree-cutting approval was expected that week and all clearances by Q3, enabling mining to ramp from Q4, and said projects were funded through adequate free cash flow and long-term bank loans. Sanjay Bothra said pellet prices had improved, CRM capex was around INR500 crore, BESS funding was tied up, and about INR900 crore of free cash was available, so no cash crunch was foreseen. Management did not quantify return hurdles or debt limits.

    Not answered directly.

  2. 2. Pellet realization, unit EBITDA and project timelines

    Tanuj Nangalia, SKP Securities Limited

    Question. How much of the pellet-realization decline came from the lost INR1,000-INR1,500 high-grade captive-ore premium versus general market pricing? What EBITDA per tonne is being earned across pellets, sponge iron and billets, and are the BESS and CRM timelines intact?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal said merchant sales of high-grade pellets had been zero for several months because mine output was used captively, creating about a INR1,000-per-tonne impact; these sales were expected to resume from Q4. Pellet prices moved from INR8,500 to INR11,000-INR11,500 before easing to INR10,500. Excluding pellets, he estimated roughly INR6-INR7 per kg across the sponge-iron-to-steel chain, while pellet EBITDA was currently about INR500-INR700 per tonne. He said the first BESS container should emerge by June-July 2027 and CRM commissioning was envisaged for December 2027, possibly stretching to March 2028.

  3. 3. BESS equipment, offtake and utilization

    Sahil Sanghvi, Monarch Networth Capital Limited

    Question. What equipment will support the commercial and industrial BESS line, when will Lead Intelligent Wuxi equipment affect offtake, will GPIL bid for 5 MW projects, and what first-year utilization should investors expect?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal said the existing line makes 5 MW-and-above grid containers, while the new 3 GW line covers 261 kWh and 418 kWh units. Machinery for the 20 GW line had begun shipping; the 3 GW line would receive equipment in July-August 2027, with commissioning indicated for December 2027 versus March 2028 in prepared remarks. GPIL formed Godawari Energy Solutions to bid as an EPC contractor; bids had started but no tenders had been won. He expected first-year utilization of 10%-20%, potentially 20%-25% by March 2028, and 5 GW of output.

    Partly answered.

  4. 4. Steel profitability, approvals and BESS business model

    Sunil Jain, Nirmal Bang Securities Private Limited

    Question. Was the non-pellet steel business also under pressure? Given the repeated delay in dumping-land permission, why is management confident of approval this time, what asset model will support captive BESS consumption, and is announced industry overcapacity a concern?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal said the other units were operating at desired capacity and the DRI, billet and wire-rod businesses were performing well apart from energy costs. He reiterated approvals by end-Q3, said permission was at the last stage despite having no official document to share with shareholders, and expected three-to-four weeks of land clearing. GPIL was not initially planning to create an owned asset base and would consider direct tenders or back-to-back supply partnerships. He acknowledged announced BESS capacity looked alarming but argued execution takes 18-24 months, giving GPIL first-mover advantage for a couple of years.

    Not answered directly.

  5. 5. BESS margin and steel plant status

    Varun Mehta, Wealth Link Investments

    Question. The annual report indicated a 12%-13% BESS margin while an earlier call indicated 7%-8%. What margin should investors use, and is the proposed steel plant still moving forward?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal said BESS margins should be only 5%-7%, with high-volume turnover, and described that as the plan from the beginning. He said he would speak to his team and correct the annual-report figure. The steel plant remains on hold because desired approvals, particularly on the water side, had not been received, and management currently had no plans to restart the project.

  6. 6. Mine safety, funding mix and mining ramp-up

    Yash Kabra, Nirmal Bang Securities

    Question. Was there any accident at the iron ore mines? With INR2,795 crore of new facilities and previously net-cash status, how will net cash evolve in FY28 and FY29, and can mining ramp in Q3 despite the reduced guidance?

    Answer, Dinesh Gandhi and Abhishek Agrawal, Executive Director. Abhishek Agrawal confirmed that no accident had occurred at any mine. Dinesh Gandhi explained that INR2,795 crore of facilities comprised almost INR1,995 crore of non-funded limits and only INR800 crore of funded debt, comprising INR700 crore for BESS and INR100 crore for working capital; a further INR550 crore related to the base CRM project. He did not provide a net-cash forecast. Abhishek said four weeks would be needed to clear the land, Q4 should show slight improvement, and Q1 FY28 should reach about 70%-80% of mining capacity.

    Not answered directly.

  7. 7. Mining output and overburden constraint

    Tanuj Nangalia, SKP Securities Limited

    Question. Was the overburden-dumping constraint only relevant to the expanded mine capacity, or did it also constrain current production, given the YoY decline in mining output?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal clarified that the space constraint applied to overburden dumping for both current and expanded capacity, not only the new mine. Additional dumping land would automatically allow mining production to improve once dumping began at the higher capacity.

  8. 8. Maharashtra CRM incentives and BESS execution

    Saksham Tyagi, Desvelado Advisory

    Question. What incentives and operating benefits does GPIL expect from moving the CRM project to Maharashtra, and what is the current execution status of the 20 GW BESS project?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal said the Maharashtra project qualified for the Mega status policy above INR1,000 crore, with tariff and interest-subvention benefits and a 9% GST refund on sales within Maharashtra. AURIC Bidkin offered a plug-and-play industrial ecosystem with water, electricity and other infrastructure available at the doorstep. On BESS, the first machinery lot had been dispatched from China after testing, and the first container was expected by June-July 2027.

  9. 9. Margin bridge and BESS project economics

    Shikhar Mundra, Vivog Commercial Limited

    Question. Can management quantify the EBITDA impact from energy costs and the dumping constraint, what margin trajectory is expected in Q3 and Q1 FY28, and what revenue, EBITDA and IRR are expected from the INR1,400 crore BESS project?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal estimated extra market ore cost at about INR3,000-INR3,500 per tonne on a yearly-average basis, with roughly INR1,000 of lost high-grade pellet premium, INR1,000-INR1,500 higher DRI coal cost and INR0.50-INR0.75 higher power cost. He quantified roughly INR15 crore from coal and INR25-30 crore from power on a quarterly basis, while noting finished-product prices also increased. Q3 should be similar to Q2, Q4 should improve marginally and Q1 should return to normal. At 80% utilization, 15 GW could generate about INR13,000 crore of turnover and INR600 crore of annual EBITDA, with a maximum payback of three to three and a half years.

    Partly answered.

  10. 10. BESS cell economics, DCR and inter-corporate loans

    Nitin Shah, Individual investor

    Question. What incremental EBITDA is expected from the new high-capacity cell technology, how does GPIL meet domestic-content requirements for BESS tenders, and how much has been lent under the inter-corporate loans policy and when will it be recovered?

    Answer, Abhishek Agrawal and Sanjay Bothra, Executive Director and Chief Financial Officer. Abhishek Agrawal corrected the cell format to 628 Ah and said the Chinese-supplied cells should reduce operating cost by 4%-5%, adding about 1.5% to EBITDA. He said BESS tenders require 20% DCR content by value and GPIL qualified. Sanjay Bothra said approximately INR120 crore had been lent to inter-corporate entities at 12%-15% interest; these loans were expected to be returned within nine to 12 months. Abhishek added that GPIL would stop making new corporate loans because of its large capex program.

  11. 11. Iron ore imports and pellet price outlook

    Sunil Jain, Nirmal Bang Securities Private Limited

    Question. How will rising international iron ore production affect domestic pellet prices, what is the landed-cost advantage, what price is reasonable over the next six to eight months, and what pellet EBITDA is possible once mining runs fully?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal said imports would not directly determine Indian pellet prices because domestic ore and regional demand were the primary drivers, although some regions faced pellet overcapacity. Imported pellets were less attractive because of inland logistics and ship cash requirements, while operators such as Lloyds were adding captive-mine pellet capacity. He expected a sustainable INR9,500-INR10,500 range ex-Raipur over the next six to eight months. At full mining and a INR10,000 selling price, pellet EBITDA should exceed INR4,000, with production cost no higher than INR5,500-INR6,000.

  12. 12. Iron ore reserves and expansion potential

    Anant Mundra, Mytemple Capital

    Question. Can the Ari Dongri and Boria Tibu reserves be expanded, how long can they support production, and what is the planned Boria Tibu mining and beneficiation capacity?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal said about 80% of exploration at Ari Dongri was complete and reserves might rise from 80 million tonnes to 90-95 million tonnes, but 80 million tonnes was the base case supporting roughly 15 years of operation. Boria Tibu held about 75-80 million tonnes of low-grade ore, with only 25-30 million tonnes considered usable at 35%-40% recovery. Current capacity of 0.7 million tonnes was expected to run fully from the next financial year, with plans to reach 4 million tonnes by FY31; a 4 million tonne beneficiation plant could produce about 1.5 million tonnes at 40% recovery.

  13. 13. Captive iron ore sourcing and external procurement

    Sahil Sanghvi, Monarch Networth Capital Limited

    Question. How much iron ore will be outsourced in H2 FY27 and FY27 overall, and when will GPIL become fully captive across FY28 and FY29?

    Answer, Abhishek Agrawal, Executive Director. Abhishek Agrawal said external purchases would be about 0.7-0.8 million tonnes, already occurring in Q3 and partly in Q4, for roughly 2 million tonnes of total FY27 sourcing. In FY28, GPIL expected internal production of 5-5.2 million tonnes, or 80%-85% of capacity, with no more than about 0.5 million tonnes purchased externally. FY29 was expected to be 100% captive, with mining reaching 6 million tonnes from October 2027 after the monsoon.

What was said

Topic by topic, in the order it was spoken

Refreshed Corporate Identity · Dinesh Gandhi (Executive Director)

  • Unveiled a refreshed corporate identity around 'ONE Godawari' and the tagline 'Powering New Horizons'.
  • Management said the unified brand would strengthen recognition, integrate the group's diverse portfolio and support its next growth phase.

Q2 and H1 Financial Performance · Dinesh Gandhi (Executive Director)

  • Q2 revenue increased 25% YoY to INR1,632 crore, while H1 revenue rose 29% YoY to INR3,382 crore.
  • EBITDA and PAT margins were 12% and 5.2% in Q2, versus 15.7% and 9.1% in H1, amid higher ore and coal costs.
  • Q2 profitability declined sequentially on lower pellet realization; management expected recovery from Q4 FY27.

Operations and FY27 Guidance Revision · Dinesh Gandhi (Executive Director)

  • H1 production grew YoY across most categories, except iron ore mining and galvanized fabricated products.
  • Pellet output fell sequentially after the temporary closure of a 2 million tonne plant for uneconomic operations; ferroalloys were affected by lower captive power and weather.
  • FY27 iron ore mining guidance was reduced to 2.5 million tonnes from 3.4 million tonnes.
  • FY27 pellet production guidance was reduced to 3.5 million tonnes from 4.4 million tonnes; ferroalloy and sponge iron had achieved over 50% of annual targets.

Mine Expansion and Beneficiation · Dinesh Gandhi (Executive Director)

  • The Godawari iron ore expansion was described as progressing according to plan.
  • The beneficiation plant was targeted for commissioning in Q3 FY27, with a ramp from Q4 and full-scale operations by FY28.
  • Additional overburden-dumping land was expected to receive regulatory clearance shortly, enabling higher captive mining.
  • H1 value-added product growth was led by pellets, sponge iron and rolled products.

CRM Relocation and Container Line · Dinesh Gandhi (Executive Director)

  • The 0.7 million tonne CRM complex was shifted to Maharashtra to capture state incentives, subsidies and customer and base-plant proximity.
  • GPIL received a 31.45-acre allotment at AURIC Bidkin Industrial Area and executed the lease deed; construction awaited building-construction EC.
  • The board approved INR100 crore of internal accruals for a container line adjacent to the CRM complex, targeting March 2027 commissioning.

BESS Scale-Up and Financing · Dinesh Gandhi (Executive Director)

  • The 20 GW BESS project received fresh environmental clearance for construction; key technology and supply partnerships, including a long-term sale arrangement, were finalized.
  • Prepared remarks cited a Q1 FY27 commissioning target, while Q&A later indicated June-July 2027.
  • Financial closure covered INR2,795 crore of limits: INR700 crore of BESS term debt, INR100 crore of working-capital funding and nearly INR2,000 crore of non-fund-based limits.
  • A separate 3 GW line for 261 kWh and 418 kWh commercial and industrial systems was approved with INR135 crore of capex, with prepared remarks targeting March 2028.

Solar and Captive Power Expansion · Dinesh Gandhi (Executive Director)

  • GPIL planned to expand captive power capacity from 190 MW to 290 MW for mining and the additional 2 million tonne pellet plant.
  • A 25 MW solar plant was synchronized in May 2026 and supplied the Ari Dongri mines.
  • The 100 MW solar project was delayed by a couple of months and the 45 MW captive solar BESS project was expected by December 2026.
  • GPIL approved INR26 crore for 26% of SolarCraft Power India 32 Ltd to pursue a 50 MW group-captive project, limiting balance-sheet investment.

Operational Efficiency and Decarbonization · Dinesh Gandhi (Executive Director)

  • The board approved INR100 crore to deploy 50 electric dumpers across iron ore mines and plant operations to reduce fuel costs.
  • Commercial production began at an expanded steel melting shop with capacity raised from 5.25 lakh to 5.75 lakh metric tonnes.
  • Almost 100% captive sponge iron was being used in billet manufacturing, supporting value addition and operating margins.

Iron Ore and Steel Market Outlook · Dinesh Gandhi (Executive Director)

  • Benchmark iron ore traded around $90-$92 per tonne in early November 2026; management expected an average near $90 in the near term.
  • Weak Chinese steel demand, rising global supply and the ramp-up of Simandou were identified as downside risks.
  • Domestic iron ore remained below the landed cost of imported ore, with stable demand-supply dynamics.
  • H1 crude-steel production rose 2.9% YoY and finished-steel consumption increased 7.6%, supported by infrastructure, housing and manufacturing.

Vision 2030 and Execution Roadmap · Dinesh Gandhi (Executive Director)

  • Management positioned GPIL for growth through captive ore, capacity expansion, cost optimization, a healthy balance sheet and decarbonization.
  • The Vision 2030 roadmap retained targets of 4x revenue growth and 3x EBITDA and PAT growth.

In their words

With a clear defined growth roadmap and disciplined execution, we remain focused on achieving our Vision 2030 target of 4x revenue growth and 3x EBITDA and PAT growth while creating long-term value for all our stakeholders.
Dinesh Gandhi (Executive Director, Godawari Power & Ispat Limited)
Q3 will be similar on Q2. Q3 will be similar on Q2.
Abhishek Agrawal (Executive Director, Godawari Power & Ispat Limited)
Because, of course, officially, I don't have any document which I can share with all the shareholders. But I'm very well aware the permission is at the last stage, because it's a complicated process, it's a long-drawn process.
Abhishek Agrawal (Executive Director, Godawari Power & Ispat Limited)

To check next time

What management committed to on this call, or the dates they gave.

  • Whether the Ari Dongri beneficiation plant commissions in Q3 FY27.
  • Tree-cutting permission and use of the additional dumping land from December 2.
  • Q3 FY27 margins staying near Q2, with marginal improvement expected in Q4 FY27.
  • Mining output improvement in Q4 FY27 and the Q1 FY28 ramp toward 70%-80%.
  • Commissioning of the 100 megawatt solar and 45 megawatt BESS projects by December 2026.
  • First 20 gigawatt BESS container, plus CRM and container-line construction progress toward 2027-2028 dates.

Transcript

Read along with the recording

The whole call, 190 lines from 12 speakers over 45:44. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.

Sign up freeLog in

The stock after the call

After the callCloseStockNifty 50
Next session Mon 16 Nov 2026₹223.45+1.50%+0.58%

From the close of Fri 13 Nov 2026, ₹220.14: the last close before the call, which began at 12:00 IST. Adjusted daily closes; the move includes everything else that happened in those sessions.

Godawari Pow & Isp's other calls