Godawari Pow & Isp Q2 FY26 earnings call

Mon 17 Nov 2025GPIL

In brief

Q2 pellet sales +71% YoY despite 40-day pellet plant shutdown post-incident; mining EC and 2 mt pellet expansion targeted by Dec and Nov 2025

Management's tone
Confident
What was said
Leaned positive
Guidance
Guidance held
Analyst pushback
Medium
Stock, next session
−0.22% (Nifty 50 +0.40%)
  • Q2 pellet production rose 31% YoY and pellet sales surged 71% YoY, despite a 40-day pellet plant shutdown after the 26 September incident.
  • Mining EC for Ari Dongri (2.35→6 mtpa) expected by end-December 2025; 2 mt pellet expansion to commission by end-November 2025.
  • Imported coal landed cost in Q2 was about ₹11,000/ton; Q3 expected ₹10,500–11,000/ton, with pellet H2 realisation similar to ~₹9,000/ton H1 average.
  • CRM complex (₹900 cr) and 10 GW BESS (₹700 cr) both target commercial production from April 2027; first-year PLF 50–60%, rising to 80%+ from year two.
  • Board approved an additional 250 MW solar (on top of 125 MW) for captive use, targeting Q4 FY27 commissioning with an internal IRR of about 24%.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY26

This quarterA year agoLast quarterMargin
Revenue₹1,308 cr+3.2%−1.2%
EBITDA (excl. other income)₹260 cr+5.2%−19.7%19.9% (19.5% a year ago)
Net profit₹162 cr+1.6%−25.1%12.4% (12.6% a year ago)
EPS (₹)₹2.63−79.7%−25.3%

From the company's filed results for the quarter ended 30 Sept 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • Pellet plant incident on 26 September 2025 caused ~40-day production loss (around 1.5 lakh tons), partly absorbed by preponeing a planned Q3 maintenance shutdown. (one-off)
  • Soft realisation across sponge, billets and finished steel dragged Q2 EBITDA and PAT margins YoY, even as volumes rose.
  • Pellet sales +71% YoY and mining production +29% YoY in Q2 supported revenue and mix, while value-added steel product sales declined.
  • Two-month shutdown of one power plant for pollution-norm compliance reduced power availability and cut billet production ~40% H1 over H1. (one-off)
  • Higher pellet and galvanized volumes supported H1 revenue stability, offsetting weakness in long-product realisations.

The numbers management led with

  • Q2 FY26 pellet sales growth: +71% YoY
  • Ari Dongri mining capacity expansion: From 2.35MT to 6MT per annum
  • Pellet capacity expansion: 2MT new capacity commissioning end-Nov 2025
  • CRM complex project cost: INR900 crores (INR600 cr debt + accruals); 452 acres land
  • Godawari New Energy BESS project size: 10 GW; INR700 crores (60% debt + accruals); INR175 cr equity infused
  • Solar power capacity addition: Additional 250MW (vs 125MW earlier); commissioning Q4 FY27

Guidance

Guidance on this call

WhatForWhat management said
Mining EC for Ari Dongri (Iron Ore Mining)—Final environmental approval expected by end of December 2025
2 mt pellet expansion commissioning (Pellets)—Commissioning targeted by end of November 2025, awaiting consent to operate
Iron ore production FY27 (Iron Ore Mining)FY27FY27 iron ore production targeted 4.7-5 million tons
Pellet volume FY27 (Pellets)FY27FY27 pellet volume bare minimum 4 million tons; could be on the higher side
Beneficiation expansion commissioning (Iron Ore Mining)—Expanded beneficiation expected in place by June-July 2026
Iron ore 6 mtpa ramp-up (Iron Ore Mining)—Full 6 mtpa throttle from January 2027
CRM complex commercial production (Sponge Iron & Steel (Value-Added))FY28Commercial production of CRM complex targeted from April 2027 (FY28)
BESS commercial production (BESS (Godawari New Energy))FY28Commercial production of BESS targeted from April 2027 (FY28)
Imported coal landed cost Q3Q3 FY26Q3 imported coal landed cost expected between ₹10,500-11,000/ton
Pellet realisation H2 (Pellets)H2 FY26H2 pellet realisation similar to H1 average of ~₹9,000/ton (plus/minus 8-10%)
New pellet plant Q4 utilisation (Pellets)Q4 FY2680-85% capacity utilisation for the new pellet plant from Q4 onwards
CRM/BESS Year 1 PLF—50-60% PLF in first year of CRM and BESS operations
CRM/BESS Year 2 PLF—80%+ PLF from second year for both CRM and BESS
Additional 250 MW solar commissioning (Solar (Captive))Q4 FY27Additional 250 MW solar to commission by Q4 FY27, coinciding with CRM project

What changed since the Wed 6 Aug 2025 call

WhatOn the Wed 6 Aug 2025 callOn this call
Mining EC for Ari Dongri (delayed)Public hearing post 15 Sept; final EC expected post Diwali/early November 2025; operations Q4 FY26Public hearing completed; final EC expected by end of December 2025; ramp-up from April 2026, full throttle 6 mtpa January 2027
2 mt pellet expansion commissioning (delayed)2 mt pellet expansion to commission in October 2025Pre-commissioning trials underway; commissioning targeted by end of November 2025, awaiting consent to operate
Solar captive capacity (raised)125 MW captive solar capacity announced earlierBoard approved additional 250 MW (total 375 MW); targeted Q4 FY27; internal IRR ~24%
Iron ore FY27 volume (restated)Operations from Q4 FY26 (start of expansion)FY27 guided 4.7–5 million tons; full 6 mtpa from January 2027
Steel plant board approval (restated)Contingent on mining EC; ₹4,500-5,000 cr with 20/60/20% phasing in FY27/FY28/FY29Board to take up steel plant for approval at next board meeting, shortly after mining EC clearance
Boria Tibu development (restated)0.7→3 mt expansion with in-mine beneficiation; ~3 yearsConstant mining of ~0.5 mt/yr producing ~0.3 mt concentrate; next expansion capex ~2 years away
BESS supply positioning (restated)Plan to ramp from 10 GW toward 40 GW; long-term diversification playWill supply containers, not bid in SECI tenders; cells only imported from top A-category Chinese suppliers

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY25 EBITDA marginFY2524–25% (on the Q4 FY24 call)22.2%, below the range
FY26 EBITDA marginFY26at least 20% (on the Q4 FY25 call)22.9%, within the range
FY26 revenue growthFY265–7% (on the Q4 FY25 call)0.1%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Iron Ore Mining

H1 production +18% YoY, Q2 +29% YoY. Public hearing done; final EC for Ari Dongri (2.35→6 mtpa) expected by end-December 2025. Boria Tibu resumed May 2025 at ~0.5 mt/yr.

H1 production +18% YoY · Q2 production +29% YoY · Boria Tibu ~0.5 mt/yr · Ari Dongri 2.35→6 mtpa

Outlook: FY27 iron ore volume guided 4.7–5 million tons; full 6 mtpa throttle from January 2027

Pellets

H1 sales +30%, Q2 sales +71% YoY with production +31% YoY, despite 40-day shutdown from 26 Sept incident (part of which absorbed planned Q3 maintenance).

H1 sales +30% YoY · Q2 production +31% YoY · Q2 sales +71% YoY · H1 realisation ~₹9,000/ton

Outlook: 2 mt expansion to commission by end-Nov 2025; Q4 run-rate ~0.9 mt; FY27 pellet minimum 4 million tons

Sponge Iron & Steel (Value-Added)

H1 production +16%, Q2 +5% YoY. Billet sales fell ~40% H1 over H1 due to 2-month power plant shutdown for pollution-norm compliance. 30-ton furnace upgrade in progress.

H1 production +16% · Q2 production +5% YoY · DRI ₹22,000-23,000 · Billets ₹34,000-35,000 · Finished steel ₹38,000-39,000

Outlook: New 30-ton furnace to absorb all sponge output, taking merchant sponge sales to zero from next year

Galvanized Fabricated Products

Only segment with YoY realisation stability. PGCIL approval secured; rolling mill capacity ramping up; new strips and billets to support Q4 volume jump.

Outlook: Substantial jump in strip and billet volumes from Q4 onwards leveraging PGCIL approval

BESS (Godawari New Energy)

10 GW BESS project in Maharashtra; 112 acres land acquired; ₹175 cr equity infused; MoU with Maharashtra signed; machine order placement underway.

Project cost ₹700 cr · 60% debt / 40% equity · ₹175 cr equity already infused · 112 acres land

Outlook: Commercial production April 2027 (FY28); 50–60% PLF Year 1, 80%+ from Year 2; cells from CATL, EVE, Lithium

Solar (Captive)

Board approved 250 MW solar (additional to 125 MW) for CRM and integrated steel plant, plus to displace thermal generation for existing operations.

250 MW new · +125 MW vs earlier plan · Solar cost ~₹5.50/unit vs grid ~₹8/unit

Outlook: Targeted Q4 FY27 commissioning; internal IRR ~24%

Balance sheet, capex and funding

  • Maintained a solid net cash position through the quarter
  • CRM complex capex ₹900 cr funded by ₹600 cr debt and ₹300 cr internal accrual; major equipment orders placed
  • BESS capex ₹700 cr funded 60% via debt and 40% via GPIL equity; ₹175 cr equity already infused into Godawari New Energy
  • ₹100 cr preferential issue; 50%+ taken by promoters; partial use for BESS and CRM funding
  • 1 mt integrated steel plant capex will require incremental debt beyond internal accruals; timing post mining EC

The industry, as management sees it

Indian steel demand expected to grow 9% in both FY25 and FY26 per World Steel Association, with infrastructure/construction-led expansion (NIP, PMAY). Acute iron ore shortage in the Eastern belt is keeping raw material prices elevated even amid soft steel realisations. Global iron ore in $95-$110 band, expected $90-$105 in China for CY25 with China demand -2%/-1%. Pellet demand-supply gap in Raipur expected to close once GPIL's 2MT plant commissions.

Risks management named

  • Soft steel realisations across billet/sponge — visibility limited, demand has been weak for 5-6 months
  • Pellet plant safety incident on 26 Sept '25 resulted in 6 fatalities and ~40 days of production loss
  • Future steel plant capex will require incremental debt beyond the recent INR100 cr preferential issue

Q&A

Q&A was dominated by project-execution and capacity-expansion granularity — Ari Dongri EC timeline, 2MT pellet commissioning within weeks, CRM/BESS commissioning Apr '27, and the 24% IRR economics of the 250MW solar. The Sept '25 pellet plant incident was acknowledged in opening remarks but no analyst pressed on regulatory/SEBI fallout, which is a notable gap. Pushback was concentrated on whether solar capex was the best use of funds (defended credibly on grid tariff math) and on whether pellet realisations can hold despite NMDC's price cut (defended on regional Raipur demand-supply gap). The weakest deflection was on near-term secondary steel demand visibility — management effectively conceded 5-6 months of weak demand without offering a Q3/Q4 outlook. Dinesh Gandhi stepped in specifically to address the preferential issue rationale.

Not answered directly

  • Safeguard duty final notification (deferred — ED not tracking HRC)
  • Aggregate India DRI capacity addition data (deferred — to revert)
  • Near-term secondary steel demand visibility (evasive — no concrete Q3/Q4 call)

Asked for a number, answered without one

  • DRI capacity additions in India: Said exact data not available; will check and get back with the number

Every question, with its answer

  1. 1. Pellet and steel realisations; safeguard duty

    Vikash Singh, ICICI Securities

    Question. Could you give an idea of spot prices vs Q1 averages and confirm any recent price increases in long products? Also any update on the lapsed provisional safeguard duty?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Pellet H1 average was close to INR9,000; H2 expected at similar level (+/- 8-10%). DRI INR22,000-23,000 lower side; billets bottomed at INR34,000, now ~INR35,000; finished INR38,000-39,000. Last 6 weeks have been at the bottom for this FY; demand picking up post-monsoon and festivals. On safeguard duty — ED does not deal directly in HRC, deferred as not closely followed.

    Follow-up. Was there any INR1,000-INR1,500 hike in long products in the last week?

    Answer. Prices are slowly picking up; attempts to raise prices have rolled back if demand didn't sustain. Trend of attempted hikes followed by partial rollbacks for last couple of weeks; confident of improvement from here.

    Partly answered.

  2. 2. What kind of cost savings and internal IRR do you expect from the 250MW solar for CRM, e…

    Vikash Singh, ICICI Securities

    Question. What kind of cost savings and internal IRR do you expect from the 250MW solar for CRM, especially given no premium for green steel?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Grid tariff would be INR7.70-8/unit; CRM operates at 8-10% margins so every penny matters. Land already available; solar reduces operating cost from day one. The 250MW will feed CRM and in long run the Boria Tibu mine (tariff ~INR12). Thermal not cheaper (INR7 cr/MW minimum); company explicitly will not return to fossil-fuel thermal. Expects carbon-tax benefits over time.

    Follow-up. Until your own HRC capacity comes in, what conversion margins do you expect in CRM at current spot?

    Answer. GPIL will not enter HRC; will be a long-term HRC buyer. CRM is high-volume, low-margin (~7-8% average, 10% good). Business planning uses the same margin assumption.

  3. 3. Once Ari Dongri goes to 6MT, will Boria Tibu need to run too, or will you save that for…

    Vikash Singh, ICICI Securities

    Question. Once Ari Dongri goes to 6MT, will Boria Tibu need to run too, or will you save that for the future?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Boria Tibu is a low-grade mine (48-50% Fe); takes 3-4 years to ramp infrastructure. Plan to start ramping Boria Tibu to a decent level in 3-4 years; minimum April '29 for any capacity increase. Long-term optionality play.

  4. 4. With Ari Dongri going to 6MT, when does the entire crushing/beneficiation come online an…

    Siddharth, Equirus Capital

    Question. With Ari Dongri going to 6MT, when does the entire crushing/beneficiation come online and we should be at 6MT run rate?

    Answer, Management, Executive Director (likely Abhishek Agrawal). State Pollution Board clearance expected by end of current quarter (i.e. Dec '25). Couple of months after that to get things in order. Ramping from Apr '26; FY27 target 4.5-5MT; full 6MT from Jan '27. Boria Tibu will mine ~0.5MT, yielding ~0.3MT concentrate.

    Follow-up. So beneficiation and crushing by end CY26 and then ramp up?

    Answer. Already running 0.6MT beneficiation; further expansion is just an extension. 4-6 months from permission; full beneficiation by June-July; Q3 onwards full capacity.

  5. 5. Peak iron ore requirement in CY27?

    Siddharth, Equirus Capital

    Question. Peak iron ore requirement in CY27?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Current pellet output above 4.2MT; with 15-20% yield loss on beneficiation, need 5.7-5.8MT iron ore. First phase ~5MT, second phase to 6MT — always 100% captive. No intention to sell surplus in market.

    Follow-up. Will we still use pellets for sponge iron, no transfer?

    Answer. Mine is magnetite — not suitable to directly feed DRI/sponge. DRI capacity will always run on 100% pellet. Mine ~5.5-5.75MT in normal monsoon year; 6MT is the goal.

  6. 6. Timelines for CRM complex and BESS plant?

    Siddharth, Equirus Capital

    Question. Timelines for CRM complex and BESS plant?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Commercial production April '27 (FY28) for both BESS and CRM. First year PLF 50-60%; from second year 80%+ in both plants.

    Follow-up. And in 2 years we should reach full utilisation?

    Answer. Confirmed — Y1 50-60% PLF, Y2 onwards 80%+ for both plants.

  7. 7. With Boria Tibu work starting, would we again expand pellet capacities in 2-3 years?

    Siddharth, Equirus Capital

    Question. With Boria Tibu work starting, would we again expand pellet capacities in 2-3 years?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Boria Tibu is to support new 1MT steel complex. Capex for Boria Tibu small; needs new EC (18-24 months) and 12 months to commission. Capex only ~2 years down the line, not before.

    Follow-up. Steel plant timeline?

    Answer. Steel plant proposal to Board only after final mining EC clearance. Capex fine-tuning in progress; possibly next Board meeting for approval. Couple of months more for capex finalisation.

    Partly answered.

  8. 8. Iron ore expansion at Ari Dongri — public hearing done, EC by Dec; any production lag on…

    Manav, Yes Securities Limited

    Question. Iron ore expansion at Ari Dongri — public hearing done, EC by Dec; any production lag once ECs in?

    Answer, Management, Executive Director (likely Abhishek Agrawal). No lag. Volumes for FY27 (Apr '26 Q1) were always calculated assuming additional volumes. EC delayed slightly (thought could get by Diwali); no production lag this year. Some monsoon overlap in Q1 FY27.

    Follow-up. Pellet plant commercial production start for the 2MT expansion?

    Answer. In a couple of weeks; awaiting final approval. Cold trials permitted. Expect 80-85% capacity from Q4 for the new pellet plant. Ramp-up 4-6 weeks.

  9. 9. Quantify impact on volumes from the pellet plant incident inclusive of maintenance shutd…

    Manav, Yes Securities Limited

    Question. Quantify impact on volumes from the pellet plant incident inclusive of maintenance shutdown?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Lost ~1.5 lakh tons of volume — some at end of Q2 and all of October. Of 35-40 day shutdown, 20-25 days were planned annual shutdown at end Q3/early Q4 — maintenance done in this window. New pellet plant ramping from Q4; confident of achieving declared FY26 3MT target.

    Follow-up. Run rate ~820 KT/quarter for next couple of quarters?

    Answer. Q4 FY26 (Jan-Mar) should be ~0.9MT. Confident new plant covers the lost volume.

  10. 10. Mining delayed, pellet plant up — merchant iron ore purchases in Q3 and Q4?

    Manav, Yes Securities Limited

    Question. Mining delayed, pellet plant up — merchant iron ore purchases in Q3 and Q4?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Yes. Have been buying ~50,000 tons/month. Pellet supply shortage in Raipur; merchants buying 100% iron ore from market are still making money. Additional pellet volumes will add to bottom line.

    Follow-up. Premiums on iron ore pellets — any fall?

    Answer. No premiums as such. Raipur has heavy addition of DRI capacities; shortage of pellets. Once new plant comes in, demand-supply gap will balance; prices expected at similar level.

  11. 11. What was the landed cost of imported coal for the quarter? Q3 shaping?

    Manav, Yes Securities Limited

    Question. What was the landed cost of imported coal for the quarter? Q3 shaping?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Q2: ~INR11,000 landed (RB1 coal, 6000 GCV). Q3: index had dropped below 80 but recovered; expects INR10,500-11,000. Dollar rate INR86-89 — needs to be considered. Stable, +/-INR500.

  12. 12. BESS — Ola and Adani announcements; how similar and what's the competition?

    Sahil Sanghvi, Monarch Networth Capital

    Question. BESS — Ola and Adani announcements; how similar and what's the competition?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Stiff competition acknowledged. Targeting top-5 in India by volume. Adani's 30GW is for captive Gujarat solar park; 30-35GW for their own use. Ola doing BESS for battery charging/net metering — different application. GPIL not a tender bidder; will supply containers directly to compete with imports and other India players. India currently 10% domestic / 90% import; government policy expected to support domestic. Reliance is doing 40GW — 30GW for telecom towers, 10GW market.

    Follow-up. Iron ore mined in FY27 — 5-5.5MT?

    Answer. FY27: ~4.7-5MT due to monsoon (5 months this year) and slight delays. Beneficiation plant 6MT by June-July.

  13. 13. Balance iron ore requirement — fully market-dependent or Boria Tibu also?

    Sahil Sanghvi, Monarch Networth Capital

    Question. Balance iron ore requirement — fully market-dependent or Boria Tibu also?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Boria Tibu continuing at ~0.5MT, yielding ~0.3MT concentrate; rest from market. Expects this continues max till ~March; from April, additional mine volumes kick in.

    Follow-up. FY27 pellet production target — 4MT or lower?

    Answer. 4MT bare minimum; likely higher. New plant at 80% from January itself. For next year 4MT+ without doubt.

  14. 14. Sponge iron production declined; are we using it internally to make pellets and other pr…

    Vinit Thakur, Plus91 Asset Management

    Question. Sponge iron production declined; are we using it internally to make pellets and other products?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Current sponge iron capacity 0.6MT, production ~0.5MT. Installing new 30-ton furnace requiring additional 1,500 tons sponge iron. Sponge sale should be totally zero from next year onwards.

    Follow-up. Spike in galvanized fabricated production — what's driving it?

    Answer. PGCIL approval received; ramping rolling mill capacity. Started taking strips for pipe segment due to billet quality. Expect substantial Q4 jump in rolled products and billets.

  15. 15. Steel billet sales declined 40% H1 over H1 — why?

    Vinit Thakur, Plus91 Asset Management

    Question. Steel billet sales declined 40% H1 over H1 — why?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Planned 2-month shutdown of one of the bigger turbines in June for pollution norm modifications as directed by State Pollution Board. Less power led to lower billet production.

    Follow-up. Iron ore capacity shortfall in India — good price rise coming in fines?

    Answer. Acute shortage of iron ore in Eastern belt (Bengal, Odisha, Jharkhand) — keeps pellet prices high. DRI players feel pellets should be INR1,000 lower but shortage of iron ore in India and 8-9% annual demand growth keeps raw material prices elevated.

  16. 16. Are current iron ore and pellet prices the bottom — going up from here?

    Vinit Thakur, Plus91 Asset Management

    Question. Are current iron ore and pellet prices the bottom — going up from here?

    Answer, Management, Executive Director (likely Abhishek Agrawal). On long-term basis, INR9,000 ex-plant pellet realisation is 'very practical'. Not optimistic or pessimistic — INR9,000 is good pricing for pellet makers.

  17. 17. BESS — utility-grade supply; have partnership discussions with developers started?

    Ashish Soni, Family Office

    Question. BESS — utility-grade supply; have partnership discussions with developers started?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Not yet — 12-13 months from supplies starting. Will engage 3-4 big developers closer to commissioning. No point in early talks given import competition.

    Follow-up. Cells imported from China; warranty for 5-10 year BESS projects?

    Answer. Will pass on cell warranty back-to-back. PCS and EMS compulsory from India; cells imported. Cells ~8,000 cycles for 2-hour charging (~8-10 years). Only CATL, EVE, lithium identified at advanced negotiation stage.

  18. 18. Recent preferential issue — what was the rationale?

    Siddharth, Equirus Capital

    Question. Recent preferential issue — what was the rationale?

    Answer, Dinesh Gandhi, Executive Director. >50% taken by promoters. Promoters wanted additional liquidity in the company; partial utilisation for upcoming projects, helps fund without raising additional debt. INR100 cr does not fund entire steel plant but helps BESS and CRM. Steel plant will require incremental debt — equity availability and additional requirement to be assessed.

    Follow-up. Pre-emptive fundraise for steel plant capex?

    Answer. Confirmed steel plant will require debt raise beyond current preferential issue.

  19. 19. Pellet volumes for 2H — NMDC price cut; can we still maintain pellet realisations?

    Siddharth, Equirus Capital

    Question. Pellet volumes for 2H — NMDC price cut; can we still maintain pellet realisations?

    Answer, Management, Executive Director (likely Abhishek Agrawal). 100% — NMDC supply limited to certain linkages; additional DRI capacity demand every month in the area. Pellet shortage in market. No challenge on volumes or pricing for remaining FY.

    Follow-up. H1 mainly Raipur or other markets?

    Answer. Max ~100 km around Raipur. Won't change on expanded capacity — pellet from outside Chhattisgarh (e.g., Odisha) will stop first. Some commodity price +/- but gap will close with new capacity.

  20. 20. Number on DRI capacity addition in India over 1-3 years?

    Siddharth, Equirus Capital

    Question. Number on DRI capacity addition in India over 1-3 years?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Don't have data; will get back. Knows Chhattisgarh capacity informally via promoter network but exact national numbers not available.

    Follow-up. Confident on incremental offtake?

    Answer. Yes confident; no concerns.

    Not answered directly.

  21. 21. Secondary steel weakness in billet and sponge — continue in Q3 and some pickup in Q4?

    Siddharth, Equirus Capital

    Question. Secondary steel weakness in billet and sponge — continue in Q3 and some pickup in Q4?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Hopefully not. Doesn't know exactly when; weakness extended 5-6 months. Hopes industry demand comes back and prices go up — otherwise tough time for industry to survive.

    Not answered directly.

  22. 22. 2MT pellets coming in — exports strategy?

    Manav, Yes Securities Limited

    Question. 2MT pellets coming in — exports strategy?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Yes, 100%. Always has eye on exports; tracks market. Even Lloyds exporting a little. Export market moderately strong (iron ore above $100). Open to exports if domestic market challenging. New capacity may mean one cargo monthly.

    Follow-up. Did anything during H1?

    Answer. No exports in H1; only when domestic demand insufficient. New capacity may change that.

  23. 23. Status on BESS — CRM order placements done in Q2?

    Manav, Yes Securities Limited

    Question. Status on BESS — CRM order placements done in Q2?

    Answer, Management, Executive Director (likely Abhishek Agrawal). Land acquired at AURIC, Aurangabad. MoU signed with Maharashtra government. Demarcation and infra work starts next month; full-throttle from January. Orders placed with India and China suppliers. Line up Jan-Mar '27; trial commissioning then. Both BESS and CRM commissioning April '27 (FY28).

    Follow-up. FY27 end?

    Answer. Confirmed April '27 (FY28) for both. Confident of meeting that.

What was said

Topic by topic, in the order it was spoken

Safety Incident and Family Support · Dinesh Gandhi (Executive Director)

  • 26 Sept '25 incident at one pellet plant resulted in 6 fatalities and 6 injuries
  • Financial assistance provided to families plus employment for non-employable members and pension benefits
  • Children's school and education expenses to be reimbursed uninterrupted
  • Acknowledged as a 'deeply mourned and unforeseen' event; framed as the highest responsibility

H1 FY26 Operational Performance · Dinesh Gandhi (Executive Director)

  • Iron ore mining production +18% YoY, value-added steel products +16% YoY despite 5 days of Sept production loss
  • Pellet sales +30% in H1; value-added steel products declined except ferro alloys and galvanized fabricated
  • Consolidated sales turnover largely stable; EBITDA and PAT lower YoY on softer realisations but margins held

Q2 FY26 Operational Performance · Dinesh Gandhi (Executive Director)

  • Q2 production growth: mining +29%, pellet +31%, value-added +5%
  • Pellet sales surged 71% YoY; value-added steel products declined
  • Revenue/EBITDA/PAT YoY lower; QoQ also lower on reduced realisations and seasonal necklaces
  • EBITDA margin 20%, PAT margin 12% in Q2 — described as holding firm

Ari Dongri Mining Capacity Expansion · Dinesh Gandhi (Executive Director)

  • Capacity being raised from 2.35MT to 6MT per annum — long-pending regulatory approval now in motion
  • Public hearing for environmental approval completed; final approval expected by end-Dec '25
  • FY27 mining target 4.7-5MT (monsoon weighed); full 6MT from Jan '27

Pellet Capacity Expansion (2MT) · Dinesh Gandhi (Executive Director)

  • Pre-commissioning trials underway; commissioning targeted end-Nov '25 pending State PCB consent to operate
  • All commissioning work completed; Q4 capacity utilisation expected at 80-85%
  • Ramp-up expected in 4-6 weeks from commissioning

CRM Complex (0.7MT Cold Rolling) · Dinesh Gandhi (Executive Director)

  • 452 acres of land acquired for integrated steel plant and CRM complex
  • Total project cost INR900 crores — INR600 crores debt, balance internal accruals
  • Major equipment orders placed; commissioning targeted April '27 (FY28)
  • Will source HRC from market on long-term basis; conversion margin guidance 7-10%

Godawari New Energy (10GW BESS) · Dinesh Gandhi (Executive Director)

  • Wholly-owned subsidiary; 10GW BESS project in Maharashtra at AURIC industrial area, Aurangabad
  • Project cost INR700 crores — 60% debt, balance from internal accruals; INR175 cr equity already infused
  • MoU signed with Maharashtra government under industrial policy; demarcation and infra work starts next month, full site work Jan onwards
  • Cells will be imported from top China suppliers (CATL, EVE, lithium); PCS and EMS compulsory from India
  • Strategy: be a container supplier to developers, not a tender bidder; targeting top-5 India position by volume

Solar Power and Renewable Strategy · Dinesh Gandhi (Executive Director)

  • Board approved additional 250MW solar (vs earlier 125MW) for captive use with CRM and integrated steel plant
  • Project commissioning Q4 FY27 coinciding with CRM commissioning
  • Surplus solar to displace thermal power at Boria Tibu mine (grid tariff ~INR12) and integrated steel plant
  • IRR ~24% at INR5.50 landed power vs INR7.70-8 grid tariff; net cost saving of ~INR2.50/unit
  • Explicit no-fossil-fuel-thermal strategy; expects carbon-tax/regulatory tailwinds

Boria Tibu Mine · Dinesh Gandhi (Executive Director)

  • Operations resumed May '25 after mining plan approval
  • Low-grade mine (Fe content ~48-50%); captive concentrate supply for pellet plants
  • Constant mining target ~0.5MT, yielding ~0.3MT concentrate
  • Future ramp planned 3-4 years out (no capacity addition before Apr '29); EC process takes 18-24 months

Market Outlook (Iron Ore, Pellet, Steel) · Dinesh Gandhi (Executive Director)

  • Global iron ore prices in $95-$110 band; currently $102-$103/ton
  • China iron ore expected $90-$105 in CY25; World Steel Association sees China steel demand -2% CY25, -1% CY26
  • Indian iron ore (NMDC 64 AC fines) range-bound INR4,500-5,500/ton
  • Pellet prices stable INR8,500-10,000, currently ~INR9,750/ton; H2 expected similar
  • World Steel Association forecasts India steel demand +9% in both FY25 and FY26; demand to be ~75MT higher than 2020 by '26

Long-term Positioning · Dinesh Gandhi (Executive Director)

  • Net cash position maintained; strategic capex pipeline plus strong ESG focus cited
  • Stated as only Indian company offering fully integrated end-to-end galvanized steel structures from iron ore to finished product
  • Received PGCIL approval for transmission-grade galvanized steel structures — billets now comparable to leading producers
  • Combined mining/pellet scaling, downstream deepening and renewable integration framed as next growth phase

In their words

This 250-megawatt solar, if you compare with the rate of INR7 and net cost to the steel plant at about INR5.50, the internal rate of return is about 24%.
Dinesh Gandhi (Executive Director, GPIL)
Today, a thermal power plant is not cheap. It's INR7 crores minimum per megawatt. Plus, as a company, we have decided we will not be going to any fossil fuel thermal plant. We have no intention of going back into that.
Management (likely Abhishek Agrawal, Executive Director, GPIL)
If I have done a preferential issue, it shows that 50% or more than 50% of this is taken by the promoters. Who else knows the business better than the promoters?
Dinesh Gandhi (Executive Director, GPIL)

To check next time

What management committed to on this call, or the dates they gave.

  • 2 mt pellet expansion commissioning by end of November 2025
  • Mining EC final approval from State Pollution Board by end of December 2025
  • Steel plant proposal to Board at next meeting post mining EC
  • BESS machine order placements completion within next 6 months
  • CRM major equipment order placement progress and site work in Maharashtra
  • Q3 imported coal landed cost tracking within ₹10,500-11,000/ton

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Mon 17 Nov 2025₹276.10−0.22%+0.40%
5 sessions Fri 21 Nov 2025₹241.70−12.65%+0.61%
20 sessions Fri 12 Dec 2025₹238.61−13.77%+0.53%

From the close of Fri 14 Nov 2025, ₹276.70: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Godawari Pow & Isp's other calls