Godawari Pow & Isp Q3 FY25 earnings call

Thu 13 Feb 2025GPIL

In brief

Management's tone
Cautious
What was said
Even-handed
Guidance
Guidance held
Analyst pushback
Medium
Stock, next session
−1.34% (Nifty 50 −0.06%)
  • 2 MT greenfield steel plant formally dropped due to capex overruns (Rs 8,000 cr estimate) and flat-steel oversupply; exploring 0.8–1 MT brownfield alternative at Rs 3,500–4,000 cr to avoid debt funding.
  • OPVC pipe project (Rs 125 cr) also dropped after Chinese tech eroded first-mover advantage; supplier has agreed to refund the Rs 14 cr advance.
  • Pellet Q3 weakness attributed to ~50,000 ton one-off export at lower realisation plus new merchant capacity in Chhattisgarh; expects sharp Q4 recovery on inventory clearance.
  • FY26 capex guided at Rs 1,000–1,100 cr (pellet Rs 432 cr residual, mining, beneficiation, solar); to be funded internally from Rs 725 cr net cash plus free cash flows — no fresh debt.
  • Ari Dongri mining EC expected by Q1 FY26, with IBM approval already secured; full ramp takes FY27 pellet capacity to 4.5 MT and unlocks targeted ~Rs 600 cr incremental EBITDA.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q3 FY25

This quarterA year agoLast quarterMargin
Revenue₹1,298 cr−0.9%+2.4%
EBITDA (excl. other income)₹221 cr−33.2%−10.6%17% (25.3% a year ago)
Net profit₹145 cr−36.8%−9.0%11.2% (17.5% a year ago)
EPS (₹)₹2.36−87.2%−81.8%

From the company's filed results for the quarter ended 31 Dec 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

The numbers management led with

  • Net cash position: Rs 725 crores
  • Pellet capacity after expansion: 4.7 million tons (up from 2.7 MT)
  • Ari Dongri mining capacity expansion: From 2.35 MT to 6 MT; EC expected by Q1 FY26
  • FY26 capex guidance: Rs 1,000-1,100 crores (incl. Rs 432 cr balance pellet)

Guidance

Guidance on this call

FY25 production volumes maintained at guidance — iron ore mining 69% achieved, pellets 73%, sponge iron 84%, ferro alloys 96% of FY25 target. FY26 pellet volume guided at 3–3.25 MT (additional ~0.5–0.7 MT from new plant at 40% utilisation); FY27 pellet volume targeted at ~4.5 MT. FY26 capex guided at Rs 1,000–1,100 cr covering pellet balance (~Rs 432 cr), mining, beneficiation, and solar. FY27 steel plant capex ballpark Rs 3,500–4,000 cr for 0.8–1 MT. FY27 incremental EBITDA target of ~Rs 600 cr from new pellet plant (range Rs 500–800 cr depending on market).

Said on the Q2 FY25 call, not repeated on this one (6)
  • JPL turnover: ~INR1,700 cr after addition of new unit in next 2-3 months
  • JPL EBITDA: ~INR125 cr once new unit is operational
  • JPL EBITDA margin: Move from current ~7-8% toward 10% via process improvement
  • JPL turnover growth: 15-20% YoY indicated
  • Capex (JPL): INR200 cr earmarked for capacity expansion; subject to debottlenecking study
  • Capacity expansion timeline: Target operational by FY27; pyro first, then hydro and electrolysis

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY25 EBITDA marginFY2524–25% (on the Q4 FY24 call)22.2%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

The industry, as management sees it

Management sees India's pellet capacity at ~150 MT installed (~80% utilisation) with an additional 6 MT of new capacity (including Lloyd's 4 MT) in the next 6–8 months, shifting Chhattisgarh from a deficit region to a structurally surplus one. India steel demand is expected to grow 8–9% in 2025 driven by housing and infrastructure, but rising imports remain a concern. Globally, iron ore prices are expected to decline in 2025 with elevated supply from Australia and weakening Chinese demand post-trade-tariff actions.

Risks management named

  • Pellet oversupply in Chhattisgarh from new merchant plants could structurally pressure realisation
  • Ari Dongri EC approval hinges on state-level public hearing and pollution board clearance
  • Steel plant capex mis-estimation; smaller capacity alternative still in evaluation stage
  • Domestic iron ore demand-supply gap persists; international prices 7-8% above lows but unlikely to spike
  • Natural gas economics may not deliver margin benefit vs producer gas despite CBAM compliance

Q&A

Q&A spanned 16 exchanges with broad institutional coverage. Discussion centred on three themes: (1) strategic — rationalisation of the 2 MT greenfield steel plant and OPVC pipe project in favour of a brownfield ~1 MT alternative; (2) pellet market dynamics — Q3 realisation weakness attributed to a one-off export shipment and Chhattisgarh oversupply, with Q4 expected to recover on inventory clearance; and (3) project execution — Ari Dongri EC timeline, pellet plant capex pacing, and FY27 earnings ramp from full 4.5 MT pellet capacity. Pushback was mild with most management responses being direct; deflection was rare aside from the steel plant scoping which remains in evaluation. The FY27 EBITDA target of ~Rs 600 cr incremental from new pellet assets was disclosed without a detailed build-up.

Not answered directly

  • Steel plant revised capacity and capex
  • Jammu Pigments top-line contribution magnitude

Every question, with its answer

  1. 1. Project rationalisation — OPVC and steel plant

    Vikash Singh, Phillip Capital

    Question. Why was the OPVC pipe project dropped and what is the plan for the cash being held by the company given that both large-scale projects have been dropped?

    Answer, Abhishek Agarwal, Executive Director. OPVC was a small capex of about Rs 125 cr (only Rs 14 cr spent on equipment). The project was dropped because Chinese technology entered India quickly, and competitors like Apollo, Sambhav and Bajarang already placed orders — wiping out the first-mover advantage that existed 1–2 years ago. The equipment supplier has agreed to return the advance; so there is no financial loss. On cash deployment, the original Rs 5,000–6,000 cr capex for the 2 MT steel plant is now projected to cross Rs 8,000 cr due to a capex structure mis-call (60% infra vs 40% equipment was reversed). Management does not want to go back into a long-term debt cycle, so the 2 MT project is being re-scoped to a smaller 0.8–1 MT capacity with lower capex. The smaller plant will consume pellets internally to convert into value-added steel; about Rs 7–8 cr spent so far — all recoverable.

    Follow-up. Spending on steel plant so far and the current international vs domestic pellet price differential given rising global iron ore prices.

    Answer. Almost nothing has been spent on the steel plant — below Rs 1 cr in license fees, approvals, and plantation work. On pricing, the company exported a pellet vessel in Q3 because post-Diwali domestic demand was sluggish and new merchant pellet plants in Chhattisgarh pressured the market. Exports have now stopped as domestic demand recovered post-budget announcement; export realisation is currently about Rs 1,000/ton lower than domestic on net basis.

  2. 2. Boria Tibu operations and iron ore pricing

    Vikash Singh, Phillip Capital

    Question. Has the Boria Tibu beneficiation plant been completed, and what is the outlook for domestic iron ore prices given the weaker domestic trend vs improving international?

    Answer, Abhishek Agarwal, Executive Director. Boria Tibu has no standalone beneficiation plant; instead, the ore is being routed to the Godawari plant's circuit and beneficiated from ~55 Fe to 65 concentrate. A dedicated mine-site beneficiation for Boria Tibu is 3–4 years away. On prices, international has moved up 7–8% from lows ($97 to $106), but domestic has remained largely stable; a substantial domestic price spike is unlikely. However, a domestic supply shortage will persist and keep pellet pricing firm relative to international.

    Partly answered.

  3. 3. Steel plant scoping and route

    Manav Gogia, YES Securities Limited

    Question. Does the Rs 8,000 cr steel plant capex estimate include a coke oven? And what production route is being pursued given earlier guidance of 2 MT minimum for an HRC plant?

    Answer, Abhishek Agarwal, Executive Director. The capex estimate does include a coke oven. About a month back, the Government of India restricted coke imports to merchant cokeries, which forced GPIL to add coke oven to its project scope (likely a reference error — figure quoted as Rs 50,000 cr appears to be a verbal misstatement; the previously stated total was Rs 8,000 cr). On the route, HRC has been dropped completely because primary producers are adding ~20 MT of flat-steel capacity over the next couple of years (NMDC's 3 MT plant commissioned, JSPL 5 MT commissioned). The company is now evaluating long products and heavy structures/beams in the flat segment where a 1.25–2 metre range is possible without competing head-on with the larger players.

    Follow-up. Capex split between Q4 FY25 and Q1 FY26 for the pellet plant capex of Rs 432 cr remaining.

    Answer. Capex has already started — equipment shipments from China are arriving. Trial production is expected by early Q2 FY26 and the full Rs 432 cr will be spent over the next 4 months (Q4 FY25 and Q1 FY26). Plant will be fully operational in 3–6 months; in the worst case, full production by Q4 FY26. Annual maintenance shutdown is ~25–30 days with shorter 4–5 day shutdowns during the year.

    Partly answered.

  4. 4. Pellet realisation and supply dynamics

    Sahil Sanghvi, Monarch Networth Capital

    Question. Why was Q3 pellet realisation so weak when Raipur steel prices were largely flat QoQ and YoY? Will the pellet supply surplus pressure repeat when the new plant comes online?

    Answer, Abhishek Agarwal, Executive Director. Post-Diwali, steel demand was sluggish and new merchant pellet plants in Raipur caused oversupply. GPIL exported one vessel while carrying an abnormal ~53,000 ton inventory (later ~1 lakh ton). End-December demand picked up; the order book is healthy through March. It was a one-off inventory situation plus a Q3 export that dragged EBITDA. Supply surplus could repeat after the new plant comes online, but GPIL is hedged because the new plant produces high-grade pellets for bigger players (JSPL, coastal movement) and exports remain an option.

    Follow-up. Have we dropped production guidance for FY25 to 2.4 MT? What is the export quantum and confidence in receiving the Ari Dongri mining EC by Q1 FY26?

    Answer. Production is on track — sale was down vs production because of inventory build; inventory now below 20,000 tons. Guidance of 2.4–2.5 MT pellet volumes for FY25 is reaffirmed 100%. On the EC, central mining ministry and law ministry approvals have already been received (took 6 months), and IBM has approved the new mining application; remaining steps are state pollution board public hearing (expected post-Holi, end-March) and final EC within a couple of months thereafter.

  5. 5. Mining EC and beneficiation economics

    Siddharth Gadekar, Equirus Securities

    Question. Has a public hearing date been received for the Ari Dongri mining expansion, and how should we think about ramp-up given that beneficiation comes online 6 months after EC? Also, what is the cost structure of beneficiating Rs 35 to Rs 65 and how does the royalty math work?

    Answer, Abhishek Agarwal, Executive Director. Public hearing expected post-Holi end-March; EC in a couple of months thereafter — confidence high that EC will be in by Q1 FY26. On ramp-up, 0.6 MT BMQ beneficiation is already commissioned and running at full flow; the remaining 0.9 MT BMQ will take 6 months post-EC. The 4.5 MT lump ore beneficiation will also take ~6 months. In the interim, GPIL will continue transporting 60–61 Fe ore to the existing plant for beneficiation at a delivered cost of ~Rs 2,200/ton post-beneficiation. On royalty, GPIL pays royalty on the 65 concentrate at ~Rs 750/ton as per IBM norms — not on the Rs 35 ROM. Until the mine-site beneficiation is up, low-grade is transported to plant (incur ~Rs 1,000 extra transportation); after commissioning, savings of ~Rs 500 from royalty reduction offset by ~Rs 150 higher transport.

    Follow-up. What is the capex outlook for FY26 and FY27 given the steel plant is being re-scoped?

    Answer. FY26 capex of ~Rs 1,000–1,100 cr covers mining, beneficiation, pellet plant, solar (both mining and pellet), and other items. FY27 will see a revised capex plan tied to the smaller steel plant capacity announcement. Ballpark for a 0.8 MT steel plant is ~Rs 3,500 cr and 1 MT plant ~Rs 4,000 cr (assumes Rs 400–450 cr per lakh ton).

  6. 6. FY26-FY27 guidance and Jammu Pigments

    Mohammed Sahil, IDBI Capital Markets

    Question. Can you provide FY26 guidance for revenue and EBITDA margins, and what is the FY27 EBITDA target? What was Jammu Pigments' contribution to the top-line this quarter?

    Answer, Abhishek Bothra / Sanjay Bothra, Executive Director / CFO. FY26 guidance: incremental production of 0.5–0.6 MT from the new pellet plant takes total pellet production to ~3 MT; FY26 revenue and EBITDA growth will be modest given mining starts only in Q2. FY27 should see a substantial jump — at 4.5 MT pellet capacity plus ancillary businesses, incremental EBITDA of Rs 600 cr (range Rs 500–800 cr) is reasonable at current market prices. Jammu Pigments: 49% acquired but only 21.46% held till December 2024; treated as a JV, so only share of profit is consolidated (~Rs 50 lakhs for 40 days of profit share).

  7. 7. Steel plant decision rationale

    Jash, Dalal & Broacha

    Question. Was dropping the 2 MT steel plant driven by environment clearance delays or higher capex? Is the smaller 1 MT alternative timed to Boria mines coming online in FY27 to avoid an earnings hit?

    Answer, Abhishek Agarwal, Executive Director. Two reasons for dropping the 2 MT project: (1) capex mis-estimation — initial Rs 6,000 cr now looks like Rs 8,000 cr minimum, and management does not want to do an HRC project where too many primary producers are adding capacity; (2) EC could have been obtained last year but the project would have started at inflated capex. The smaller steel plant will definitely come up because converting pellets to value-added steel internally is necessary; the company is evaluating capacity and a concrete plan will follow.

  8. 8. Long-term pellet competitive structure

    Aditya Welekar, Axis Securities

    Question. Structurally, does the surge in pellet capacity in the Chhattisgarh-Raipur area pose a long-term risk to pellet realisations, and how easy is it for new entrants to set up pellet plants?

    Answer, Abhishek Agarwal, Executive Director. Buying fines from the market and investing in a pellet plant is not a viable business proposition; only backward-integrated players with captive iron ore will survive. GPIL is 100% captive on iron ore and will continue to make money. Lloyd's 4 MT plant in Maharashtra will be an additional competitor in the same Chhattisgarh region. In the longer term, GPIL plans to hedge by converting pellets into steel internally via the new steel addition.

  9. 9. India pellet industry capacity and exports

    Chirag Singhal, First Water Fund

    Question. How much pellet capacity was commissioned in the last 12 months and how much is expected in the near term (excluding GPIL expansion)? What is total India pellet capacity and the export quantum?

    Answer, Abhishek Agarwal, Executive Director. About 2 MT has been commissioned in the last 12 months. An additional ~6 MT is expected in the next 6–8 months: Lloyd's 4 MT plant in Maharashtra (Q1 FY26) and Raipur-area additions of 2.5 MT. Of the 2 MT commissioned earlier, Bengal has effectively turned into a seller rather than a buyer because each steelmaker has invested in its own pellet plant — pushing Orissa merchants to divert sales to Chhattisgarh. Total India installed pellet capacity is ~150 MT with ~80% utilisation (so ~120 MT annualised). Export is limited to port-based players (BRPL, Mandovi Goa, Asit Mittal); inland plants like GPIL do not export economically.

    Follow-up. Is it fair to assume Q4 pellet realisations will be at least Rs 1,000 higher than Q3 reported? Should investors expect a pricing-led or volume-led Q4 recovery?

    Answer. Pricing impact will be minimal because the export vessel was only 50,000 tons against 3 lakh tons sold (only ~18% volume impact). What drives Q4 EBITDA is the inventory clearance of the stock accumulated in Q3 — Q4 sales volumes will be substantially higher than Q3, with minimal pricing improvement.

  10. 10. Pellet volume guidance and buyer mix

    Suraj Khan, SKP Securities

    Question. With coking coal prices down, is the demand for high-grade pellets that save coking coal cost lower, which could explain weaker pellet sales? What is capacity utilisation guidance for FY26 and FY27, what is the per-product margin, and who are the top 3 pellet buyers?

    Answer, Abhishek Agarwal, Executive Director. 90–95% of GPIL pellets go to coal-based DRI, not blast furnaces — coking coal price does not directly affect demand. Pellet pricing remains based on low-alumina and low-fines quality premium. FY26 pellet volume guidance: 2.4–2.5 MT from existing plant + 0.5–0.6 MT from new plant = 3–3.25 MT total. FY27: full 4–4.5 MT. Per-product margin: pellet ~Rs 4,000/ton at current Rs 10,000/ton ASP and Rs 6,000/ton cost (ex-works); sponge-to-finished product adds Rs 5,000–7,000/ton profit. Top 3 pellet buyers: Prakash Industries, Real Ispat Group, and Kanukripa Group.

  11. 11. Natural gas switch and CBAM readiness

    Rakesh Roy, Boring AMC

    Question. Is the new pellet plant fuel mix shifting to natural gas via the GAIL MoU, and how much margin improvement can be expected from the gas switch?

    Answer, Abhishek Agarwal, Executive Director. GPIL has signed an MoU with GAIL. The current 2.7 MT plant runs on producer gas; the new pellet plant will run on natural gas. All 3 pellet plants may eventually switch depending on commercials. There is no commercial margin benefit expected because natural gas is imported and logistically expensive at Raipur. The reason for switching is CBAM compliance from January 2026 to enable exports to Europe.

  12. 12. High-grade vs commercial grade mix

    Yogansh Jeswani, Mittal Analytics

    Question. What is the current contribution from high-grade pellets and how will the new beneficiation and pellet capacity reshape this mix?

    Answer, Abhishek Agarwal, Executive Director. Today, 65% of production is high grade and 35% commercial grade. Once the new capacity comes online, the mix will shift to ~80% high grade and ~20% commercial. High-grade pellets can be sold to blast furnaces like JSPL or Tata, exported, or sold domestically depending on where maximum value is realised. Management is open to all three options.

  13. 13. Plant shutdown schedule

    Manav Gogia, YES Securities Limited

    Question. Did the pellet plant see additional maintenance shutdowns in Q3 beyond the planned Q2 shutdown?

    Answer, Abhishek Agarwal, Executive Director. Apart from the ~25–30 day annual shutdown during monsoon, there are smaller 4–5 day shutdowns for routine maintenance. These do not impact annual volumes; FY25 guidance is on track.

  14. 14. External iron ore purchase run rate

    Siddharth Gadekar, Equirus Securities

    Question. How much external iron ore (fines) has GPIL purchased in 9M FY25 and what is the annual run rate? Will this go to zero once mining expansion ramps up?

    Answer, Abhishek Agarwal, Executive Director. Currently mining provides ~70–75% of requirement; about 6 lakh tons are purchased from the market annually (around 50,000 tons in 9M FY25 referenced). Once the expanded mining is at full capacity, all purchases — both the current market purchases and the additional requirement for the larger pellet plant — will become 100% captive.

  15. 15. Beneficiation plant yield

    Divya Agarwal, Ficom Family Office

    Question. What is the yield on the beneficiation plant?

    Answer, Abhishek Agarwal, Executive Director. BMQ (low-grade banded magnetite quartz) yield is ~50%; higher-grade iron ore (60–61 Fe) processed at the plant yields ~80–85% on an annual basis to maintain pellet quality.

  16. 16. Integrated production process

    Chirag, Individual Investor

    Question. Can you describe the integrated production process from iron ore mining to pellets, sponge iron, and downstream? Given that 0.5 MT integrated steel capacity exists, how do total MS round plus HB wire volumes exceed 1 MT?

    Answer, Abhishek Agarwal, Executive Director. Process flow: mining → pellets → DRI → sponge iron → steelmaking in furnaces (with scrap) → billets hot-charged to rolling mill → wire rods and structures → HB wires from wire rods. Pellet excess is merchant-sold. On volumes, the 0.5 MT crude steel produces ~0.20–0.25 MT wire rods and ~0.20–0.25 MT structures. Once the RR ISPAT mill is fully operational, the split will move to 50% wire rods and 50% structures. The reference to >1 MT combined is likely a mathematical error on the part of the investor; the 0.5 MT crude steel capacity cannot produce 1 MT of finished products.

What was said

Topic by topic, in the order it was spoken

Strategic and project updates · Sanjay Bothra (CFO)

  • Ari Dongri mining expansion from 2.35 MT to 6 MT expected to be approved by Q1 FY26.
  • Boria Tibu iron ore captive mines (0.7 MTPA) restarted; 0.6 MT beneficiation commissioned at Ari Dongri out of planned 6 MT.
  • Pellet plant capacity expansion from 2.7 MT to 4.7 MT to be commissioned by Q2 FY26.
  • Greenfield 2 MT integrated steel plant project dropped; exploring smaller alternative with lower capex.
  • OPVC pipe manufacturing plan dropped owing to changed market scenario.
  • 70 MW solar for pellet expansion plus 25 MW solar for mining beneficiation decided.
  • GAIL MoU signed for 7-year natural gas supply to upcoming pellet plant; eligible to supply blades for PGCIL transmission projects.

Operational performance vs FY25 guidance · Sanjay Bothra (CFO)

  • FY25 production guidance achievement: iron ore mining 69%, pellets 73%, sponge iron 84%, ferro alloys 96%.
  • Q3 FY25 pellet sales declined YoY due to export consignment shifting to Q4 FY25.
  • Sponge iron, steel billets and MS round sales fell YoY due to higher HB wire production mix.
  • Pellet realisation up ~2% on 9M basis to Rs 10,387/ton; other product realisations down 3–8%.
  • Sales of HB wires and ferro alloys rose sharply on both QoQ and 9M basis.

Financial performance · Sanjay Bothra (CFO)

  • 9M FY25 revenue flat YoY at Rs 3,908 cr; EBITDA and PAT down on lower realisations.
  • EBITDA margin held at 22% and PAT margin at 15% despite realisation pressure.
  • Balance sheet remains healthy with net cash position of Rs 725 cr.
  • Higher pellet inventory (~53,000 tons) in Q3 was a one-off driver of weaker QoQ print.

Market outlook · Sanjay Bothra (CFO)

  • Global iron ore market in 2025 characterised by anticipated price decline, increased production and evolving demand patterns in China.
  • US-China trade tariffs and counter-measures create uncertainty for major exporters like Australia.
  • India steel demand projected to grow 8–9% in 2025 led by housing and infrastructure.
  • Domestic industry faces challenge from rising imports; potential safeguard duties and strategic investment under consideration.
  • Pellet pricing to remain supported by domestic iron ore shortage and gap between domestic and international prices.

In their words

The capex we envisage initially, we got it wrong. So usually what happens, we thought 60% is equipment cost and 40% will be the infra cost. But what has happened is it is opposite. So 40% is your equipment cost 60% is your infra cost, so the entire capex which is about INR5,000 crores to INR6,000 crores 2 million plant will probably cross INR8,000 crores. So, with so much of capital investment where we would have gone to the bank on a long-term basis to keep the project running on time, we don't want to go back into the same debt cycle, which we had entered last 10 years back.
Abhishek Agarwal (Executive Director, GPIL)
FY27, there will be a substantial jump because the mining will be at full capacity and the new pellet plant will get full capacity. For current market scenario, you can easily assume an additional EBITDA of close to INR600 crores from any pellet plant.
Abhishek Agarwal (Executive Director, GPIL)
It was a one-off situation where prices were a little corrected, plus we had a higher inventory than we maintained. So all these factors impacted the EBITDA for Q3. But I'm confident going forward, in Q4, you will see much better results compared to Q3.
Abhishek Agarwal (Executive Director, GPIL)

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Thu 13 Feb 2025₹173.23−1.34%−0.06%
5 sessions Wed 19 Feb 2025₹175.14−0.26%−0.49%
20 sessions Thu 13 Mar 2025₹172.83−1.57%−2.81%

From the close of Wed 12 Feb 2025, ₹175.59: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.