Godawari Pow & Isp Q1 FY27 earnings call
In brief
GPIL puts 1mt steel plant on hold, shifts CRM to Maharashtra for Dec '27 commissioning; FY27 guidance intact despite pellet plant shutdown.
- Management's tone
- Mixed
- What was said
- Even-handed
- Guidance
- Guidance cut
- Analyst pushback
- Low
- Stock, next session
- −1.44% (Nifty 50 +0.05%)
- 1mt steel plant kept on hold due to water approval delays; CRM complex relocated to Maharashtra with commissioning targeted Dec '27 at INR1,100 cr capex.
- 4.7mt pellet capacity at 77% utilization in Q1; one pellet plant shut in July as market iron ore + 40-45% higher gas prices made operations unviable.
- Q1 revenue ₹1,750 cr (+32% YoY), EBITDA ₹334 cr (margin 19.1%), PAT ₹222 cr (+2.7% YoY); margin pressured by higher coal and market iron ore costs.
- Ari Dongri mine ramp-up from Q3 after tree-cutting clearance and beneficiation plant commissioning; full capacity targeted end Q4 FY27/early Q1 FY28.
- BESS 20GW Phase-1 on track for Q1 FY28 commissioning; INR501 cr capex incurred, soil testing done, first container roll-out targeted Q1 FY28.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q1 FY27
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹1,750 cr | +32.3% | +8.7% | |
| EBITDA (excl. other income) | ₹334 cr | +3.0% | −20.7% | 19.1% (24.5% a year ago) |
| Net profit | ₹222 cr | +2.7% | −20.8% | 12.7% (16.3% a year ago) |
| EPS (₹) | ₹3.59 | +2.0% | −21.3% |
From the company's filed results for the quarter ended 30 Jun 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
What moved the numbers, as management explained it
- Higher iron ore market procurement (~75% of input cost increase) due to lower captive mining volume from dumping space constraints on government land; mining cost INR3,000-3,500/ton vs target <INR2,700/ton by FY28.
- Imported coal prices up ~25% to ~INR13,000/ton post West Asia crisis from INR10,500 in Q4/early Q1; ~25% of input cost increase; expected to stay elevated in Q2.
- Natural gas prices up 40-45% per new PNGRB guidelines; combined with elevated market iron ore costs, led to shutdown of one of three pellet plants since July.
- YoY production growth across most segments (sponge iron, billet, rolled); 4.7mt new pellet plant operating at full capacity drove higher pellet sales; revenue +32% YoY.
- Pellet plant shutdown since July (~45-50 days) is transitory and likely to resume in September; FY27 pellet production guidance slightly below original 4mt. (one-off)
The numbers management led with
- Iron ore mining volume guidance FY27: 3.4 million tons (unchanged)
- CRM complex capex revision: INR1,100 crores (up from INR950 crores)
- BESS 20 GWh project capex incurred: INR501 crores
- Total capex FY27+FY28: Approximately INR2,000 crores (funded via internal accruals)
- CRM margin guidance (with Maharashtra incentives): 10-11% (vs 7-8% standalone)
Guidance
Guidance on this call
| What | For | What management said |
|---|---|---|
| Pellet production from FY28 (Pellets) | FY28 | Pellet production at full capacity ~4.5 million tons from FY28 |
| Total capex | FY27-FY28 | Total capex ~INR2,000 crores for remaining FY27 and entire FY28 |
| CRM Complex capex | — | CRM planned capex of INR1,100 crores |
| CRM Complex margin | — | CRM margin to touch 10-11% with Maharashtra incentives |
| Iron ore mining cost | FY28 | Mining cost target below INR2,700/ton from FY28 |
| CRM Complex commissioning | Q3 FY28 | CRM Complex targeted for commissioning by December '27 (Q3 FY28) |
| CRM Complex construction start | Q3 FY27 | CRM construction activities expected to start from October 2026 |
| CRM Complex land allotment | — | Land allotment approval expected by end of August '26 |
| BESS Phase-1 commissioning | Q1 FY28 | BESS project scheduled for commissioning in Q1 FY28 |
| Ari Dongri mine full capacity (Iron ore mining) | Q4 FY27 | Full mining capacity targeted end Q4 FY27 or early Q1 FY28 |
| Beneficiation plant commissioning (Iron ore mining) | Q3 FY27 | Beneficiation plant targeted for commissioning Q3 FY27 |
| 100MW solar commissioning | Q2 FY27 | 100MW solar project targeted for commissioning by September '26 |
| Pellet prices longer term (Pellets) | — | Pellet prices to hover between INR9,000 to INR10,000 ex-Raipur longer term |
| Pellet Q2 FY27 production (Pellets) | Q2 FY27 | Q2 FY27 pellet production ~500 kt if plant remains shut for entire quarter |
| FY27 pellet production (Pellets) | FY27 | FY27 pellet production expected slightly below 4mt due to plant shutdown |
What changed since the Wed 20 May 2026 call
| What | On the Wed 20 May 2026 call | On this call |
|---|---|---|
| 1mt steel plant construction (delayed) | Construction begins October 2026 (Q3 FY27) | keep the proposed 1 million ton integrated steel project in abeyance due to on-ground challenges and delays in approval, especially the approval for water allocation |
| CRM Complex commissioning (delayed) | First line by end Q4 FY27 / early Q1 FY28 | project is now targeted to be, commissioned by December '27 |
| CRM Complex location (restated) | Chhattisgarh (CRM Complex on same land as steel plant) | relocated to Maharashtra, near Sambhaji Nagar (AURIC industrial belt) |
| Ari Dongri mine full capacity (delayed) | End of Q3 / early Q4 FY27 | full ramp-up capacity will happen end of Q4 and early of Q1 next financial year |
| FY27 pellet production (cut) | Pellet production: 4 million tons (FY27) | you can expect a slightly lower guidance for the entire year since one of our pellet plants is already shut from last almost 45 days now |
| 150 MW solar project (delayed) | Expand captive solar to 540MW (priority); CRM Complex commissioning Q4 FY26/early Q1 FY27 | The proposed 150 megawatt solar project has been kept in abeyance due to relocation of CRM project to Maharashtra |
| Vision 2031 revenue (restated) | ~INR 24,000 crore topline (BESS 16 GW + steel + CRM); INR 3,000 crore PAT (by 2031) | now we've removed the steel part from that investor presentation |
| FY27 capex envelope (restated) | FY27 capex ~INR 1,500-2,000 crore; FY28-29 ~INR 3,000 crore/year (steel plant) | we envisage a CapEx of close to about INR2,000 crores for remaining FY'27 and entire FY'28 |
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| FY26 EBITDA margin | FY26 | at least 20% (on the Q4 FY25 call) | 22.9%, within the range |
| FY26 revenue growth | FY26 | 5–7% (on the Q4 FY25 call) | 0.1%, below the range |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
Iron Ore Mining
Q1 mining volume declined due to space constraints for dumping overburden; tree-cutting approval for additional government land pending. Ramp-up targeted from Q3 FY27 after beneficiation plant commissioning.
3.4mt net usable iron ore for pellet plant (FY27 guidance on track) · Mining cost INR3,000-3,500/ton in Q1 · Capex incurred INR218 cr in beneficiation plant till June '26
Outlook: Mining cost target below INR2,700/ton from FY28; 100% captive by FY28 vs ~25-30% market purchase in Q3
Pellets
4.7mt pellet capacity operated at 77% utilization in Q1; one of three plants shut since July as market iron ore purchase plus 40-45% higher gas prices made operations commercially unviable.
Pellet prices ranged INR8,700-10,000/ton in Q1 · FY27 pellet guidance 4mt (now slightly lower)
Outlook: FY27 production slightly below 4mt; Q2 pellet production ~500 kt if plant remains shut; ramp-up to full capacity from FY28 (~4.5mt)
BESS
20GW Phase-1 BESS project progressing on track; soil testing completed, compound wall construction underway, key supply agreements finalized for cells and raw materials.
INR501 cr capex incurred to date · 20GW Phase-1 capacity
Outlook: First container roll-out Q1 FY28; machine deliveries from December '26; targeting 90% capacity in 2-3 years
CRM Complex
0.7mt CRM complex relocated from Chhattisgarh to Maharashtra (Sambhaji Nagar) after steel plant kept on hold; capex revised to INR1,100 cr (from INR950 cr) for land + standalone infrastructure.
INR1,100 cr capex (vs INR950 cr earlier) · INR550 cr debt + internal accruals funding · INR45-50 cr land cost on 35 acres
Outlook: Land allotment approval expected by end August '26; construction from October '26; commissioning December '27 (Q3 FY28); EBITDA margin 10-11% with Maharashtra incentives
Steel Plant (1mt)
1mt blast furnace integrated steel plant kept in abeyance due to water allocation approval delays and final EC/consent to establish pending; treated as optional for medium-term.
INR7,000 cr capex (originally planned, now on hold)
Outlook: On hold pending water allocation approval; treated as optional medium-term growth; no debt requirement for current projects
Solar/Captive Power
25MW solar commissioned May 2026; 100MW under construction for September '26 commissioning; 150MW project kept in abeyance due to CRM relocation and solar land delay.
165MW to 290MW solar capacity expansion · 25MW commissioned May '26 · 100MW under construction
Outlook: 100MW solar commissioning by September '26; 45MW storage targeted Q3 '26 (corrected from Q3 '27); 150MW on hold pending CRM relocation
Jammu Pigments
Partial stake worth INR25 cr sold to promoters; strategy under evaluation given operational complexity at Jammu and other priorities in Chhattisgarh and Maharashtra.
INR25 cr worth of Jammu Pigments stake sold
Outlook: Strategy under discussion; could exit further or increase stake; no timeline set
Balance sheet, capex and funding
- Cash position healthy; sufficient free cash flows to fund all current projects; no debt required for steel plant which is on hold.
- CRISIL reaffirmed long-term credit rating at AA- Stable.
- Capex incurred till Q1 FY27: INR218 cr on Ari Dongri beneficiation plant; INR501 cr cumulative on BESS Phase-1; INR80 cr on CRM (out of INR1,100 cr planned).
- Total capex ~INR2,000 cr planned for remaining FY27 + entire FY28 (BESS, CRM, mining, solar); CRM funded via INR550 cr debt + internal accruals.
- Steel plant capex INR7,000 cr previously planned now on hold; FY27 capex guide INR1,500-2,000 cr under revision given steel plant removal.
The industry, as management sees it
India iron ore production seen rising ~8% to 340-345mt in FY27 with captive mines driving supply; pellet output provisionally 120mt in FY26 (vs 109mt FY25). Industry pellet utilisation remains constrained at ~65% on weak exports, limited high-grade availability, and margin pressure. Iron ore prices stable around INR5,500/t ex-mine and INR9,000-11,000/t for pellets globally. India's steel demand outlook strong on infra, housing, railway and manufacturing investments. Simandou project ramp seen as soft downside risk to global iron ore but not expected to push prices below USD90/t in the near term.
Risks management named
- Government approval delays (water allocation, dumping land tree-cutting) flagged as outside management control
- Imported coal cost up ~25% to INR13,000/t on West Asia crisis; Q2 to remain elevated
- Natural gas prices up 40-45% post-PNGRB guidelines, making merchant-iron-ore pellet production commercially unviable
- Pellet prices touched COVID-era low of INR8,700-9,000 in early-July FY27; commodity cyclicality
- Boria Tibbu expansion (to 4mt) deferred to FY31 due to lower ore grade (~45-50%) and higher tailings
Q&A
Q&A focused on three themes: (1) the rationale and impact of parking the 1mt integrated steel project on hold and relocating CRM to Maharashtra, with management repeatedly attributing the steel plant deferral to Chhattisgarh government delays; (2) the pellet plant economics, where management openly conceded Q2 will be soft (~500kt) due to gas price spike and weak pellet pricing, with FY27 guidance likely trimmed; (3) cost trajectory and capex outlook, with management articulating a clear roadmap to bring mining cost below INR2,700/t by FY28 via beneficiation and EV deployment, and reaffirming no incremental debt. Pushback was limited — most analyst questions were informational rather than challenging, though several follow-ups probed the credibility of government approval timelines.
Not answered directly
- FY27 pellet production guidance — no formal revision issued, only directional
- Cash deployment strategy post steel-plant deferral — explicitly deferred until projects complete
- Vision 2030 numbers — rebased to exclude steel plant but exact re-quantification not provided
- Three-year capex beyond FY28 — no projection available
Asked for a number, answered without one
- Combined EBITDA/ton benefit post mining ramp-up + beneficiation + pellets: INR100 saving in iron ore = INR45-50 cr EBITDA on 5-6 mt production. Target mining cost <INR2,700/ton by FY28. Pellet capacity 4.5mt from FY28.
- FY27 pellet production guidance: Although we haven't revised, we are still evaluating but you can expect volumes to be slightly on the lower side. Will inform investors once internal clarity is reached.
- FY27/FY28 capex breakdown post steel plant removal: Referred to investor presentation. Total capex ~INR2,000 crores for remaining FY27 and entire FY28. CRM capex INR1,100 cr (INR550 cr debt + internal accruals); ~INR1,000 cr remaining.
- Jammu Pigments stake decision timeline: No timelines. We are still in discussion as to how to go forward. Jammu Pigments stake partially sold worth INR25 cr; could exit further or increase stake.
Every question, with its answer
1. Steel plant status
Manav Gogia, YES Securities Limited
Question. On the 1mt integrated steel project delay: what specific milestones need to be satisfied before the board revives it, and should investors still bake it into medium-term expectations or treat it as optional?
Answer, Abhishek Agrawal, Executive Director. The key milestone was water allocation — only LOI received so far, with the confirmation letter stuck for 6-8 months, blocking the 9.4 MCM allocation. Until approvals come through there is no visibility, so investors should treat the steel plant as an optional medium-term growth project. Vision 2030 numbers (4x revenue / 3x EBITDA & PAT) have been rebased to exclude the steel plant and now reflect CRM commissioning in Dec-2027 and the BESS project.
Follow-up. Does the steel plant deferral impact the CRM or BESS projects, and are there cost benefits from moving the CRM closer to the BESS facility in Maharashtra?
Answer. CRM was originally on the same land as the steel plant; with water stuck, CRM is being moved to AURIC industrial belt in Maharashtra, which is a plug-and-play model. CRM faces ~6 month delay but stays on track. Steel plant remains on hold. CRM benefits from local consumption (auto hub), Maharashtra industrial policy incentives (SGST etc.), and access to HR coil suppliers like JSW Dolvi and ArcelorMittal Gujarat.
2. Iron ore mining guidance
Aman Kothari, Aequitas Investment
Question. Is the 3.4mt iron ore mining guidance for FY27 inclusive of the upcoming beneficiation plant? Will the balance be procured from the market?
Answer, Abhishek Agrawal, Executive Director. The 3.4mt guidance is for usable ore feeding the pellet plant and remains firmly on track — no revision. Beneficiation is on the input/processing side, not on output volume. Since one 2mt pellet plant is shut, market purchase volumes will be slightly lower than earlier indicated.
Follow-up. How big is the gas supply issue for the pellet plant shutdown, and when could it normalise?
Answer. Gas procurement is at 100%, but per new PNGRB guidelines, gas purchase price is up 40-45%. Combined with market iron ore purchases, pellet operations become commercially unviable at INR8,700-9,000 pellet prices (touched COVID lows in early July).
3. Iron ore pricing outlook
Aman Kothari, Aequitas Investment
Question. Where do you see iron ore pricing in the next 1-2 years given Simandou ramp-up, and will beneficiation allow commanding a better quality premium?
Answer, Abhishek Agrawal, Executive Director. Iron ore likely to hover USD90-100/t as Simandou ramp-up takes time and Indian port-based plants continue importing. Beneficiation will mainly reduce mining cost (saves ~INR1,000/t by avoiding factory-complex transportation) rather than fetch a quality premium — pellet prices are driven by steel sentiment, not iron ore fines prices.
Follow-up. Do you run sensitivity on iron ore pricing — what is the EBITDA impact of a 5-10% fall?
Answer. A INR100 fall in pellet realisations costs ~INR40cr/year on 4mt pellet output. Pellet is the bigger driver; iron ore cost matters less. Recent ~10% rebound in domestic steel demand has lifted pellet prices back to INR10,000/t.
4. FY28 cost benefits
Yogansh, Mittal Analytics
Question. Once pellet, beneficiation and mining ramp all come into play (FY28), what is the quantified EBITDA benefit and EBITDA/ton improvement?
Answer, Abhishek Agrawal, Executive Director. Current mining cost INR3,000-3,500/t; target below INR2,700/t from FY28 via beneficiation and EV deployment. INR100 saving on iron ore = INR45-50cr EBITDA on 5-6mt production. Pellet production to run at full 4.5mt capacity from FY28, driving further profitability uplift.
Follow-up. Can surplus iron ore be sold externally given the 50% MMDR Act allowance, and what is the iron ore to pellet conversion ratio?
Answer. MMDR Act allows 50% market sale of iron ore at 150% additional royalty only if 100% of pellet plant is fed captive first. GPIL has no intention of selling iron ore externally — wants 100% captive to extend mine life. Conversion ratio is 1,500-1,800 kg (units used verbatim: 'INR1,500 to INR1,800 on annual basis'). Delta in pellet (~INR4) versus iron ore sale (loses INR1,000 to royalty) makes pellet more attractive commercially.
5. Mining land approval
Sunil Jain, Nirmal Bang Securities
Question. On Ari Dongri mining: what is the nature of the pending government approval, and is there risk of further delay?
Answer, Abhishek Agrawal, Executive Director. Pending approval is entry and tree-cutting permission on government (revenue) land with plantation, involving forest department process. Application is in; approval expected by end-September, after which dumping can start from October. Ramp-up begins October with full capacity by end-Q4 FY27 / early Q1 FY28.
Follow-up. Can production on private land scale independently, and is there scope for higher CRM/BESS margins from the Maharashtra shift?
Answer. Clarified by Dinesh Gandhi: the additional land is only for dumping ground (separate from mining area); mining area land is fully available. Production is capped by overburden dumping space. On Maharashtra shift, CRM margins seen improving another 2-3% from incentives (state policy), taking margin from 7-8% standalone to 10-11%. BESS project was always in Maharashtra — no change.
6. Mining cost and pellet sales
Tanuj, SKP Securities
Question. Iron ore mining cost is up ~10% — is it purely fuel-driven? And why did pellet sales volumes rise sharply when peers also ramped up?
Answer, Abhishek Agrawal, Executive Director. Iron ore cost rise is mainly due to higher market purchase, not fuel. Mining cost up because of lower production levels (operating cost de-leverage) plus diesel price impact. Once mines ramp up, cost will normalise. Pellet sales rose because new 4.7mt plant ran at full capacity in Q1 with all three plants operating, while captive consumption for DRI stayed flat — incremental pellet flowed to market.
Follow-up. Post ISP deferral, is there any plan to use captive pellets for sponge iron expansion or alternative capex pipeline?
Answer. No plans to expand DRI capacity — fresh land and EC would be a long-drawn process. Incremental pellets will continue to be sold in merchant market; GPIL exported two vessels in end-Q1/early-Q2 before shutting one plant. There is strong demand for high-grade pellets both domestically and internationally.
7. Mining approval timeline and BESS update
Vinit Thakur, Plus91 Asset Management
Question. By when do you expect approval for the dumping area expansion, and what is the latest on the BESS project?
Answer, Abhishek Agrawal, Executive Director. Pending approvals expected by end-Q2; mining production improvement from Q3, full capacity from FY28. BESS project on track — groundwork underway, machine delivery starts December, first container rollout targeted Q1 FY28.
Follow-up. Iron ore and pellet realisations peaked in Q4/start of Q1 — softer now. Will they trend lower further, and is pellet export a viable option?
Answer. Long-term pellet realisations expected INR9,000-10,000/t; current prices already back to INR10,000/t after 10% rebound. Cyclicality is inherent. Two export vessels shipped in June-July at ~INR9,000 ex-plant (at par with domestic). Exports remain an open lever depending on domestic pricing.
8. Jammu Pigments divestment
Kartik Gada, Multipl Wealth Management
Question. Why was stake in Jammu Pigments sold down this quarter, and what is the long-term plan?
Answer, Dinesh Gandhi, Executive Director. Only ~INR25cr worth of Jammu Pigments stock sold. Promoters' family (daughter, son-in-law) have now joined the business, addressing the earlier succession concern. Strategically, GPIL's focus is on Chhattisgarh and the new Maharashtra CRM — operating Jammu and Kota locations is becoming difficult. Final call (hold, increase, or exit) is still under discussion with no fixed timelines.
Partly answered.
9. Boria Tibbu expansion
Aman Kothari, Aequitas Investment
Question. What is the update on Boria Tibbu TOFR filing that was expected in Q1, and is the beneficiation plant also being scaled to 4mt?
Answer, Abhishek Agrawal, Executive Director. Boria Tibbu expansion plans on track — document preparation in progress, TOFR to be filed after finalisation. Current capacity 0.2-0.3mt ramping to 0.7mt from FY28, with expansion to 4mt targeted by FY31. In-mine beneficiation also planned — at 40% yield on lower-grade ore (45-50% Fe), output will be 1.5-2mt usable concentrate for pellet feed.
Follow-up. On BESS, are commercial arrangements and customer discussions in place, and why did galvanised volumes fall?
Answer. Domestic EMS and PCS partners already tied up to meet 20% Make-in-India requirement. From August, BESS containers are being quoted in the market with a back-to-back guarantee structure via EPC developers participating in tenders. Galvanised volume decline is purely seasonal — monsoon delays project dispatches; volumes should normalise post-monsoon.
10. FY27 pellet guidance
Nidhi, BigMint
Question. With one pellet plant shut, should investors expect a change to the FY27 pellet production guidance of 4.0mt?
Answer, Abhishek Agrawal, Executive Director. Guidance has not been formally revised yet, but volumes will be slightly lower than 4.0mt given the 45-day shutdown. Management will share revised numbers once full internal clarity is reached.
Follow-up. What is the pellet market outlook in FY27 on demand, pricing and margin given rising domestic supply and subdued export demand?
Answer. Pellet prices touched lows two months ago but have rebounded ~10% on steel demand revival. Longer-term, pellet prices expected INR9,000-10,000 ex-Raipur; pricing outlook broadly stable.
Partly answered.
11. Raw material cost breakdown
Rohan Mehta, StartEazy
Question. Cost of materials up ~40% — can you segregate the iron ore vs coal impact given procurement is typically a quarter lagged?
Answer, Abhishek Agrawal, Executive Director. Iron ore contributes ~75% of cost increase (market procurement vs captive); imported coal ~25%. Imported coal cost was INR10,500/t in Q4/early-Q1, now at INR13,000/t — ~25% rise from West Asia crisis. Q2 cost impact will continue to be higher; dollar, freight and Middle East tensions still elevated.
Follow-up. When can gas normalise post force majeure, what pellet price makes third plant viable, and is incremental debt needed if steel plant is dropped?
Answer. No clarity on gas — GAIL has no guidelines given volatile situation. Restart of third plant being evaluated with suppliers; August likely shut, possible September restart. Since steel plant is on hold, no incremental debt needed for current projects; sufficient free cash flows to fund entire capex pipeline.
12. CRM capex revision
Swati Agrawal, Chhatisgarh Investments
Question. What is the revised budgeted capex for the CRM rolling mill project, and what is the Maharashtra land cost?
Answer, Abhishek Agrawal, Executive Director. CRM capex revised to INR1,100cr from INR950cr — a 15-20% rise driven by one-time Maharashtra land and infrastructure costs (transmission lines etc.) since CRM is now standalone without common steel plant infrastructure. Land cost ~INR50cr for ~35 acres. Commissioning December 2027 (Q3 FY28).
13. Cash deployment plan
Nitin Shah, Independent investor
Question. With healthy cash on books, ~INR1,000-1,200cr annual generation and steel plant shelved, what are the plans for cash utilisation?
Answer, Dinesh Gandhi, Executive Director. Management will outline cash utilisation plans once the CRM and BESS capex cycles are completed and there is full clarity on the integrated steel plant — no immediate decision. Focus is on funding the current project pipeline first.
Not answered directly.
14. FY27/28 capex and Q2 pellet
Manav Gogia, YES Securities Limited
Question. Given steel capex is dropped, how should capex be modelled for FY27 and FY28, and is ~650-700kt the right pellet production run-rate for Q2?
Answer, Dinesh Gandhi, Executive Director. Detailed capex numbers are disclosed in the investor presentation — to be referred to there. On Q2 pellet production, with the third plant potentially shut the entire quarter, run-rate will be ~500kt rather than 675-700kt.
Partly answered.
15. Capex outlook 3 years
Vinit Thakur, Plus91 Asset Management
Question. With CRM and BESS funded internally, what is the total capex outlook for the next three years (excluding ISP)?
Answer, Abhishek Agrawal, Executive Director. CRM capex INR1,100cr with INR80cr already spent → ~INR1,000cr remaining. BESS capex ~INR500cr already spent, with INR700-800cr remaining. Mining capex makes up the balance. Total capex for remaining FY27 plus full FY28 is ~INR2,000cr. No FY29 projection available currently.
What was said
Topic by topic, in the order it was spoken
Q1 FY27 Performance Overview · Dinesh Gandhi (Executive Director)
- Resilient revenue growth with YoY and sequential improvement; healthy sales volume and improved realisation across key products
- Sequential profitability softened on elevated input costs from higher market iron ore procurement and West Asia-driven coal price spike
- EBITDA margin 19.1% and PAT margin 12.7% in Q1; margin recovery expected from Q4 FY27 post-beneficiation plant commissioning
- Q1 achieved 16-29% of full-year guidance across product segments, keeping FY27 guidance on track
- Value-added products (sponge iron, billet, rolled) posted healthy YoY growth; iron ore mining and galvanised volumes declined sequentially
Iron Ore Mining and Beneficiation · Dinesh Gandhi (Executive Director)
- Iron ore mining volume constrained by space for overburden dumping on allotted government land; tree-cutting approval pending
- Private land dumping area already operational; government land approval expected by end-September 2026
- Mining ramp-up expected from Q3 FY27; full capacity by Q4 FY27 / early Q1 FY28
- Beneficiation plant commissioning targeted Q3 FY27; capex of INR218cr incurred till June-2026
- Target to reduce mining cost from INR3,000-3,500/t to below INR2,700/t from FY28
Pellet Operations and Pricing · Dinesh Gandhi (Executive Director)
- 4.7mt expanded pellet capacity operated at 77% utilisation in Q1 FY27; ramp to 80-85% targeted for FY27
- 2mt pellet plant shut from July on commercially unviable economics (high gas, weak pricing)
- Pellet prices touched COVID-era low of INR8,700-9,000 in early July; recovered ~10% to INR10,000
- FY27 pellet guidance of 4.0mt likely to be trimmed given ~45 days of lost production
- Pellet prices expected to range INR9,000-10,000 ex-Raipur in the longer term
Steel Plant Deferral and CRM Relocation · Dinesh Gandhi (Executive Director)
- 1mt integrated steel project placed in abeyance due to non-availability of water allocation (9.4 MCM) from Chhattisgarh
- Project kept on hold till water and EC approvals secured; to be treated as optional medium-term growth
- 0.7mt CRM complex relocated to AURIC industrial belt, Sambhaji Nagar, Maharashtra to access state incentives and proximity to auto demand
- CRM capex revised to INR1,100cr (from INR900-950cr); INR550cr debt + balance internal accruals
- Targeted commissioning Dec-2027 (Q3 FY28); construction to start October-2026; land allotment expected by end-August-2026
- Maharashtra incentives expected to lift CRM margin to 10-11% from 7-8% standalone
BESS, Solar and Other Growth Projects · Dinesh Gandhi (Executive Director)
- 20GWh battery energy storage system (BESS) project on track for Q1 FY28 commissioning; INR501cr capex incurred
- Solar capacity expansion 165MW → 290MW: 25MW commissioned May-2026, 100MW targeted Sep-2026, 150MW kept in abeyance
- 45MW-based solar storage targeted for commissioning Q3 FY27
- Domestic EMS and PCS partners tied up to comply with 20% Make-in-India mandate; BESS container quoting starts August
- Boria Tibbu expansion to 4mt deferred to FY31 with in-mine beneficiation; current capacity 0.2-0.3mt to ramp to 0.7mt from FY28
ESG, Carbon and Cost Initiatives · Dinesh Gandhi (Executive Director)
- 6.9MW WRHB plant commissioned taking total to 49MW; 5 TPD carbon capture project with IIT Mumbai targeted for end-FY27
- CO2 emission intensity 3.180 t/t steel (CBAM) improved 1.9% QoQ and 4.2% YoY; 2.485 t/t (WSA) stable vs 2.492 target
- EV mining fleet expanded to 15 dumpers, 24 loaders, 15 excavators; cuts operating cost ~75% and CO2 ~88%
- CRISIL reaffirmed AA-/Stable; added to Burgundy Private Hurun India 500 list in 2025
Market Outlook and Iron Ore Pricing · Dinesh Gandhi (Executive Director)
- India iron ore production expected to rise ~8% to 340-345mt in FY27 led by captive mines; pellet output at 120mt in FY26
- Iron ore prices stable at USD95-105/t globally; INR5,500/t ex-mine domestic; pellet INR9,000-11,000/t
- Industry pellet utilisation at ~65% on weak exports and limited high-grade availability
- Simandou ramp viewed as soft downside; Indian demand offsets; prices seen stable USD90-100/t
- Indian steel demand supportive on infra, housing, railway, manufacturing investments
In their words
It's very unfortunate, but it's really not in our hands, to be honest.
Yes, exactly. We should touch 10%-11% with incentives.
A INR100 down in iron ore pellet will lose INR40 crores in a year, based on 4 million production of iron ore pellet. It's very simple. Iron ore cost still doesn't impact so much in terms of pellet prices. Pellet prices are mainly driven on, you know, the steel sentiment.
To check next time
What management committed to on this call, or the dates they gave.
- Tree-cutting approval for Ari Dongri government dumping land - expected by end September '26; critical for mining ramp-up from October.
- CRM land allotment approval from Maharashtra government - expected by end August '26; critical for construction start from October '26.
- Beneficiation plant commissioning at Ari Dongri - targeted Q3 FY27; needed to enable higher captive iron ore usage and lower mining cost.
- Pellet Q2 FY27 production run rate ~500 kt indicated if plant remains shut for entire quarter; check actual vs guidance.
- BESS Phase-1 progress: machine deliveries to start from December '26; first container roll-out Q1 FY28 commissioning.
- 100MW solar project commissioning - targeted September '26; captive solar to reach 290MW total.
Transcript
Read along with the recording
The whole call, 285 lines from 21 speakers over 1:00:21. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Mon 10 Aug 2026 | ₹237.15 | −1.44% | +0.05% |
| 5 sessions Fri 14 Aug 2026 | ₹235.43 | −2.15% | −0.83% |
| 20 sessions Fri 4 Sept 2026 | ₹240.67 | +0.02% | −2.74% |
From the close of Fri 7 Aug 2026, ₹240.61: the last close before the call, which began at 12:00 IST. Adjusted daily closes; the move includes everything else that happened in those sessions.
Godawari Pow & Isp's other calls
- Q2 FY27Mon 16 Nov 2026Tone: Mixed
- Q4 FY26Wed 20 May 2026Tone: Confident
- Q3 FY26Wed 11 Feb 2026Not read
- Q3 FY26Mon 9 Feb 2026Not read
- Q2 FY26Mon 17 Nov 2025Tone: Confident
- Q1 FY26Wed 6 Aug 2025Tone: Optimistic
- Q4 FY25Wed 21 May 2025Tone: Confident
- Q3 FY25Thu 13 Feb 2025Tone: Cautious
- Q2 FY25Thu 19 Dec 2024Tone: Confident
- Q2 FY25Mon 28 Oct 2024Tone: Mixed
- Q1 FY25Thu 8 Aug 2024Tone: Confident