Jkumar Infr.ltd. Q1 FY26 earnings call
In brief
J.Kumar Q1 FY26 PAT up 19% to ₹103 cr; reaffirms 15-16% revenue growth and EBITDA margin target of 15-16% in 6-8 quarters
- Management's tone
- Confident
- What was said
- Leaned positive
- Guidance
- Guidance held
- Analyst pushback
- Low
- Stock, next session
- +0.40% (Nifty 50 +0.14%)
- Q1 FY26 revenue grew 16% YoY to ₹1,484 cr; EBITDA up 18% to ₹217 cr (margin 14.6%); PAT up 19% to ₹103 cr.
- Net debt is negative ₹159 cr (cash positive) as on June 30, 2025; order book stands at ₹20,946 cr.
- Reaffirmed 15-16% revenue growth and 15-16% EBITDA margin target to be achieved in 6-8 quarters (by FY27).
- Order inflow guidance of ₹5,000-6,000 cr for FY26; ~₹2,000 cr expected in Q2 FY26 alone.
- Capex of ₹450-500 cr additional + ₹100 cr maintenance over next 2 years (FY26-FY27); Q1 FY26 capex already at ₹107 cr.
An AI read of the company's transcript · the filing
The numbers
The quarter, Q1 FY26
| This quarter | A year ago | Last quarter | Margin | |
|---|---|---|---|---|
| Revenue | ₹1,484 cr | +15.8% | −9.1% | |
| EBITDA (excl. other income) | ₹217 cr | +17.8% | −7.7% | 14.6% (14.4% a year ago) |
| Net profit | ₹103 cr | — | — | 7% (0% a year ago) |
| EPS (₹) | ₹13.67 | +19.1% | −9.4% |
From the company's filed results for the quarter ended 30 Jun 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.
What moved the numbers, as management explained it
- Revenue grew 16% YoY to ₹1,484 cr driven by execution from the existing ₹20,946 cr order book across metros, elevated corridors and tunnels.
- EBITDA margin expanded to 14.6% from 14.4% YoY; management attributes this to operational efficiency and leverage from complex projects.
- PAT grew 19% to ₹103 cr on revenue growth, margin expansion and stable finance cost (~2.75% of revenue).
- Net debt remained cash positive at negative ₹159 cr with working capital at 115 days vs 120 days guidance.
The numbers management led with
- Total order book: INR20,946 crores as on 30 June 2025
- Net debt: Negative INR159 crores (net cash positive) as on 30 June 2025
- Bid pipeline: INR30,000 crores across building, elevated corridors, flyover roads, metro and water
- FY26-27 capex plan: INR450-500 crores over two years plus INR100 crores annual maintenance
Guidance
Guidance on this call
| What | For | What management said | Filed |
|---|---|---|---|
| EBITDA margin | FY27 | EBITDA margin to reach 15-16% in 6-8 quarters (by FY27) | — |
| Top line growth | FY26 | Maintain 15-16% top line growth | 0.5%, below the range |
| FY26 order inflow | FY26 | Order inflow target of ₹5,000-6,000 cr for FY26 | — |
| Q2 FY26 order inflow | Q2 FY26 | Q2 FY26 order inflow expected at ~₹2,000 cr | — |
| Order book target | FY26 | Target order book of ₹22,000-23,000 cr by FY26 end | — |
| Capex FY26-FY27 | FY26-FY27 | Capex of ₹550-600 cr over FY26-FY27 (incl. ₹100 cr maintenance + ₹450-500 cr equipment) | — |
| Debt | FY26-FY27 | Total debt expected around ₹750-800 cr for FY26 and FY27 | — |
| Working capital days | FY26 | Maintain working capital at 120-125 days | — |
| Finance cost as % of revenue | FY26 | Finance cost to remain around 2.75% of overall revenue | — |
| Depreciation as % of revenue | FY26 | Depreciation may marginally go up to 3.5% of revenue | — |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
Guided on earlier calls, and what was filed
| What | For | Guided | Filed |
|---|---|---|---|
| FY25 revenue | FY25 | ₹5,600–5,700 cr (on the Q4 FY24 call) | ₹5,693 cr, within the range |
| FY26 top line growth | FY26 | 15% (on the Q4 FY25 call) | 0.5%, below the figure guided |
Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.
The business
By business
Metros
Metros contributed ~40% of Q1 revenue; Metro Line 3 underground (₹6,000 cr) progressing; Line 4 Kasaravadavali to Gaimukh (₹500 cr) ~85% complete; priority commissioning targeted within ~1 year.
Q1 metro share of revenue ~40% · Metro Line 3 underground project ₹6,000 cr · Line 4 (J.Kumar scope) ~85% complete · Underground metro Q1 revenue ₹250 cr
Outlook: Pune Metro bid (₹2,000 cr) opening before August 15; bidding Delhi Metro underground; Thane Metro tenders in process; Line 11 of MMRCL upcoming.
Elevated corridors
Chennai 4-package elevated corridor (₹4,200 cr) progressing with 40% piling complete; biggest casting yard operational; Thane Anand Nagar-Saket (8 km) work started; New Bombay Coastal Road at full speed.
Chennai elevated 4 packages total ₹4,200 cr · Chennai piling 40% complete · Q1 elevated flyover revenue ~₹300 cr
Outlook: Bids being submitted for elevated projects; Lagoon Bridge tender by BMC; MMRDA Line 10, 11, 13 in pipeline.
Tunnels and roads
GMLR progressing with 60% TBM received and 200 tunnel rings cast; Versova-Dahisar coastal road LOI received with designs approved for 40 foundations; Dwarka Expressway nearing completion.
GMLR TBM 60% received · Q1 road tunnel revenue ~₹270 cr
Outlook: Versova-Dahisar physical work starting August 2025; first GMLR TBM expected August, second by January; Dwarka Expressway to complete shortly.
Water infrastructure
Water is a newer vertical for J.Kumar; contributed ₹65 cr to Q1 revenue as the company expands beyond metros and elevated corridors.
Q1 water revenue ₹65 cr
Outlook: Continuing to explore water infrastructure opportunities as part of vertical expansion.
Civil and buildings
NBCC building project (₹300 cr) currently in preparatory phase; other civil building projects contributed ₹270 cr revenue in Q1; legacy slow-moving ₹350 cr project to start by September-October.
NBCC project ₹300 cr · Q1 civil building revenue ~₹270 cr · Other slow-moving project ₹350 cr
Outlook: NBCC project work to start by September/October 2025.
Balance sheet, capex and funding
- Net debt: negative ₹159 cr (cash positive) as on June 30, 2025.
- Total debt guidance: ₹750-800 cr for FY26 and FY27.
- Capex: ₹107 cr already in Q1 FY26; total ₹550-600 cr over FY26-FY27 (₹450-500 cr equipment + ₹100 cr maintenance).
- Working capital at 115 days in Q1 FY26 (target 120-125 days); finance cost ~2.75% of revenue and depreciation ~3.5% of revenue expected for FY26.
- Mobilization advance ₹789 cr, retention money ₹386 cr, unbilled revenue ₹650 cr.
- Raw material inventory ₹315 cr, trade receivable ₹1,697 cr, creditors ₹795 cr.
The industry, as management sees it
Management sees Q1-Q2 as muted due to new government formation and digestion of existing commitments but is constructive that H2 FY26 will see strong order inflow across metros, elevated corridors, road tunnels and water infrastructure as departments float pending tenders; H2 capex execution expected to pick up correspondingly.
Risks management named
- Promoter pledge of ~22% still outstanding; release timeline dependent on bankers
- Versova-Dahisar project has ~30% stretch through mangrove/CRZ areas requiring clearances
- Variation approvals cause periodic payment delays even when regular billing is on time
- NBCC INR300 cr building project not yet in full execution, expected to ramp by Sep-Oct
Q&A
Q&A was friendly and broad, with analysts mostly seeking data points and confirming the H2 order inflow thesis. Management held firm on the EPC-only strategy and refused to engage on BOT in either roads or metros, and the only points of mild pushback were around the modest FY26 order inflow target (Shravan Shah pushing for INR8,000 cr+ vs INR5,000-6,000 cr guided) and the unresolved 22% promoter pledge (no committed timeline). The largest, partially deflected, data request was the outstanding value of the Chennai elevated corridor, which management said it would provide separately.
Not answered directly
- Outstanding value of Chennai elevated corridor
- Promoter pledge release timeline
- Specific FY26 PAT guidance
- MSRDC order book reference
Asked for a number, answered without one
- Line 8 BOT project value: Management said exact figure cannot be mentioned at this stage as contemplation still happening on elevated vs underground split.
- Chennai elevated corridor outstanding order value: Management said they do not have the exact figure handy and will revert separately.
- Promoter pledge release timeline: Management said they are trying to get the pledge released but cannot commit to a timeline as bankers have their own.
- Equity fundraising via QIP: Management said it depends on opportunity and market scenario; no immediate call taken on it.
Every question, with its answer
1. Order pipeline strategy - HAM/BOT
Jainam Jain, ICICI Securities
Question. NHAI has announced a strong road project pipeline of 3.4 GDM, mostly BOT and HAM. Given JKIL's size window, are you looking to bid for these projects?
Answer, Nalin Gupta, Managing Director. We are currently focusing on EPC only and not on BOT. Some HAM projects may be explored where we see good opportunity and our strength is there, but BOT is ruled out. EPC project flow is strong enough.
Follow-up. Are we looking at any opportunities outside Maharashtra for metro projects?
Answer. Maharashtra Metro projects will be bid for. Thane Ring Road, MMRCL Line 11, ongoing Line 3 underground (INR6,000 cr), CIDCO lines around new airport — all in focus. Kamal Gupta added that Thane Metro tenders are being bid, Pune Metro elevated/underground recently submitted, MMRDA Lines 10/11/13 coming up, Delhi Metro underground package to be bid, BMC Lagoon Bridge tender being bid.
2. Q1 order inflow
Jainam Jain, ICICI Securities
Question. As per our calculations, we had an order inflow of INR19 billion. Is this just a conversion of existing LOIs or are there LOIs for new projects?
Answer, Nalin Gupta, Managing Director. Order book is INR21,000 cr. In Q1, no new orders received. Bids worth around INR3,500 cr have been submitted; very hopeful of picking up around INR2,000 cr in Q2.
3. Metro BOT opportunity
Vaibhav Shah, JM Financial
Question. You said some BOT projects are coming on the metro side. Is that right?
Answer, Nalin Gupta, Managing Director. Yes. Line 8 (International Airport to New Bombay Airport) may come up on BOT, but only ~5-10% of metro lines come on BOT. Pune Metro's PMRDA elevated corridor on BOT was taken by Tata. Metros are not profit-making so government usually puts them on EPC.
Follow-up. What would be the value of Line 8, and if it comes on BOT, will JKIL bid?
Answer. Nalin Gupta: exact figure not known as elevated vs underground split is still being worked out. JKIL is not open to BOT, whether metro or elevated corridors; if cash contracts dry up (which is not the case), may explore HAM but not BOT — that's internal policy.
Partly answered.
4. Bid pipeline
Vaibhav Shah, JM Financial
Question. What is the bid pipeline across verticals? Last time it was mentioned at around INR25,000-odd cr.
Answer, Nalin Gupta, Managing Director. Pipeline is now INR30,000 cr across building, elevated corridors, flyover roads, metro and water.
Follow-up. What is the status of GMLR project? Has the TBM arrived?
Answer. Work has started. First TBM ~60% received at site; main break-bulk consignment expected first week of August; second TBM factory acceptance test in first week of August; both machines available by August and January.
5. Capex guidance
Vaibhav Shah, JM Financial
Question. What is the capex guidance for FY26 and FY27?
Answer, Nalin Gupta, Managing Director. Q1 FY26 capex of INR107 cr done. Normal maintenance capex of INR100 cr expected. Over next 2 years, INR450-500 cr of capex is being looked at, in addition to GMLR-specific TBM requirement.
Follow-up. Do we maintain 15% revenue growth and 15-16% EBITDA margin guidance?
Answer. Yes, absolutely, very comfortably.
6. L1 and order inflow guidance
Vaibhav Shah, JM Financial
Question. What is the L1 position right now? And is INR6,000-8,000 cr order inflow guidance maintained despite Virar-Alibaug cancellation?
Answer, Nalin Gupta, Managing Director. L1 around INR4,000 cr but Virar-Alibaug is on BOT and no official communication received, so not considered L1. Order inflow target ~INR6,000 cr for FY26; INR2,000 cr expected in Q2.
Follow-up. Do we expect further working capital reduction in FY26 or similar levels?
Answer. Q1 working capital at 115 days; guidance of 120 days maintained. Will maintain 120-125 days going forward.
7. Virar-Alibaug tender
Nishit Jain, S&J Investments
Question. Last con call mentioned Virar-Alibaug tender validity was increased. Any update — will it continue or be BOT?
Answer, Nalin Gupta, Managing Director. Two projects of ~INR4,000 cr where we were L1 on Virar-Alibaug multimodal corridor. Now learning the project is going on BOT; not sure. Not considering it L1 for the moment; no official communication from department yet.
Follow-up. Last year company invested INR100 cr in PSL Vizag. Any more such asset-buying opportunities this year?
Answer. Right now doesn't look like any more such projects. PSL Vizag work is going well; major amount of loan has been prepaid, on track.
8. Versova-Dahisar project
Nishit Jain, S&J Investments
Question. What is the status of the Versova-Dahisar project? Has operation started?
Answer, Nalin Gupta, Managing Director. LOI received; preparatory works underway (mangroves, CRZ, Pollution Control Board clearances). Permission to start road portion works received. Soil investigation, test piles, GAD submission, design approval for ~40 foundations done. Physical piling to start next week; substantial work from August. ~30% of stretch is on mangrove/affected areas; 70% on road area with elevated corridor.
Follow-up. Will this be extended to Virar and Palghar in future?
Answer. Current line is till Bhayandar (Dahisar-Mira Road). Extension to Vasai-Virar being worked on by MMRDA and BMC; most likely by MMRDA. Tender expected in 3-6 months.
9. Metro Line 4 status and Virar funding
Dhvaneet, Savla Family Office
Question. On Metro Line 4, how much of the order book is under construction and when will it complete? Second, was any funding procured for L1 in Virar-Alibaug?
Answer, Nalin Gupta, Managing Director. No funding taken for Virar-Alibaug. For Line 4, J. Kumar's scope is small ~INR500 cr (Kasaravadavali to Gaimukh). Overall project expected to complete in ~1.5 years; J. Kumar has done ~85% of its portion. 5-6 km stretch to be opened on priority basis within a year.
10. Peak debt / capex correction
Aditya Sahu, HDFC Securities
Question. Confirm the peak gross debt guidance of INR9 billion for FY26 given earlier — does it continue?
Answer, Nalin Gupta, Managing Director. There are two TBMs required for GMLR, but JKIL's requirement is only one. One TBM is bought by NCC. J. Kumar never intended to take INR900 cr capex for this project; ours was 50%. Over 2 years, expect to book capex close to INR500 cr including maintenance.
Follow-up. What is the overall debt expected for FY26 and FY27?
Answer. As guided, around INR750-800 cr for FY26 and FY27.
11. Multi-year revenue/margin guidance
Devang Shah, Asit C Mehta Investment Intermediates
Question. Do we maintain the 15%-plus revenue CAGR and same EBITDA margin guidance for the next 2-3 years?
Answer, Nalin Gupta, Managing Director. Very sure of maintaining 15-16% top-line growth and 14-15% EBITDA margin, targeting 15-16% EBITDA over next 6-8 quarters through operational efficiency and leverage.
Follow-up. What is the order book possibility at end of FY26 given the INR6,000 cr inflow target and FY25 base of INR5,700 cr revenue?
Answer. Maintaining order book at minimum INR22,000-23,000 cr. Q1 was not aggressive because already at comfortable INR21,000 cr (3-4 years of top line). Q2 should add ~INR2,000 cr; full year INR5,000-6,000 cr.
12. Industry outlook and H2 pickup
Devang Shah, Asit C Mehta Investment Intermediates
Question. What is the industry outlook — is H2 likely to see a step-up in order inflow from government? What about private projects?
Answer, Nalin Gupta, Managing Director. Q1-Q2 was muted on order inflow/tendering due to new government formation and existing commitments. H2 should see good order inflow. Government is very pushy on infrastructure. Very hopeful about H2 with new tenders in metros, elevated corridors, road tunnels. J. Kumar only works in government sector, not private — enough opportunity there.
13. Order mix shift
Lokesh Kashikar, SMIFS Institutional Equities
Question. Metro share in order mix has declined to <15% — strategy or competition?
Answer, Nalin Gupta, Managing Director. Concentrate more on structures across metro and elevated corridors. New verticals added: road tunnels and water. Focus is bottom line — when good metro projects came (Line 3 underground INR5,000 cr), metro share rose; when GMLR, Chennai elevated, Dwarka Expressway came, metro share fell. Will go where right opportunity with right margin is, including metro.
Follow-up. Is it fair to assume 14.7-14.8% margin for FY26 and 15% for FY27?
Answer. Yes, currently 14-15%; going up 1 notch percentage in 6-8 quarters; 15-16% by FY27.
14. Chennai elevated corridor
Lokesh Kashikar, SMIFS Institutional Equities
Question. What is the progress and outstanding order value of the Chennai elevated corridor?
Answer, Nalin Gupta, Managing Director. 4 packages, all going well. One of India's biggest casting yards established. Superstructure segment casting started. Foundation work in river going full-fledged; ~40% of piling completed.
Follow-up. What is the outstanding value of the total INR6,500 cr Chennai project?
Answer. Will get back separately on the exact outstanding figure; not handy right now.
Not answered directly.
15. Order book quality
Diwakar Rana, Prudent Equity
Question. Of the INR21,000 cr order book, do we have any slow-moving legacy order?
Answer, Nalin Gupta, Managing Director. Only NBCC building project of INR300 cr is not in full execution; only preparatory work. Apart from that, all projects going well. Expected to start by September-October.
Follow-up. Are we planning to bid in waste management?
Answer. Looking at the opportunity but cautious as it's a new vertical. Will explore; given the right opportunity will go for it.
16. Revenue mix and project status
Ashwin Kumar, Individual Investor
Question. Can you provide revenue breakup this quarter across metros, expressways etc.? And status of biggest projects?
Answer, Nalin Gupta, Managing Director. This quarter: ~40% revenue from metro, rest from flyovers and tunnels. Vertical inflows: Metro INR340 cr, Underground Metro INR250 cr, Elevated flyovers/corridors INR300 cr, Road tunnels INR270 cr, Water INR65 cr, Other civil/building INR270 cr. Dwarka Expressway near completion; Chennai Elevated 4,000 going full-fledged; GMLR TBM arriving; new Bombay Coastal Road going well; Thane Anand Nagar-Saket elevated corridor 50-55% piles done.
Follow-up. Is there any delay in payments?
Answer. Regular payments on time. Variation approvals take time; old payments being received, new ones coming. Otherwise no payment issues.
17. Q2 order inflow pipeline
Ankita Shah, Elara Capital
Question. What kind of projects are expected in Q2 in the INR2,000 cr you mentioned — which segment?
Answer, Nalin Gupta, Managing Director. Mostly from elevated corridors and elevated metro. Pune Metro bid of ~INR2,000 cr should open before 15 August; some elevated projects being submitted soon. Underground metro also part of expected inflow.
Follow-up. You mentioned MSRDC payments coming through — how is funding tied up for future projects?
Answer. We have not mentioned any MSRDC project; we don't have any MSRDC order book. For Maharashtra, until EPC contract funding is approved, tenders are not floated. Existing INR21,000 cr order book is fully funded.
18. Labor situation
Uttam Kumar Srimal, Axis Securities
Question. Labor issues at construction sites — is JKIL facing this?
Answer, Nalin Gupta, Managing Director. Labor situation is tight given many projects floating. JKIL is a good paymaster with a long-tied workforce. Heavy use of automation, mechanization and pre-casting reduces labor dependency. Don't usually face labor issues.
Follow-up. How will depreciation and finance cost pan out for full year FY26?
Answer. Vasant Savla: Finance cost guided at 2.75% of revenue. Depreciation currently ~3%, may marginally go up to 3.5% with TBM addition.
19. Balance sheet data points
Shravan Shah, Dolat Capital
Question. Data points on balance sheet — mobilization advance, retention money, unbilled revenue, trade receivables and payables as of June?
Answer, Vasant Savla, Chief Financial Officer. Mobilization advance INR789 cr; Retention money INR386 cr; Unbilled revenue INR650 cr. Trade receivable INR1,697 cr; Creditors INR795 cr. Total inventory (raw material + unbilled) INR967 cr; apple-to-apple raw material inventory INR315 cr vs INR503 cr in March.
Follow-up. Is the INR100 cr maintenance capex annual or one-time, and put together how much over two years?
Answer. Apart from INR100 cr annual maintenance capex, INR450-500 cr additional capex for TBM and equipment. Put together INR550-600 cr over both years.
20. Dahisar-Virar corridor
Shravan Shah, Dolat Capital
Question. Virar-Versova tender value earlier discussed at INR80,000 cr — will JKIL participate individually or via JV?
Answer, Nalin Gupta, Managing Director. It is Dahisar to Virar (or Uttan to Virar), not Versova to Virar. Total project cost ~INR55,000 cr. Will participate; will decide on JV vs individual based on project size split and qualification criteria.
Follow-up. Why is order inflow target only INR6,000 cr when revenue is INR6,600 cr — shouldn't target be INR8,000 cr+?
Answer. Cannot be mechanized; bottom line is the most important factor. Don't want growth not supported by bottom line — that discipline has made us net cash positive. FY24 booked >INR10,000 cr; this is opportunity-based. INR5,000-6,000 cr is a safe figure; we are open to even INR20,000 cr if priced right. Don't want to underbid.
21. HAM and QIP
Shravan Shah, Dolat Capital
Question. If we explore HAM in roads, how much equity can we commit? And is there a thought process on QIP fundraising this year?
Answer, Nalin Gupta, Managing Director. HAM: no HAM project currently in pipeline given plenty of EPC opportunities. QIP: will depend on opportunity and market scenario; not desperate either way. Resolution is in place, will go for it if pricing and market are suitable.
22. PSL Vizag asset monetisation
Vaibhav Shah, JM Financial
Question. PSL land — outstanding loan as of June? When will monetisation complete? How was payment funded?
Answer, Nalin Gupta, Managing Director. Out of INR90 cr original, INR70 cr paid; INR20 cr balance. Entire transaction to complete by next June; debt paid off by December. Payment is entirely from monetising equipment, machineries and some land bank of that asset.
Follow-up. What is the exact value of the Chennai elevated corridor order?
Answer. INR3,600 cr plus INR550 cr = INR4,200 cr in all. Entirely ours.
23. Casting yard setup
Nishit Jain, S&J Investments
Question. For GMLR, is there a casting yard setup? And for Versova-Bhayandar, would you need a new yard?
Answer, Nalin Gupta, Managing Director. Yes, casting yard for GMLR already set up; batching plants installed; 200 rings cast. For Coastal Road package B, new casting yard being finalised, to close soon. All casting yards on lease.
24. Promoter pledge
Diwakar Rana, Prudent Equity
Question. Promoter pledge at ~22% — any plan to release?
Answer, Nalin Gupta, Managing Director. Pledge was done with Bank of India for initial debt and bank guarantees. No new pledge. Trying to get the pledge released. Bankers have their own timeline; cannot commit exactly. Kamal Gupta added there is no new pledge and the team is working on release.
Follow-up. Any timeline for pledge release?
Answer. We are trying, but bankers have their own timeline; cannot commit exactly on that.
Not answered directly.
25. Net profit trajectory
Dinesh Maheshwari, Kirti Creations
Question. Will the company be able to reach a PAT of INR400-500 cr this year given last year's INR300+ cr?
Answer, Nalin Gupta, Managing Director. Yes, we are trying; will not mention exact number. It will be good growth.
Not answered directly.
What was said
Topic by topic, in the order it was spoken
Opening and Sector Positioning · Nalin Gupta (MD)
- Welcomed participants and confirmed presence of MD Kamal Gupta, CFO Vasant Savla and Marathon Capital as IR partner
- Positioned JKIL as a leading infrastructure construction company benefiting from sustained government push on urban development, metros and transport infrastructure
- Highlighted strategy of deepening presence in metros, elevated corridors, tunnels and water infrastructure while enhancing execution frameworks
- Described JKIL's edge as taking on technically demanding, first-of-kind projects where others see complexity
Q1 FY26 Financial Performance · Nalin Gupta (MD)
- Revenue from operations grew 16% YoY to INR1,484 cr vs INR1,281 cr in Q1 FY25
- EBITDA up 18% YoY to INR217 cr vs INR84 cr (note: prior base appears unusually low per management); EBITDA margin 14.6% vs 14.4%
- PAT grew 19% YoY to INR103 cr vs INR87 cr; PAT margin 7% vs 6.8%
- Total order book at INR20,946 cr as of 30 June 2025; net debt negative INR159 cr (cash positive)
In their words
Where others see complexity, we see opportunity. Technically demanding first of their kind projects are not roadblocks, they are catalysts. The challenges to innovate, adapt and lead.
We are very bullish about the infrastructure segment in this 2 years' time and including H2, there should be good amount of works that we should be expecting.
We don't want to have a growth, which is not supported with a strong bottom line. That financial discipline of our company has made us a net cash flow positive company. We are surely open to even INR20,000 crores worth of order if we get it at our price.
To check next time
What management committed to on this call, or the dates they gave.
- Q2 FY26 order inflow target of ~₹2,000 cr with Pune Metro bid opening before August 15.
- First GMLR TBM arrival in August; second TBM expected by January.
- Versova-Dahisar coastal road physical work starting from August 2025.
- NBCC ₹300 cr project work commencement by September/October.
- Status of H2 FY26 industry order inflow pickup as guided by management.
- Progress on promoter pledge release (~22% with Bank of India).
Transcript
We have not transcribed this call's recording. Read the company's transcript (PDF).
The stock after the call
| After the call | Close | Stock | Nifty 50 |
|---|---|---|---|
| Next session Wed 30 Jul 2025 | ₹707.15 | +0.40% | +0.14% |
| 5 sessions Tue 5 Aug 2025 | ₹703.70 | −0.09% | −0.69% |
| 20 sessions Thu 28 Aug 2025 | ₹614.50 | −12.75% | −1.29% |
From the close of Tue 29 Jul 2025, ₹704.30: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.
Jkumar Infr.ltd.'s other calls
- Q2 FY27Mon 16 Nov 2026Tone: Confident
- Q1 FY27Fri 7 Aug 2026Tone: Mixed
- Q4 FY26Wed 20 May 2026Tone: Confident
- Q3 FY26Fri 6 Feb 2026Not read
- Q2 FY26Fri 7 Nov 2025Tone: Confident
- Q4 FY25Wed 21 May 2025Tone: Confident
- Q3 FY25Wed 5 Feb 2025Not read
- Q1 FY25Wed 7 Aug 2024Tone: Confident
- Q4 FY24Wed 29 May 2024Tone: Confident