Jkumar Infr.ltd. Q2 FY27 earnings call

Mon 16 Nov 202614:30 ISTJKIL

In brief

Q2 revenue rose 15% to ₹1,539 crore, EBITDA margin hit 14.9%, and management held 15% FY27 growth with a ₹22,711 crore order book.

Management's tone
Confident
What was said
Leaned positive
Guidance
Guidance held
Analyst pushback
Low
Stock, next session
−0.60% (Nifty 50 +0.58%)
  • Q2 FY27 revenue rose 15% to ₹1,539 crore on sustained project execution and disciplined cost management.
  • EBITDA margin improved to 14.9% from 14.5% a year earlier, while PAT rose 25% to ₹113 crore.
  • FY27 revenue growth stayed 15% at about ₹6,500 crore, with H1 up 8% and management relying on an H2 ramp after a flat Q1.
  • The order book was ₹22,711 crore; management planned ₹3,000 crore-₹5,000 crore of additional H2 inflow within FY27's ₹8,000 crore-₹10,000 crore target.
  • Net cash was ₹69 crore at September 30, working-capital days were 100, and about ₹900 crore of ₹1,500 crore due had been collected.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY27

This quarterA year agoLast quarterMargin
Revenue₹1,539 cr+14.7%+1.9%
EBITDA (excl. other income)₹229 cr+17.5%+6.6%14.9% (14.5% a year ago)
Net profit₹113 cr+24.8%+16.1%7.4% (6.8% a year ago)
EPS (₹)₹14.97+25.1%+16.2%

From the company's filed results for the quarter ended 30 Sept 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

Where management's figures differ from the filing

  • Q2 EBITDA excluding other income: said Operating margin increased by 18% to INR229 crores; EBITDA margin improved at 14.9%.; filed EBITDA excluding other income: ₹228.65 cr. Management called the figure operating margin; the filed line explicitly excludes other income, and no definition was stated on the call.

What moved the numbers, as management explained it

  • Q2 revenue rose 15% to ₹1,539 crore, which management attributed to sustained project execution and strong operational momentum.
  • Q2 EBITDA margin rose to 14.9% from 14.5%, which management linked to execution efficiency and disciplined cost management.
  • H1 revenue rose 8% to ₹3,050 crore, EBITDA 8% to ₹443 crore and PAT 9% to ₹221 crore after a flat Q1 and stronger Q2.
  • Labor shortages caused some issues during the quarter, although mechanisation, automation and pre-casting kept the impact manageable.
  • TBM depreciation starts from Q3 after its launch; management indicated roughly ₹50-52 crore for Q3.
  • Vizag monetization brought cash into the quarter, but one local-government layout approval remained pending.

The numbers management led with

  • Order book: INR22,711 crores as on 30 September 2026 (metro 7%, elevated corridors 47%, road tunnels 19%, others 26%)
  • FY27 order intake: INR5,540 crores booked in H1; total FY27 target INR8,000 crores-INR10,000 crores, with INR3,000-5,000 crores more planned in H2
  • Net cash position: Net cash of INR69 crores (net debt INR-69 crores) as on 30 September 2026; debt-equity 0.23x
  • Fixed deposits: FD of INR700 crores held, largely encumbered against performance guarantees (10%), mobilization-advance-linked bank guarantees and collateral

Guidance

Guidance on this call

WhatForWhat management said
Top-line growthFY27FY27 top-line growth of 15% YoY, which management said it was confident of achieving.
Top lineFY27Around ₹6,500 crore of FY27 revenue.
Order inflowFY27FY27 order inflow of ₹8,000 crore-₹10,000 crore.
Additional H2 order bookH2 FY27Additional H2 order inflow of ₹3,000 crore-₹5,000 crore.
Top-line growthFY28FY28 revenue growth of 15%, following the ₹7,500 crore revenue ambition.
RevenueFY28FY28 revenue target of ₹7,500 crore, confirmed in response to the analyst's question.
RevenueFY30Revenue target of ₹10,000 crore by FY30.
Operating marginFY28-FY29Operating margin to rise by 100 bps to 15%-16% in another one to two years.
CapexFY27-FY28FY27-FY28 capex remains broadly ₹150 crore a year.
Working capital daysFY27Working-capital cycle to stay around 100-120 days.
GMLR completionFY30GMLR completion targeted before end-2029.
Chennai completion (Chennai elevated corridor)FY29Chennai elevated-corridor completion targeted by December 2028 or January 2029.
Project completion (Worli-Sewri, Sewri-Navi Mumbai Airport and Metro Line 2B)FY27Worli-Sewri, Sewri-Navi Mumbai Airport and Metro Line 2B were targeted for FY27 completion.
Vadhavan project revenuesH2 FY27Vadhavan project revenues expected from December or January.
DepreciationQ3 FY27Q3 depreciation expected near ₹50-52 crore; management said the previously guided number still stands.

What changed since the Fri 7 Aug 2026 call

WhatOn the Fri 7 Aug 2026 callOn this call
FY27 revenue growth (held)FY27 revenue growth maintained at 15% (~₹6,500 cr).15% growth and about ₹6,500 crore reaffirmed, with an H2 ramp described.
FY27 order inflow (held)FY27 order-inflow guidance of ₹8,000-10,000 cr.₹3,000-5,000 crore additional H2 inflow planned; FY27 total retained at ₹8,000-10,000 crore.
Big-ticket order-inflow upside (not repeated)Potential ₹12,000-13,000 crore inflow if the big-ticket pipeline converted.Not mentioned
EBITDA margin (held)14-15% for FY27; intent to reach 15-16% over 1-2 years.Current margin of 14-15%; management again seeks 15-16% in one to two years.
Delhi Metro L1 conversion (not repeated)₹1,500 cr L1 on Delhi Metro was expected to convert in Q1-Q2.Delhi Metro cancelled it; a fresh restricted tender was expected in 10-15 days.
Long-term revenue horizon (restated)₹7,500 cr topline target set for FY28.FY28 discussion was confirmed and management added a ₹10,000 crore revenue target for FY30.
Working-capital days (raised)FY27 guidance of 100-110 days; Q1 actual was 103 days.100 days at September; management expected the cycle to remain around its 100-120 day band.
Quarterly depreciation after TBM capitalisation (restated)₹60 cr per quarter after TBM capitalisation.Higher from Q3; roughly ₹50-52 crore was indicated, though prior guidance was said to stand.

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY26 top line growthFY2615% (on the Q4 FY25 call)0.5%, below the figure guided
Top line growthFY2615–16% (on the Q1 FY26 call)0.5%, below the range
FY26 revenue targetFY26₹6,200–6,300 cr (on the Q2 FY26 call)₹5,723 cr, below the range
FY26 revenue growthFY2611% (on the Q2 FY26 call)0.5%, below the figure guided
FY26 EBITDA marginFY2614–15% (on the Q2 FY26 call)14.2%, within the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Metro

Metro represented 7% of the September order book. Four of seven tunnel boring machines were in execution at Delhi, and Metro Line 2B was targeted for FY27 completion.

Order book contribution 7% · Tunnel boring machines 7 · Machines in execution at Delhi 4

Outlook: Three Delhi underground tenders, Mumbai Metro Line 5 and Pune jobs were in the pipeline; completed tunnel work may free machines for redeployment.

Elevated corridors

Elevated corridors represented 47% of the order book. Chennai foundation work was about 70%-75% complete, with 2,900 precast segments cast.

Order book contribution 47% · Chennai foundation work 70%-75% · Precast segments cast 2,900

Outlook: Chennai was targeted for December 2028 or January 2029; Worli-Sewri, Sewri-Navi Mumbai Airport and Metro Line 2B for FY27.

Road tunnels

Road tunnels represented 19% of the order book. At GMLR, one tunnel had progressed over 300 m and the second TBM had drilled about 8 m.

Order book contribution 19% · One GMLR tunnel progress over 300 m · Second TBM progress 8 m

Outlook: Management said GMLR should complete before end-2029, about one year ahead of the revised schedule.

Other projects

Other projects represented 26% of the order book; management said it was not thirsty for orders and would quote projects only at its margins.

Order book contribution 26%

Outlook: New bids were to remain selective, with EPC the primary focus and HAM explored case by case.

Balance sheet, capex and funding

  • Net debt was negative ₹69 crore at September 30; debt-equity was 0.23x, which management expected to remain around 0.23x-0.24x.
  • Working-capital days were 100 versus 99 in FY26; management expected the cycle to remain around the 100-120 day band.
  • Management reaffirmed FY27-FY28 capex at broadly ₹150 crore a year.
  • Fixed deposits were ₹700 crore, largely required for performance and margin-money guarantees; the free portion was not stated.
  • Around 70% of fund and non-fund limits were utilised; non-fund limits were ₹5,000 crore of ₹6,200 crore, with ₹3,500 crore utilised.
  • Of about ₹1,500 crore due at September 30, ₹900 crore had been collected by the call and roughly ₹600 crore remained pending.

The industry, as management sees it

Management sees the broader infra tender market as competitive today but expects it to loosen over the next 10-12 months as INR50,000-100,000 crore of projects planned in Maharashtra alone convert into orders. MoRTH's tighter prequalification and net-worth norms are expected to reduce competition on niche projects, while metro, large-diameter tunnel and complex elevated corridor tenders consistently attract five to six bids.

Risks management named

  • Competition intensity in tenders remains high, though expected to ease as order pipeline improves
  • Labour shortage across simultaneous projects, partly mitigated by mechanisation and precasting
  • Higher depreciation from Q3 FY27 as recently launched TBMs are capitalised
  • Delhi Metro order cancelled and to be re-tendered as a limited tender
  • Execution risk on GMLR and Chennai, with long completion timelines to FY29-FY30

Q&A

Discussion was largely friendly and sequential, dominated by Varun Aggarwal (individual investor, three turns) and Shravan Shah (Dolat Capital), who probed order intake, Q3 sequential revenue, depreciation, working capital, bank limits and HAM strategy. Pushback was low overall - management generally answered directly - with only two soft spots: the exact Q3 depreciation number was deferred to the finance team offline, and the HAM equity commitment sizing was left case-by-case with no commitment. There were no hostile exchanges; management rebutted the TBM China-supply risk, the Maharashtra water-restriction impact and the SFIO query with flat dismissals rather than argument.

Not answered directly

  • Exact Q3 FY27 depreciation quantum
  • HAM equity commitment size per project
  • Free/unencumbered fixed deposit quantum
  • Breakup of utilisation of bank fund-based and non-fund-based limits

Asked for a number, answered without one

  • Q3 sequential revenue: Management said Q3 would be higher than that, but offered no exact figure and said the financial team would provide it offline.
  • Free fixed deposits: Management confirmed total FDs of ₹700 crore but said it would check the free amount; some cash is retained for bidding and margin money.
  • HAM equity commitment: Management said commitment would depend on each project's type, nature and opportunity, and declined to give an amount.
  • FY30 EBIT margin: Management did not validate 20%; it reiterated a 15%-16% operating-margin goal in one to two years.
  • Vizag monetization: Management said it was going well, with one local-government layout approval pending, and expected collections to exceed projections over two quarters.

Every question, with its answer

  1. 1. Competition and bidding environment

    Varun Aggarwal, Individual Investor

    Question. What is the general state of the infra market - bidding activity and competition versus any other period?

    Answer, Kamal Gupta, Managing Director. Competition is quite competitive right now and he would not deny it, but the last two years saw limited order inflows. There are now good orders in the pipeline - more than INR50,000 crores to INR100,000 crores worth of projects planned in Maharashtra alone - giving traction over the next 10 to 12 months. As orders keep coming in, competition should loosen. Nalin Gupta added that MoRTH has tightened prequalification and net-worth conditions after quality issues on some projects, so smaller contractors cannot bid for larger projects, reducing competition on niche projects; the company is exploring HAM projects where competition is much lower.

  2. 2. Order book guidance

    Varun Aggarwal, Individual Investor

    Question. Can you update the order book guidance - you mentioned INR8,000-10,000 crores expected this financial year; what is expected additionally in H2?

    Answer, Nalin Gupta, Managing Director. The company has already bagged orders of INR5,540 crores as of H1. We are quite confident that we should be able to bag orders close to around INR8,000 crores-INR10,000 crores in the coming H2, taking total FY27 order intake to INR8,000-10,000 crores.

  3. 3. Delhi Metro L1 order

    Varun Aggarwal, Individual Investor

    Question. What is the status of the Delhi Metro L1 order that was expected to convert in Q1 and Q2?

    Answer, Nalin Gupta, Managing Director. Delhi Metro has cancelled the order; it did not convert into the order book because there is a change in the project and the project cost is likely to go up. In the next 10 to 15 days they should come up with a fresh tender, restricted to the number of bidders who had bid for the job - a limited tender for only those bidders.

  4. 4. Bid pipeline

    Varun Aggarwal, Individual Investor

    Question. What is the current bid pipeline in terms of projects being bid and their locations?

    Answer, Nalin Gupta, Managing Director. Bids worth around INR3,000 crores have already been submitted. Around INR30,000 crores worth of projects are expected to be bid within the next six months, including elevated corridors, roads and flyovers worth around INR10,000 crores, metros around INR15,000 crores and building works around INR5,000 crores.

  5. 5. Revenue growth guidance

    Varun Aggarwal, Individual Investor

    Question. Can you update the FY28 top-line guidance?

    Answer, Nalin Gupta, Managing Director. We had given guidance of around 15% growth on last year's top line. Q2 achieved 15% though Q1 was flattish, so currently we stand at 8%. With the H2 ramp-up, management is quite confident it should achieve the targeted 15% growth.

  6. 6. Project execution timelines

    Varun Aggarwal, Individual Investor

    Question. What is the execution timeline for the big-ticket projects, specifically Chennai and GMLR?

    Answer, Nalin Gupta, Managing Director. GMLR had an original five-year period but land was handed over around two years late; with progress ramped up, management expects to complete it in less than one year ahead of schedule - around before end of '29. One tunnel has gone more than 300 m inside and the second TBM has started drilling, having entered the ground around 8 meters; both machines are functional. Kamal Gupta added that for Chennai, almost 70-75% of foundation work is complete with around 2,900 precast segments cast, and completion is expected by December '28 or January '29.

  7. 7. Q3 sequential revenue outlook

    Shravan Shah, Dolat Capital

    Question. Does the 15% growth target imply a significant sequential Q3 improvement over Q2's INR1,536 crores - logically INR100-150 crores higher?

    Answer, Kamal Gupta, Managing Director. Yes, what you are saying is right - Q3 and Q4 have to be better than the previous year, and more than 15% growth, then only will we achieve 15% for the year. We are on that target and hopeful to achieve it. On sequential growth, yes it will be higher than that; if exact numbers are needed, the financial team will pass them on.

    Partly answered.

  8. 8. Medium-term revenue guidance

    Shravan Shah, Dolat Capital

    Question. Does the previously given 15% next-year growth guidance implying ~INR7,500 crores of FY28 revenue remain intact?

    Answer, Kamal Gupta, Managing Director. Yes. We are now targeting for INR10,000 crores revenue by FY30, which will be like a 15% growth. Kamal Gupta also confirmed that there is already some margin improvement in this quarter.

  9. 9. Depreciation outlook

    Shravan Shah, Dolat Capital

    Question. Depreciation was INR4-5 crores lower versus Q1; how should depreciation be looked at from Q3 given the TBM has started?

    Answer, Nilesh Sharma, General Manager (F&A). From Q3 the depreciation will be higher than in Q2 or H1, since the TBM was launched only recently around the Diwali period and depreciation on the TBM starts from this quarter onwards. On the specific number, the exact calculation is not ready at present, but it will be near about INR50 crores, INR52 crores or something like that. Nalin Gupta added that if the nitty-gritty is needed, the financial team can be contacted offline, and that the number already guided stands.

    Not answered directly.

  10. 10. Balance sheet items

    Shravan Shah, Dolat Capital

    Question. Can you give the mobilization advance, retention money and unbilled revenue balances as on September?

    Answer, Nilesh Sharma, General Manager (F&A). The current mobilization advance balance as of date is around INR627 crores. Unbilled amount is INR572 crores and security deposit is around INR490 crores. Nalin Gupta had opened by confirming the mobilization advance balance of around INR627 crores.

  11. 11. Capex guidance

    Shravan Shah, Dolat Capital

    Question. Capex of INR80 crores has been done and ~INR150 odd crores was guided for this year and next year - does it remain broadly the same?

    Answer, Kamal Gupta, Managing Director. Yes, it will broadly remain the same. You are right, Shravan.

  12. 12. Vadhavan project

    Shravan Shah, Dolat Capital

    Question. Any update on the Vadhavan project?

    Answer, Kamal Gupta, Managing Director. The Vadhavan project has already been mobilised - work for the service road has started with excavation and ground clearing, and the survey has been done. The work is taking shape and should not be an issue; revenue is expected from December/January.

  13. 13. Order inflow phasing

    Shravan Shah, Dolat Capital

    Question. You have INR5,500 crores of orders already - is the additional INR8,000-10,000 crores for the second half or for the full year?

    Answer, Nalin Gupta, Managing Director. Another INR3,000 crores-INR5,000 crores of order book is planned for H2, taking the entire order book for the current financial year to INR8,000 crores to INR10,000 crores.

  14. 14. FY30 margin and revenue targets

    Dhvaneet Savla, Savla Family Office

    Question. With the FY30 INR10,000 crores revenue target and improving margins, can EBIT margins cross 20%? What is the project mix - road heavy or metro heavy? And which marquee projects complete this year?

    Answer, Kamal Gupta, Managing Director. J. Kumar is always focused on profitable growth. With an order book of INR22,700 crores the company is not thirsty for orders and does not quote projects at any rate - only at its margins. For FY30 with INR10,000 crores of revenue, operating margin currently 14-15% is being targeted up ~100 bps into a 15-16% range, achievable in another one or two years. Projects completing in FY27 include the Worli-Sewri connector, the Sewri-Navi Mumbai Airport link, and Metro Line 2B from Mira Road extended to Bandra on the Link Road and SV Road.

  15. 15. Water/drought impact on execution

    Dhvaneet Savla, Savla Family Office

    Question. Are there execution problems from the severe drought-like situation in Maharashtra, with water usage restricted for certain projects?

    Answer, Nalin Gupta, Managing Director. That is absolutely not the case. All resources are in place and works are going on smoothly, as the Q2 result of 15% growth shows. Q3 and Q4 are expected to do much better than Q2. Management does not find the water-restriction information to be really true and it is not affecting the work.

  16. 16. Receivables and collections

    Varun Aggarwal, Individual Investor

    Question. A lot of contractors face delays in payments from government in various states - are we facing any such issue in our projects?

    Answer, Kamal Gupta, Managing Director. The company is very conservative in selecting geography, project and client, and by God's grace does not see any issues in collecting payments - all payments are coming on time, with the working capital cycle well within 100 days versus peers. Nalin Gupta added that of the ~INR1,500 crores receivable as of 30 September, around INR900 crores has already been received, leaving only ~INR600 crores pending, so collection is reasonably good.

  17. 17. Working capital cycle

    Shravan Shah, Dolat Capital

    Question. Given INR900 crores already collected, will working capital days - inventory, debtors, payables - improve further from 100 days or is 100 manageable?

    Answer, Nalin Gupta, Managing Director. 100-120 days has always been the stated range and today we stand at 100 days, so it should remain in the same band and nothing should change drastically. It has already improved from 120 days to 100 days.

  18. 18. Leverage and net cash

    Shravan Shah, Dolat Capital

    Question. Gross debt is below INR800 crores - will this level be managed or is further reduction possible?

    Answer, Kamal Gupta, Managing Director. Debt-equity is at 0.23x and will stay around 0.23-0.24x. Nalin Gupta added that even with growth in top line and new order bookings, the company remains cash positive at the net level - hardly any infra company has such financial discipline, and management will continue to maintain it.

  19. 19. Vizag land monetisation

    Shravan Shah, Dolat Capital

    Question. Will the Vizag monetisation of INR180 odd crores be completed by Q3?

    Answer, Kamal Gupta, Managing Director. The Vizag monetisation is going well; only one approval from the local government on layout approvals is awaited. A lot of deals are already finalized and good money has been received this quarter; over the coming two quarters management expects to be much above the targeted projections.

  20. 20. HAM strategy and equity commitment

    Shravan Shah, Dolat Capital

    Question. Going beyond EPC, are you now looking at HAM projects - and what equity commitment of INR200-300 crores would you look at initially?

    Answer, Kamal Gupta, Managing Director. MoRTH has tightened PQ and net-worth conditions, so small contractors cannot bid for bigger projects; the company will concentrate on projects in its niche area where competition is less. Nalin Gupta added that HAM is a deferred payment model and the company will explore selective, lucrative opportunities with decent numbers, but its primary focus remains EPC. On equity commitment, it is case-by-case depending on project type and opportunity; management believes it has sufficient leverage and no issue on that account.

    Not answered directly.

  21. 21. Competitive strategy and Adani entry

    Hemant Kanungo, Norasia

    Question. With current competition intensity and players like Adani entering the sector, and our 15-16% margin standard, how do we plan to sustain continuous order intake - more complex projects or otherwise?

    Answer, Nalin Gupta, Managing Director. Adani Enterprises is mainly focusing on BOT and HAM projects and not coming into EPC at all, while J. Kumar is a core EPC player, so this is not a relevant point. Competition has always been there over 45 years and intensity rises and falls with the number of opportunities available. In metro, large diameter tunnels and complex elevated corridors, there are always five to six bids on average; nothing has changed dramatically.

  22. 22. SFIO/SEBI regulatory matter

    Hemant Kanungo, Norasia

    Question. In April there was an exchange notice regarding an SFIO-related matter - is it resolved, any update?

    Answer, Nalin Gupta, Managing Director. It is the old matter earlier raised by SEBI; all matters have been clarified and all documents were submitted long back. It was cleared by SEBI and a similar reply is expected from SFIO. It is a matter of procedure, the company is cooperating fully with the department, and there is nothing to worry about.

  23. 23. TBM supply chain and China export risk

    Vipul Shah, Sumangal Investments

    Question. Media reports say China has restricted export of TBM machines to India - will this affect the company or are we fully covered?

    Answer, Nalin Gupta, Managing Director. This is a myth. Of the hundreds of TBMs available in India, Chinese contribution is less than 10%. Herrenknecht, Terratec and Robbins supplied the heart of the machines and major components from Europe and the US to China for assembly of the shield and cutter head, but that base has now shifted to other locations and supply has been very regular. One GMLR machine assembled in China was delayed by one to two months while the second, assembled elsewhere, is already working with the company. Herrenknecht has opened a huge facility in Chennai and is manufacturing TBMs and shipping them regularly. Machine supply for TBM is absolutely no issue.

  24. 24. Marine and coastal road strategy

    Vipul Shah, Sumangal Investments

    Question. Any plans to enter marine segments? We generally don't bid for marine projects - any reason?

    Answer, Kamal Gupta, Managing Director. The company is already doing projects in water - the Chennai project spans 25 km with the last 20 km in the Cooum River, and the Navi Mumbai coastal road is again marine in nature. Given the right opportunity with the right numbers, it can do it. Nalin Gupta added that Mothagaon sea bridge, Mumbai coastal road and riverfront development jobs have been done, though earlier marine jobs were not bigger ticket size; now with bigger ticket sizes emerging, the company is trying to explore that vertical, subject to specific prequalification requirements.

  25. 25. Marine capability

    Vipul Shah, Sumangal Investments

    Question. So we have all the technical capabilities to bid for all marine projects, right?

    Answer, Nalin Gupta, Managing Director. Yes. For coastal roads you need to make temporary access bridges (TAB), which the company already does at all its coastal road and other projects - the same technology. So doing these works is not a problem; it depends on ticket size, geography and the geometries attached to the job, and the company will surely look at those ventures as well.

  26. 26. TBM fleet and underground metro pipeline

    Pritesh, Daga Investments

    Question. On TBMs - underground metro order booking is only 3-4% of the order book. How many of the seven TBMs are in use, and where is the potential for metro underground order booking?

    Answer, Nalin Gupta, Managing Director. The company has seven TBMs for metro, out of which four are in execution right now at Delhi. Delhi has three underground metro projects in the pipeline and the company is about to bid for them; Bombay has one underground project at Metro Line 5 in the Thane/Bhiwandi area, plus jobs in Pune. With completion of Surat and the Delhi tunnelling job, machines will be free and redeployed after a gap of six to 12 months, and each machine will need refurbishment before bidding again. Having already done two to three projects each, the company has an upper hand in bidding for these jobs.

  27. 27. Free FD and capital efficiency

    Pritesh, Daga Investments

    Question. You are cash positive with INR69 crores net cash - how much FD is free, and why not use it to reduce debt given the impact on ROE and ROCE?

    Answer, Kamal Gupta, Managing Director. The company has FD of INR700 crores; the free FD quantum would need to be checked. Nalin Gupta explained that FDs are required for margin money: every project requires a 10% performance guarantee, and if a mobilization advance is taken, 110% of that 10% must be given as bank guarantees requiring cash deposits converted into FDRs; performance guarantees also stay blocked through the defect liability period. The company also keeps some free FDRs to fund bidding on larger-ticket projects and as collateral security, and does not touch that unless required. Debt is just 0.23x and reflects working capital requirement for ongoing projects.

    Not answered directly.

  28. 28. Banker pledge release

    Varun Aggarwal, Individual Investor

    Question. Any update on the pledge with our banker? It would allow more institutional participation if released.

    Answer, Kamal Gupta, Managing Director. The pledge was done at the very initial stage of the company when the working capital limit was taken with the main Bank of India, pledged against fund and non-fund based working capital requirements. It is difficult to get it back once given to the bank. Nalin Gupta added that a request was sent to the bank six months back to return the pledge because debt has been reduced substantially, but it is a process and they are working on it.

    Partly answered.

  29. 29. Bank limit utilisation

    Raj Shah, Insight Advisors

    Question. Can you provide the breakup of fund-based and non-fund-based limits and their utilisation?

    Answer, Kamal Gupta, Managing Director. Total sanctioned is INR6,230 crores-INR6,290 crores with utilised of INR4,400 crores, i.e. around 70% of fund and non-fund based limits used. Non-fund-based sanctioned is INR6,200 crores (INR5,000 crores per Nalin Gupta) with utilisation of around INR3,500 crores. Fund-based: sanctioned around INR780-800 crores with ~42% utilised, plus a term loan of ~INR400 crores taken against equipment (TBM and other equipment, repaid in three-to-five-year instalments) which is 100% utilised.

    Partly answered.

  30. 30. Labour availability and execution

    Raj Shah, Insight Advisors

    Question. There is commentary of labour shortage for execution across infra companies - does the 15% growth account for any labour challenges, or is this rational growth?

    Answer, Kamal Gupta, Managing Director. Labour shortage is there - with so many works simultaneously going on there are some shortages, and the company faced some issues this quarter too, but can manage them by mechanising work and using more automation and equipment to reduce labour requirement versus other projects. As a good paymaster, J. Kumar attracts labourers, so it should not be an issue. Nalin Gupta added there is no alarming labour shortage situation, with the company moving to more pre-casting and mechanised methods.

  31. 31. FY27 revenue guidance

    Raj Shah, Insight Advisors

    Question. Given the current run rate, how do you see the year closing in terms of revenues?

    Answer, Nalin Gupta, Managing Director. We have given a top-line growth guidance of 15%, which we are confident we should be able to achieve. Kamal Gupta added that this translates to around INR6,500 crores for FY27.

What was said

Topic by topic, in the order it was spoken

Q2 & H1 FY27 Performance Highlights · Kamal Gupta (MD)

  • Revenue from operations for Q2 FY27 up 15% to INR1,539 crores.
  • Q2 operating margin up 18% to INR229 crores; EBITDA margin improved to 14.9% versus 14.5% a year ago.
  • Q2 PAT improved 25% to INR113 crores.
  • H1 FY27 revenue from operations up 8% to INR3,050 crores; EBITDA up 8% to INR443 crores; PAT up 9% to INR221 crores.
  • Net cash position of INR69 crores as at 30 September 2026, described as a source of flexibility for future growth.
  • Working capital days of 100 for H1 FY27 versus 99 days for FY26.

Order Book & Revenue Visibility · Kamal Gupta (MD)

  • Order book of INR22,711 crores as at 30 September 2026.
  • Mix: elevated corridors 47%, others 26%, road tunnels 19%, metro projects 7%.
  • Management cited a strong order book, healthy pipeline and robust execution capability as the basis for revenue visibility.
  • FY27 described as an important year in the growth journey, with focus on accelerating execution and operational efficiency.

Order Pipeline & Competitive Environment · Kamal Gupta (MD) and Nalin Gupta (MD)

  • Competition described as 'quite competitive' at present, though expected to loosen as the order pipeline builds over the next 10-12 months.
  • INR50,000-100,000 crore of projects planned in Maharashtra alone over the next 10-12 months.
  • MoRTH has tightened prequalification and net-worth conditions, which management expects to reduce competition on niche projects.
  • INR3,000 crore of bids already submitted, with INR30,000 crore of projects to be bid in the next six months: metros ~INR15,000 cr, elevated corridors/roads/flyovers ~INR10,000 cr, building works ~INR5,000 cr.

Big-Ticket Project Execution: GMLR, Chennai, Vadhavan · Nalin Gupta (MD) and Kamal Gupta (MD)

  • GMLR: original five-year period, land handed over two years late; management now expects completion before end-2029, ahead of schedule.
  • At GMLR one TBM has bored more than 300 m and a second machine has entered the ground by ~8 m; both TBMs functional.
  • Chennai Elevated Corridor: ~70-75% of foundation work complete and ~2,900 precast segments cast; completion expected by December 2028 or January 2029.
  • Vadhavan project already mobilised with service road work, excavation and ground clearing underway; revenue expected from December/January.

Revenue, Margin and Capital Guidance · Kamal Gupta (MD)

  • FY27 top-line growth guidance of ~15% reiterated; H1 achieved 8% and Q2 achieved 15%, so H2 must ramp materially.
  • FY27 revenue target of around INR6,500 crores; management expects Q3 and Q4 to be better than Q2.
  • FY30 revenue target of INR10,000 crores reiterated.
  • EBITDA margin currently 14-15%, targeted to move up ~100 bps into a 15-16% range over one to two years.
  • Capex broadly unchanged at ~INR80 crores done in the quarter and ~INR150 odd crores for the year and next year.

Balance Sheet, Working Capital & Bank Limits · Kamal Gupta (MD) and Nilesh Sharma (GM, F&A)

  • Working capital cycle of 100 days against a stated band of 100-120 days; management expects to stay in the band.
  • Gross debt below INR800 crores; debt-equity of 0.23x expected to stay at 0.23-0.24x with net cash retained.
  • Mobilization advance balance ~INR627 crores, unbilled receivables INR572 crores, security deposits ~INR490 crores as at September.
  • FDs of ~INR700 crores held largely against performance guarantees (10%), mobilization advance-linked bank guarantees and collateral requirements; free FD quantum not confirmed.
  • Sanctioned limits ~INR6,230-6,290 crores with ~INR4,400 crores utilised (~70%); non-fund-based sanctioned ~INR6,200 crores with ~INR3,500 crores utilised; fund-based ~INR780-800 crores at ~42% utilisation plus a term loan of ~INR400 crores taken against equipment.

Strategy: HAM, Marine & Project Selection · Nalin Gupta (MD) and Kamal Gupta (MD)

  • Management stated it is 'not thirsty for orders', quotes projects at its margins and will not quote at any rate.
  • Selective exploration of NHAI HAM (deferred payment) projects, mainly NHAI, where competition is lower; EPC remains the primary focus and BOT is excluded.
  • Marine/coastal road capability already demonstrated via Chennai (Cooum River), Navi Mumbai coastal road, Mothagaon sea bridge and riverfront development; larger-ticket marine projects to be explored as they emerge.
  • Prefers prestigious, technically complex marquee projects such as the INR1,600 crores Lagoon Bridge (Malad) with 125 m pylon height and 800 tonnes of cable stay, GMLR, Anand Nagar-Saket, Chennai Elevated Corridor and Uttan-Virar.

In their words

If you see our order book, which is INR22,700 crores as of now, we are not thirsty for orders. We do not quote projects at any rate. We are quoting projects at our margins.
Kamal Gupta (Managing Director, J. Kumar Infraprojects Limited)
Delhi Metro, they have canceled the order. It did not get converted into order book because there is some change in the project that they are doing, and because of which the project cost is also likely to go up.
Nalin Gupta (Managing Director, J. Kumar Infraprojects Limited)
If you look at the tunnel boring machines, this is a myth that it was being supplied by the Chinese companies. ... Machine supply for TBM is absolutely no issue.
Nalin Gupta (Managing Director, J. Kumar Infraprojects Limited)

To check next time

What management committed to on this call, or the dates they gave.

  • Check whether Q3-Q4 revenue ramps enough for more than 15% YoY growth and about ₹6,500 crore FY27 revenue.
  • Check H2 order inflow of ₹3,000-5,000 crore against the ₹8,000-10,000 crore FY27 target.
  • Check Q3 depreciation after the TBM launch; management indicated roughly ₹50-52 crore while retaining prior guidance.
  • Check Vizag monetization after the pending local-government layout approval; cash was expected over the coming two quarters.
  • Check Vadhavan revenue recognition from December or January after service-road work started.
  • Check completion of the Worli-Sewri and Sewri-Navi Mumbai Airport connectors and Metro Line 2B during FY27.

Transcript

Read along with the recording

The whole call, 233 lines from 13 speakers over 45:58. Click any line to hear it, jump to the Q&A, or find a word. Free with an account.

Sign up freeLog in

The stock after the call

After the callCloseStockNifty 50
Next session Mon 16 Nov 2026₹433.95−0.60%+0.58%

From the close of Fri 13 Nov 2026, ₹436.55: the last close before the call, which began at 14:30 IST. Adjusted daily closes; the move includes everything else that happened in those sessions.

Jkumar Infr.ltd.'s other calls