Jkumar Infr.ltd. Q4 FY26 earnings call

Wed 20 May 2026JKIL

In brief

FY26 was flat YoY; FY27 revenue and PAT guided 15% higher; ₹6,300 cr new orders booked/L1 in FY27 vs ₹1,000 cr in FY26.

Management's tone
Confident
What was said
Leaned positive
Guidance
Guidance raised
Analyst pushback
Medium
Stock, next session
−1.96% (Nifty 50 +0.17%)
  • FY26 revenue grew 1% to ₹5,723 cr, EBITDA at ₹823 cr (14.4% margin) and PAT at ₹387 cr as execution slowed after a slack order intake year.
  • Q4 FY26 revenue declined 3% YoY to ₹1,585 cr; EBITDA fell 5% to ₹224 cr (14.1% margin) and PAT fell 5% to ₹110 cr.
  • Net debt was cash-positive at ₹264 cr and working capital improved to 99 days from 112 days as on 31 March 2026.
  • Order book stood at ₹18,554 cr at FY26-end and has risen to a lifetime high of ~₹25,000 cr with ₹4,500 cr booked plus ₹1,770 cr L1 in FY27.
  • FY27 guided for 15% revenue and PAT growth (to cross ₹6,500 cr) with EBITDA margin moving to 15-16%; ₹9,000-10,000 cr order inflow targeted.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q4 FY26

This quarterA year agoLast quarterMargin
Revenue₹1,585 cr−2.9%+20.9%
EBITDA (excl. other income)₹225 cr−4.1%+28.4%14.2% (14.4% a year ago)
Net profit₹110 cr——6.9% (0% a year ago)
EPS (₹)₹14.58−3.4%+33.5%

From the company's filed results for the quarter ended 31 Mar 2026 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • FY26 called a year of consolidation: revenue +1%, EBITDA flat at ₹823 cr, PAT flat at ₹387 cr as order intake fell to ~₹1,000 cr vs ₹2,500 cr in FY24-25, slowing execution.
  • Q4 FY26 revenue declined 3% YoY to ₹1,585 cr and EBITDA fell 5% to ₹224 cr on slower execution of new projects pending preparatory and design approvals.
  • EBITDA margin slipped to 14.1% in Q4 from 14.4% YoY on lower operating leverage and higher depreciation after ₹280 cr (FY25) and ₹400 cr (FY26) of capex.
  • PAT margin held at ~7% in Q4 FY26; net debt stayed cash positive at -₹264 cr and working capital improved to 99 days from 112 days as receivables normalised.
  • Management flagged zero impact from commodity prices and geopolitical changes as all contracts carry price variation/escalation clauses covering steel, cement, POL and labour.

The numbers management led with

  • Order book (as of call date): INR25,000 crores (lifetime high); composition: metro 11%, elevated corridors/flyovers 51%, road/tunnel 18%, others 20%
  • Q1 FY27 new order intake: INR6,300 crores (INR4,500 crore LOA + INR1,770 crore L1 on Delhi Metro D207)
  • FY27 order intake target: INR9,000-10,000 crores (already INR6,300 crore booked)
  • Maharashtra project pipeline (12 months): INR1 lakh crore expected from Maharashtra metro/elevated corridor projects in next 12 months

Guidance

Guidance on this call

WhatForWhat management said
Top-line growthFY27we are expecting a growth of around 15% in the top line
Bottom-line growthFY2715% increase in top line and bottom line is what we are expecting
EBITDA marginFY27our endure would be to increase it from 14%, 15% to 15%, 16%
PAT marginFY27the PAT would be around 7%
Revenue targetFY27we should be crossing INR6,500 crores
Order intakeFY27order book close to around ₹9,000 crores to ₹10,000 crores for the full year
CapexFY27around INR200 crores to INR250 crores for the next coming 2 years, that is FY27 and '28
CapexFY28around INR200 crores to INR250 crores for the next coming 2 years, that is FY27 and '28
Revenue targetFY28in the next year, that is FY28, we are one year behind from the target...in '28 we will do INR7,500 crores

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY25 revenueFY25₹5,600–5,700 cr (on the Q4 FY24 call)₹5,693 cr, within the range
FY26 top line growthFY2615% (on the Q4 FY25 call)0.5%, below the figure guided
Top line growthFY2615–16% (on the Q1 FY26 call)0.5%, below the range
FY26 revenue targetFY26₹6,200–6,300 cr (on the Q2 FY26 call)₹5,723 cr, below the range
FY26 revenue growthFY2611% (on the Q2 FY26 call)0.5%, below the figure guided
FY26 EBITDA marginFY2614–15% (on the Q2 FY26 call)14.2%, within the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

Balance sheet, capex and funding

  • Net debt was negative ₹264 cr (cash positive) as on 31 March 2026; not raised despite higher order book.
  • Working capital improved to 99 days in FY26 from 112 days in FY25; unbilled revenue ₹578 cr, mobilisation advance ₹706 cr, retention ₹464 cr.
  • Capex guidance of ₹200-250 cr per year for FY27 and FY28, including incremental capex for new orders of ~₹6,500 cr booked/L1.
  • FY25 capex ₹280 cr; FY26 capex ₹400 cr; ₹680 cr of capex in two years will keep depreciation elevated.
  • Q4 FY26 quarterly depreciation ~₹66 cr versus ₹40-45 cr earlier trend; expected to stay elevated.
  • TBM financed as 3-year term loan; ~10% repaid from receivables; full repayment targeted along with project execution.

The industry, as management sees it

Management is highly positive on infrastructure sector trajectory — last 2 years were slack but Q1 FY27 shows sharp recovery with INR6,300 crore intake in a single quarter. Maharashtra CM War Room monitoring each flagship project fortnightly, accelerating approvals. INR1 lakh crore of metro/elevated corridor opportunities expected in Maharashtra alone over 12 months.

Risks management named

  • Labour shortage of 10-15% at sites in Q1 due to seasonal factors (marriages, farming, elections)
  • Execution timeline for new INR6,300 crore orders: contributions expected from Q2-Q3 FY27
  • Timing risk on INR15,000-20,000 crore bid pipeline if project awards slip beyond 3-6 months
  • Possibility of order intake falling short of INR10,000 crore target if market conditions change

Q&A

Q&A was dominated by questions on the order book pipeline and execution timelines — Vaibhav Shah (JM Financial) and Parikshit Kandpal (HDFC Securities) were the most probing analysts. Order book strength (INR25,000 crore lifetime high, INR6,300 crore Q1 intake) and the Maharashtra metro opportunity (INR1 lakh crore over 12 months) generated the most engagement. Management was confident and direct on all project execution questions, providing granular updates on GMLR TBM status (SAT June 8) and Chennai metro (50% complete). Mild pushback came from Shravan Shah (Dolat Capital) on whether INR10,000 crore order intake target is too conservative and from Girija Ray on margin reconciliation despite commodity cost claims. No topics were deflected — management answered all questions directly or partially, with only the TBM capex amount being withheld as price-sensitive.

Asked for a number, answered without one

  • Incremental quarterly depreciation from GMLR TBM: Said TBM costed into the project and amortised over 3 years internally vs ~8 years in books; no quarterly number given.
  • TBM cost, loan amount and balance drawdown: Declined as price-sensitive; said TBM already procured and financed, ~10% repaid, to be fully repaid in 2-3 years.
  • Buyback plans: Said buyback on the cards but waiting for financial comfort; Board discussed it yesterday and decided to pay dividend for now.
  • Vizag investment property profit: Declined exact number; said ₹90 cr of ₹106 cr loan already paid; expects good profitability and ROI but no figure.

Every question, with its answer

  1. 1. Order book pipeline

    Jainam Jain, DAM Capital

    Question. What is the current bid pipeline for the fiscal year?

    Answer, Dr. Nalin Gupta, Managing Director. Already bagged orders of INR4,500 crores with L1 of INR1,770 crores totalling INR6,300 crores, taking order book to approx INR25,000 crores. Expect order book close to INR9,000-10,000 crores for full year. Projects worth INR15,000-20,000 crores expected to be bid in FY27.

    Follow-up. Are there major opportunities in Maharashtra this year, especially metro segment?

    Answer. Delhi Metro D207 INR1,770 crores just won. Metro opportunities: Mumbai Metro Line 5, 13, 10 (Gaimukh to Dahisar). Bombay, Delhi, Pune coming up with metro projects. Last 2 years were slack (only INR1,000 crore booked in FY26) but Q1 itself saw INR6,300 crore — very positive year.

  2. 2. Working capital

    Jainam Jain, DAM Capital

    Question. What are the working capital components — retention money, unbilled revenues, mobilisation advances?

    Answer, Vasant Savla, Chief Financial Officer. Unbilled revenue INR578 crores; mobilisation advance INR706 crores; retention INR464 crores.

  3. 3. FY27 guidance

    Vaibhav Shah, JM Financial

    Question. What kind of revenue growth and margins are we looking for FY27?

    Answer, Dr. Nalin Gupta, Managing Director. Expecting 15% growth in top line — should cross INR6,500 crores. EBITDA should increase from 14-15% to 15-16%; PAT would be around 7%. Bottom-line also expected to grow 15%.

    Follow-up. Is the 15% revenue guidance conservative given the strong order backlog?

    Answer. There is a possibility of doing better but given last year's bad experience where we expected orders and couldn't get them, I'd like to commit to 15%. J. Kumar's policy is not to book orders without good bottom line — we waited 2 years rather than book at low margins. The orders now bagged are at similar margins we target.

  4. 4. Capex

    Vaibhav Shah, JM Financial

    Question. What are the capex plans for FY27?

    Answer, Dr. Nalin Gupta, Managing Director. INR200-250 crore for next 2 years (FY27 and FY28) including incremental capex and pending capex for GMLR and Chennai.

  5. 5. Execution timeline

    Vaibhav Shah, JM Financial

    Question. When do we expect new orders (Vadhavan, vestibule, Lucknow) to start contributing to execution?

    Answer, Dr. Nalin Gupta, Managing Director. Initial 6-9 months involves preparatory work (soil investigation, survey, geology, design approvals). Contribution expected from Q2 or Q3 FY27.

    Follow-up. Update on Chennai NHAI and GMLR execution?

    Answer. Chennai: foundation and substructure work in line; casting yard fully operational; already casting segments. GMLR: 3.5 km of tunnels already cast; INR800 crore COS received; new casting yard acquired and being developed; shaft excavated; both TBMs arrived at site; one TBM in advanced assembly; SAT on June 8; second TBM 1.5 months behind.

  6. 6. Execution outlook

    Vaibhav Shah, JM Financial

    Question. Can we expect 30% execution on Chennai and 20% on GMLR in FY27?

    Answer, Dr. Nalin Gupta, Managing Director. Yes, around 20-30% output expected from both projects in FY27.

  7. 7. Geopolitical impact

    Parikshit Kandpal, HDFC Securities

    Question. Are we facing any execution slowness in Q1 due to geopolitical issues or client-initiated slowdown?

    Answer, Dr. Nalin Gupta, Managing Director. Zero impact due to geopolitical changes. Maharashtra CM War Room monitoring each flagship project fortnightly — problem-solving is improving. No negative impact; being EPC, no material implications.

    Follow-up. Have peers highlighted labour shortage? What is current site labour vs peak? How does fixed-price vs pass-through commodity pricing work?

    Answer. Labour shortage of 10-15% at all sites is seasonal (post-elections, April-May, marriages, farming) — routine annual occurrence, not alarming. All contracts have price variation and escalation clauses covering steel, cement, POL, labour and others — fully covered with no impact on bottom line. Monthly running bills include PV component approved by the engineer along with work done — no separate approval required.

  8. 8. Metro project pipeline

    Parikshit Kandpal, HDFC Securities

    Question. Status of Metro Lines 8, 14, Gold Line, Vikhroli-Ghansoli connector and Uttan-Virar project timelines?

    Answer, Dr. Nalin Gupta, Managing Director. Uttan-Virar elevated corridor (similar to MTHL/coastal road) tender expected from MMRDA in 3-6 months. Metro Lines 5, 10, 13, 14 in advanced stage — tender process expected in 3-6 months. Vikhroli connector: not very sure, would not like to make false statement.

    Follow-up. How big is the combined pipeline for Lines 5, 10, 13, 14 and Uttan-Virar?

    Answer. Uttan-Virar alone is more than INR50,000-60,000 crore. Together INR1 lakh crore expected from Maharashtra in 12 months. J. Kumar has significant market share in Maharashtra. We expect to cross INR10,000 crore order intake this year.

  9. 9. Margin dynamics

    Girija Ray, Nirmal Bang Securities

    Question. We maintained 14% margins despite claiming zero geopolitical impact — but construction cost as % of revenue increased in Q4. How do you reconcile this?

    Answer, Dr. Nalin Gupta, Managing Director. Price escalation clauses cover steel, cement, POL, labour, others — these get covered in monthly running bills. When analysed on annual basis even post-COVID steep increases resulted in only 0.5% variance — immaterial. EPC contracts with PV clauses have zero impact; BOT contracts are different.

    Follow-up. Confirm the INR6,000 crore new order inflow (EPC Maharashtra, Lucknow, Metro Rail) is excluding GST?

    Answer. All order book figures discussed are excluding GST. INR18,500 crores (March) and INR25,000 crores (current, including INR1,770 crore L1) are both excluding GST.

  10. 10. TBM depreciation

    Jahnvi Mishra, Green Portfolio

    Question. TBM was guided to start in February — can you quantify the incremental quarterly depreciation once GMLR TBM becomes operational?

    Answer, Dr. Nalin Gupta, Managing Director. We never said TBM would start in February — we said machine would start moving in shaft from February, which we have. TBM on track, ahead of schedule (contract allowed 1 year; doing it in less than 9 months). Depreciation will be as per books of accounts; machine cost is in the project. Internal target to complete GMLR in 3-3.5 years (contract allows 4 years); will amortise TBM faster.

    Follow-up. Can you quantify the incremental quarterly finance cost for the TBM?

    Answer. TBM financed via 3-year term loan; 10% already repaid from receivables. No major additional capex needed. Full repayment in 2-3 years along with project progress; option to early repay.

    Partly answered.

  11. 11. Order book definition

    Sidhant Lodaya, Sanshi Fund

    Question. When you say order book of INR10,000 crore in FY27, is it new order intake or year-end order book?

    Answer, Dr. Nalin Gupta, Managing Director. It is new order intake. Current order book INR25,000 crores minus INR6,500 crore top line will still be ~INR19,000 crores even with zero new intake.

    Follow-up. Does the INR10,000 crore include the existing INR4,500 crore LOA?

    Answer. Yes, INR10,000 crore includes INR4,500 crore LOA already received. L1 of INR1,770 crore expected within 15-30 days. Additional INR2,700-3,000 crore needed over and above INR6,300 crore to meet target.

  12. 12. Coastal road execution

    Nishit Jain, SNJ Investments

    Question. Progress on Versova-Dahisar Coastal Road?

    Answer, Dr. Nalin Gupta, Managing Director. Most approvals received; minor environmental approvals pending. Mangrove cutting 10% complete; temporary access bridge material procured; labour contractor in place. 100+ piles, 14-15 foundations, 7-8 piers cast. Work physically started; casting yard being set up. Should see decent top line contribution this year.

    Follow-up. Is the casting yard setup done or still ongoing?

    Answer. Casting yard is being set up; all work is on-site and casting yard is in setup stage.

  13. 13. TBM capex

    Bhavin Modi, Anand Rathi Group

    Question. How much has been spent on TBM? How much capex remains? What is the loan amount and balance drawdown?

    Answer, Dr. Nalin Gupta, Managing Director. Cannot share exact TBM price — price-sensitive. TBM fully procured and financed; no additional major capex needed. 10% already repaid from receivables; full repayment in 2-3 years along with project execution.

    Follow-up. Has Aarey tree cutting permission for GMLR been received?

    Answer. 100% permission received — not from Aarey but from Supreme Court. Tree cutting and transplantation completed by December; shaft excavated and cut executed; issue fully resolved.

    Partly answered.

  14. 14. FY28 outlook

    Shravan Shah, Dolat Capital

    Question. Given 15% growth this year, can we see 18%+ next year to catch up on lost FY26 growth?

    Answer, Dr. Nalin Gupta, Managing Director. You can look at it that way but I won't commit right now. Want things to start moving. Will be able to comment in Q2-Q3. You're not wrong in that view.

    Follow-up. To achieve 15% growth, will we see at least 10%+ growth from Q1 itself, or will it be backend-loaded?

    Answer. Not sure about Q1 at this stage. Q2 onwards will see the increase to achieve 15% top line.

    Partly answered.

  15. 15. Order intake ambition

    Shravan Shah, Dolat Capital

    Question. Given INR1 lakh crore opportunity in Maharashtra and INR6,300 crore already booked, why not target INR13,000-15,000 crore inflow? Will we bid independently or through JV for these large projects?

    Answer, Dr. Nalin Gupta, Managing Director. In 2024 we bagged INR11,000 crore — capacity is not the constraint. But we want to be realistic given last 2 years' experience (only INR2,500 crore in FY25, INR1,000 crore in FY26). If projects slip, timing matters. We will cross INR10,000 crore this year for sure. Given opportunity, we can even bag INR20,000 crore — our mindset is not to stay at INR10,000 crore. JV vs independent will be project-specific depending on size and technical requirements.

    Follow-up. Status of INR106 crore Vizag investment — will it be off balance sheet by Q2? Expected profit INR70-80 crore?

    Answer. Out of INR106 crore loan, INR90 crore already repaid via plant and machinery sale and internal accruals. Remaining land in Vizag with high data centre demand — expect good profitability. Should be out by Q2.

  16. 16. Chennai project

    Chandramouli Jagannath, Individual Investor

    Question. How is the Chennai flyover project progressing given the new state government formation?

    Answer, Dr. Nalin Gupta, Managing Director. Project at 50% completion — foundation and substructure done, casting yard operational. Once a project has physically started and substantial work completed, change of government has no negative impact. Only projects not yet started could be affected.

    Follow-up. Is there further room to improve working capital? And will bottom line grow slightly above top line given efficiency gains?

    Answer. Working capital improved to 99 days vs 112 days. Endeavour is to increase EBITDA from 14-15% to 15-16%. Expect in 6-8 quarters to increase EBITDA basis points further. Bottom line should grow in line with top line at 15%.

  17. 17. Capital return

    Chandramouli Jagannath, Individual Investor

    Question. Given attractive valuation, cash surplus and debt-free status, do you plan a share buyback?

    Answer, Dr. Nalin Gupta, Managing Director. Point well noted and on our cards. Board discussed buyback vs dividend yesterday — decided to pay dividend this year but buyback remains on the agenda going forward. Dividend at ~10% of PAT.

  18. 18. Depreciation

    Vaibhav Shah, JM Financial

    Question. Depreciation was INR66 crore in Q4 — a jump from INR40-45 crore quarterly run rate. How does it look going forward?

    Answer, Dr. Nalin Gupta, Managing Director. Going forward, similar level — around INR65 crore per quarter. FY25 capex ~INR280 crore; FY26 capex ~INR400 crore; INR600 crore capex in last 2 years. Elevated depreciation run rate will continue.

  19. 19. Billion-dollar target

    Dinesh, Kirti Creation

    Question. In August 2024 con call you set a $1 billion revenue target. Given improved order book (INR25,000 crore), pan-India expansion, improved margins, debt-free status, is the $1 billion target still achievable for FY27?

    Answer, Dr. Nalin Gupta, Managing Director. When we said $1 billion, dollar was INR75. $1 billion = INR7,500 crore. We are running 1 year behind that target. FY27 top line of INR6,500 crore (15% growth) will be followed by INR7,500 crore in FY28 — matching the $1 billion milestone at current exchange rates. Need to cover INR3,500 crore gap from last 2 years of low order intake. If we do INR10,000 crore orders this year, we can catch up by FY28.

    Follow-up. As a purely domestic company, does rupee depreciation affect your margins given imports (TBM, equipment)?

    Answer. Price escalation clauses cover dollar, euro, yen, RMB-denominated imports. For dollar contracts like Delhi Metro, we quote in dollars to cover 200-250 expats — giving zero effect. No hit or benefit from rupee movement.

What was said

Topic by topic, in the order it was spoken

FY26 Performance Overview · Dr. Nalin Gupta (MD)

  • FY26 revenue from operations grew 1% to INR5,723 crores vs INR5,693 crores in FY25; EBITDA INR823 crores (14.4% margin) vs INR826 crores (14.5%); PAT INR387 crores (6.8%) vs INR391 crores (6.9%)
  • Q4 FY26 revenue moderated 3% to INR1,585 crores vs INR1,633 crores in Q4 FY25; EBITDA INR224 crores (14.1%) vs INR235 crores (14.4%)
  • FY26 described as year of consolidation; impact largely operational and time-related, stemming from external factors that temporarily slowed execution
  • Company maintained strong balance sheet and adequate liquidity, ensuring resilience and continuity of operations

Order Book & Bid Pipeline · Dr. Nalin Gupta (MD)

  • Total order book as of March 31, 2026: INR18,554 crores; composition: metro projects (elevated + underground) 11%, elevated corridors and flyovers 51%, road and tunnel 18%, others 20%
  • Q1 FY27 intake: INR4,500 crores LOA received + INR1,770 crores L1 (Delhi Metro D207) = INR6,300 crores total, taking order book to INR25,000 crores (lifetime high)
  • FY27 order intake target: INR9,000-10,000 crores; additional INR2,700-3,000 crores beyond already-booked INR6,300 crores needed to meet target
  • Bid pipeline: INR15,000-20,000 crores of projects expected to be bid in FY27
  • Maharashtra pipeline: INR1 lakh crore of metro/elevated corridor projects expected over next 12 months (Metro Lines 5, 10, 13, 14 and Uttan-Virar INR50,000-60,000 crore elevated corridor)
  • Uttan-Virar tender (MMRDA) expected in 3-6 months; Metro Lines 5, 10, 13, 14 tenders expected in 3-6 months; all in advanced stages

Project Execution Updates · Dr. Nalin Gupta (MD)

  • Chennai NHAI metro project: 50% complete; foundation and substructure work in line; casting yard fully operational
  • GMLR tunnel project: 3.5 km of tunnel already cast in casting yard; INR800 crore COS received; new casting yard acquired and being developed; shaft excavated; both TBMs arrived at site; one TBM in advanced assembly stage; SAT scheduled June 8, 2026
  • Versova-Dahisar Coastal Road Package B: approvals largely received; mangrove cutting 10% complete; 100+ piles, 14-15 foundations, 7-8 piers cast; traffic permissions obtained; casting yard being set up
  • New orders (Vadhavan, vestibule, Lucknow) to start contributing from Q2-Q3 FY27 after preparatory work (soil investigation, design approvals)
  • Expected 20-30% output from both Chennai and GMLR in FY27

Working Capital & Financial Position · Vasant Savla (CFO)

  • Working capital: 99 days in FY26 vs 112 days in FY25 (improved by 13 days)
  • Net debt as of March 31, 2026: negative INR264 crores (cash positive)
  • Unbilled revenue: INR578 crores; mobilisation advance: INR706 crores; retention money: INR464 crores

FY27 Guidance & Outlook · Dr. Nalin Gupta (MD)

  • FY27 revenue growth guidance: 15% to cross INR6,500 crores; bottom-line growth also guided at 15%
  • EBITDA margin guidance: 14-15% to 15-16% (improvement of ~100 bps); PAT margin guided at ~7%
  • Capex guidance: INR200-250 crore each for FY27 and FY28 (including GMLR and Chennai remaining capex and incremental capex)
  • Depreciation run rate: elevated at INR65 crore per quarter going forward (capex of INR600 crore done in last 2 years)
  • TBM financed via 3-year term loan; 10% already repaid; full repayment expected in 2-3 years with project progress

Margin & Commodity Cost Dynamics · Dr. Nalin Gupta (MD)

  • All EPC contracts covered under price variation and escalation clauses (5 components: steel, cement, POL, labour, others) — zero impact on bottom line from commodity/ geopolitical changes
  • Price variation approved by engineer along with monthly running bill; no separate budget approval required
  • Geopolitical changes: zero impact on execution or margins for EPC contracts; positive push from Maharashtra CM War Room monitoring
  • Labour shortage of 10-15% in Q1 is seasonal (marriages, farming, post-elections) — routine, temporary issue

Asset Divestment & Buyback · Dr. Nalin Gupta (MD)

  • Vizag land/asset divestment: INR106 crore loan taken for PSL; INR90 crore already repaid via plant and machinery sale and internal accruals; remaining land expected to be sold in Q2 FY27 with good profitability and ROI
  • Share buyback discussed at board level; decided to pay dividend this year but buyback remains on the cards for future
  • Dividend policy maintained at ~10% of PAT

In their words

J. Kumar's policy is not to book orders without good bottom line. We waited for 2 years rather than book at low margins. The order that the company has bagged is with similar margins which is our target.
Dr. Nalin Gupta (MD, J. Kumar Infraprojects)
We have hit an all-time high — lifetime high order book of INR25,000 crores as we speak now. Given opportunity, we can even bag INR20,000 crores. Our mindset is not to stay at INR10,000 crores.
Dr. Nalin Gupta (MD, J. Kumar Infraprojects)
GMLR TBM — contract allowed 1 year to start; we are doing it in less than 9 months. By June 8, we will do the site acceptance test to start drilling the tunnel.
Dr. Nalin Gupta (MD, J. Kumar Infraprojects)

To check next time

What management committed to on this call, or the dates they gave.

  • TBM site acceptance test on 8 June at GMLR; both TBMs to start drilling thereafter (one with 1.5 month lag).
  • New order wins beyond current ₹6,300 cr; FY27 target of ₹9,000-10,000 cr requires ₹2,700-3,000 cr more.
  • Tendering of Metro Lines 5, 10, 13, 14 and Uttan-Virar elevated corridor expected in 3-6 months.
  • Execution contribution from new orders (Vadhavan, vestibule, Lucknow) expected from Q2-Q3 FY27 after preparatory work.
  • Capex run rate of ₹200-250 cr/year and Q1 FY27 working capital after ₹6,300 cr of new orders booked.
  • Chennai NHAI and GMLR execution at 20-30% output ballpark for FY27.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Wed 20 May 2026₹473.30−1.96%+0.17%
5 sessions Tue 26 May 2026₹504.85+4.58%+1.25%
20 sessions Wed 17 Jun 2026₹492.60+2.04%+1.98%

From the close of Tue 19 May 2026, ₹482.75: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.