Jkumar Infr.ltd. Q2 FY26 earnings call

Fri 7 Nov 2025JKIL

In brief

H1 FY26 revenue grew 10% to ₹2,826 cr at 14.6% EBITDA margin; FY26 revenue target trimmed to ₹6,200-6,300 cr on monsoon delay.

Management's tone
Confident
What was said
Even-handed
Guidance
Guidance cut
Analyst pushback
Low
Stock, next session
−5.43% (Nifty 50 −0.07%)
  • H1 FY26 revenue grew 10% YoY to ₹2,826 cr with EBITDA margin at 14.6% and PAT up 10% to ₹195 cr at 6.9% margin.
  • FY26 revenue target trimmed to ₹6,200-6,300 cr (~11% YoY growth) from earlier ₹6,500 cr on extended monsoon impact on Q2 execution.
  • Order book at ₹20,160 cr on Sept 30; secured ₹150 cr in H1 and L1 in ₹1,200 cr Lucknow project; ₹5,000-6,000 cr inflow targeted for FY26.
  • EBITDA margin guidance held at 14-15% for FY26, with 15-16% target pushed to next two years from earlier 6-8 quarter horizon.
  • H1 capex at ₹398 cr; full-year FY26 capex ~₹500 cr (incl. ₹100 cr maintenance); FY27 capex guided at ~₹200 cr.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY26

This quarterA year agoLast quarterMargin
Revenue₹1,343 cr+3.9%−9.5%
EBITDA (excl. other income)₹195 cr+3.2%−10.3%14.5% (14.6% a year ago)
Net profit₹90.7 cr+0.6%−12.2%6.8% (7% a year ago)
EPS (₹)₹11.97+0.4%−12.4%

From the company's filed results for the quarter ended 30 Sept 2025 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • Extended and early monsoon through October compressed Q2 execution; H1 still delivered 10% revenue growth and 14.6% EBITDA margin on resilient underlying execution. (one-off)
  • Q2 is historically the weakest quarter of the year for J. Kumar; management expects H2 FY26 to drive acceleration in execution and revenue. (one-off)
  • All EPC contracts carry price variation clauses covering steel, cement, labor and POL, securing 14-15% EBITDA margins on the existing order book.
  • GMLR TBM (CWIP of ₹292 cr) reached job site and is under assembly; depreciation to start only from Q2 FY27, so no P&L drag from this capex in FY26. (accounting)

The numbers management led with

  • Total order book: INR20,160 crores as of 30 September 2025
  • Order inflow target FY26: INR5,000-6,000 crores
  • L1 status: L1 in INR1,200 crores convention centre in Lucknow
  • Bid pipeline H2 FY26: INR20,000-25,000 crores of projects to bid in H2 FY26
  • FY26 capex guidance: ~INR500 crores for FY26 including INR100 crores maintenance

Guidance

Guidance on this call

WhatForWhat management saidFiled
FY26 revenue targetFY26FY26 revenue target ₹6,200-6,300 cr₹5,723 cr, below the range
FY26 revenue growthFY26FY26 revenue growth ~11% YoY0.5%, below the figure guided
FY26 EBITDA marginFY26FY26 EBITDA margin 14-15%14.2%, within the range
Forward EBITDA margin targetFY27-FY28Targeting 15-16% EBITDA margin in the coming two years—
FY26 order inflowFY26FY26 order inflow ₹5,000-6,000 cr—
FY26 closing order bookFY26Closing order book of ₹20,000-23,000 cr by March 2026—
FY26 capexFY26FY26 capex ~₹500 cr including ₹100 cr maintenance—
FY27 capexFY27FY27 capex ~₹200 cr—
Working capital daysFY26Working capital days guided at 120-130 days—
FY26 gross debtFY26FY26 gross debt ~₹800 cr (vs ~₹750-770 cr currently)—
Forward revenue growth aimFY27Aim to grow 16-17% going forward aided by GMLR tunnel inflows—

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

What changed since the Wed 30 Jul 2025 call

WhatOn the Wed 30 Jul 2025 callOn this call
FY26 revenue growth target (cut)FY26 revenue growth guidance maintained at 15-16% (~₹6,500 cr)Target revised to ₹6,200-6,300 cr (~11% growth) on extended monsoon impact
EBITDA margin 15-16% target timing (restated)15-16% margin over next 6-8 quarters from current 14-15%15-16% target reframed to next two years from 14-15%
FY26-27 capex plan (restated)Capex of INR450-500 cr over FY26-27 for TBMs and equipment plus INR100 cr annual maintenanceFY26 capex ~₹500 cr (incl. ₹100 cr maintenance); FY27 capex ~₹200 cr
Forward revenue growth aim (held)Looking at 16-17% growth for at least a couple of yearsAim to grow at 16-17% going ahead; GMLR tunnels to help
PSL Vizag asset monetisation priority (not repeated)Monetise PSL Vizag asset and complete loan repayment by December 2025Not mentioned on this call
GMLR TBM delivery status (achieved)GMLR TBMs arrivingTBM has reached job site, under assembly, to be capitalised; depreciation starts Q2 FY27

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY25 revenueFY25₹5,600–5,700 cr (on the Q4 FY24 call)₹5,693 cr, within the range
FY26 top line growthFY2615% (on the Q4 FY25 call)0.5%, below the figure guided
Top line growthFY2615–16% (on the Q1 FY26 call)0.5%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

Balance sheet, capex and funding

  • Gross debt ~₹750 cr; net cash position at ₹124 cr (net debt negative).
  • Working capital ~₹775 cr as on Sept 30, expected to stay at ~₹800 cr by FY26 close; days guided at 120-130.
  • H1 capex ₹398 cr; FY26 capex ~₹500 cr (incl. ₹100 cr annual maintenance); FY27 capex guided at ~₹200 cr.
  • Mobilization advance ~₹900 cr (of which ~₹500 cr is interest-bearing); TBM funded partly via term loan on deferred credit.
  • Unbilled revenue ~₹695 cr; retention money ~₹389 cr as on Sept 30.
  • Non-fund based limit ~₹5,000 cr with ~75% utilization; QIP only an enabling resolution with no immediate plans to launch.

The industry, as management sees it

Management acknowledged a slowdown in EPC order inflows in the prior financial year but is working across seven states and multiple verticals (metros, elevated corridors, roads, tunnels, water, buildings) to drive H2 bid pipeline of INR20,000-25,000 crores. They see no industry-level headwinds in the near term and expect faster order conversion once key coastal road and metro projects move from DPR to bidding stage.

Risks management named

  • Extended and early monsoon impacting on-site execution (Q2 FY26 affected)
  • Industry-level slowdown in EPC order inflows in the prior financial year
  • QIP enabling resolution kept alive; dilution risk if large capex-heavy orders are bagged
  • Mobilization advance of INR900 crores, of which INR500 crores is interest-bearing
  • Depreciation and finance cost step-up once TBM is capitalized from Q2 FY27

Q&A

Q&A was friendly and orderly across ten analyst participants, with the dominant theme being execution catch-up after a monsoon-hit Q2. Most pointed pushback came on the lowered revenue guidance and the still-active QIP enabling resolution, where management defended its conservative stance and reiterated no immediate dilution plans. Operational depth was probed on TBM commissioning timing, Chennai elevated corridor status, Versova-Dahisar coastal road clearances, and the working capital and mobilization advance composition; management provided specific data points on each. No major surprises emerged, with the call functioning as a confirmation of H2 acceleration thesis.

Not answered directly

  • Timing and quantum of any QIP raise
  • Exact GMLR tunneling revenue contribution in FY26
  • Specific execution percentage on Chennai elevated corridor
  • Tender timelines for Dahisar-Virar and Virar-Uttan coastal projects

Asked for a number, answered without one

  • QIP fundraising size and timing: It would be little premature for me to reply to that... just an enabling resolution... no immediate plans; depends on nature of work bagged and working capital requirement.
  • Chennai Elevated Corridor execution progress: Individually, I may not have the figure right now, but my people will pass on you the figures.
  • GMLR Goregaon execution percentage this year: We cannot give you that exact number... four to five months has been balanced... 20% would be too optimistic... huge figure will be unpractical.

Every question, with its answer

  1. 1. Order inflows and L1 pipeline

    Aditya Sen, Findoc

    Question. Can you throw some light on the quantum of orders in advanced stages or L1, and will we be able to sustain the target of approximately 4,000 to 5,000 inflows for the financial year? Any industry-level headwinds in order inflows?

    Answer, Kamal Gupta, Managing Director. We have already secured around INR150 crores of projects and are L1 in INR1,200 crores for a convention centre in Lucknow, expecting these orders very soon. We are very confident of order inflow of around INR5,000 to INR6,000 crores in FY26 with a closing order book of INR20,000 to INR23,000 crores by March 2026. We don't see any industry-level headwinds.

    Follow-up. There was some decline in execution, was that because of the extended monsoon or other reasons?

    Answer. Yes, the monsoon this year started early and continued till October, affecting the top line. That was the main reason. Overall, H1 still delivered around 10-11% growth.

  2. 2. FY26 revenue guidance and QIP plans

    Diwakar Rana, Prudent Equity

    Question. Are you maintaining the 15% growth guidance for FY26? What is the total amount of orders bagged in H1? And any plans for the QIP?

    Answer, Kamal Gupta, Managing Director. Previous guidance was INR6,500 crores; we now expect INR6,200-6,300 crores for FY26, around 11% YoY growth, because Q2 was weak on extended monsoon. We secured INR150 crores in H1 and are L1 in INR1,200 crores Lucknow project. QIP is just an enabling resolution, no immediate plans; will depend on nature of work bagged and working capital needs.

    Follow-up. Can you explain the nature of the INR292 crore CWIP and the INR385 crore cash outflow?

    Answer. Majority of CWIP is from the GMLR tunnel boring machine that J. Kumar has purchased. The TBM has reached the job site and is under assembling; once assembled and put to use, it will be capitalised. The INR385 crores is not fully for this, as part is on deferred credit basis.

  3. 3. Bid pipeline, working capital and capex

    Dhananjay Mishra, Sunidhi Securities

    Question. What is the bid pipeline and which orders are expected to be finalised? How do you see working capital going ahead and what is the capex run rate?

    Answer, Kamal Gupta, Managing Director. Today we are submitting bids for a BMC flyover and river bridge of ~INR2,250 crores; Delhi Metro INR2,500 crores by month-end; and another ~INR3,000 crores tender. Total expected bidding in H2 is INR20,000-25,000 crores. Working capital will be around INR800 crores (FY25 was INR696 crores); we intend to maintain 120-130 days. Capex for H1 was INR398 crores; full-year capex of ~INR500 crores including INR100 crores maintenance. Next year capex ~INR200 crores.

  4. 4. Project execution update

    Vaibhav Shah, JM Financial

    Question. How is execution going on the Chennai elevated corridor? Have recently won projects like CIDCO INR1,000 crores, MMRDA project and NBCC projects started execution? And what execution can we expect in the current year from GMLR?

    Answer, Kamal Gupta, Managing Director. Chennai elevated is in full swing with casting yard operational, 40-45% of piles completed. CIDCO INR1,020 crores is awaiting environmental clearance expected this month, start by next month. MMRDA Anand Nagar-Saket INR1,800 crores is in full swing with revenue pouring in. NBCC Silicon Valley Noida has started with revenue. GMLR has the TBM at site with ~700 rings cast at the casting yard; main shaft excavation is ongoing. We cannot give an exact GMLR execution figure, 20% in the current year would be too optimistic; substantial revenue from next year.

    Partly answered.

  5. 5. Margin guidance and capex funding

    Aditya Sahu, HDFC Securities

    Question. What is the margin guidance for FY26? Are you maintaining earlier guidance? Any more capex on TBM? And is capex being funded from internal accruals or debt?

    Answer, Kamal Gupta, Managing Director. H1 EBITDA margin at 14.6%; we will maintain 14-15% this year and target 15-16% in the next two years; PAT margin around 7% maintained. No major TBM capex expected; the other TBM is in NCC's books. Our TBM part is more or less done. TBM funded via term loan; no additional debt for remaining capex. Current gross debt around INR75 crores [75 was stated by MD, likely INR750-800 crores] but net debt is negative INR124 crores.

    Follow-up. What is the peak debt level planned? And details of the bid pipeline?

    Answer. We are looking at order inflow of INR5,000-6,000 crores in current year. Already bagged INR150 crores and L1 in INR1,200 crores Lucknow project. Have submitted projects worth INR2,200 crores, financial bid to open. Today submitting INR2,000+ crores. Total bidding pipeline of INR20,000-25,000 crores in H2.

  6. 6. Win ratio and net debt target

    Shubham, RV Investments

    Question. What is the order-bid ratio and what is the win ratio based on past? What is the net debt target for FY26 year-end?

    Answer, Kamal Gupta, Managing Director. INR20,000-25,000 crores of bidding and INR5,000-6,000 crores inflow implies a win ratio of around 20%. We intend to maintain order book of INR22,000-23,000 crores by year-end. Current net debt position is INR770 crores gross; FY26 year-end target is similar at around INR800 crores.

  7. 7. Margins, mobilization and QIP rationale

    Venkat Subramanian, Organic Capital

    Question. How do you maintain margins in an inflationary atmosphere given a three-year order book? What costs are covered under escalation and what is the quantum of mobilization advance? With negative net debt, why dilute via QIP at current valuations?

    Answer, Kamal Gupta, Managing Director. All EPC contracts of around INR1,000 crores are covered under price variation and escalation clauses covering steel, cement, labour, POL and others. Over 45 years of experience shows escalation is fairly covered. Mobilization advance is around INR900 crores, of which about INR500 crores is interest-bearing. Net debt is negative INR124 crores. QIP is just an enabling resolution; we did not go for it last year despite approval and have no immediate plans. Decision will depend on order book nature, capex and working capital needs.

  8. 8. Growth trajectory, project pipeline and balance sheet

    Shravan Shah, Dolat Capital

    Question. Revenue guidance has been lowered from INR6,500 to INR6,200-6,300 crores. Are you still facing monsoon or labour delays? Can the company still reach INR6,500 crores? Can we look at 16-17% growth from next year? What major big projects are coming? And data points on retention money, unbilled revenue, and TBM depreciation timing.

    Answer, Kamal Gupta, Managing Director. Monsoon extended till October, hence conservative figure; we always intend to do more than what we say. We aim for 16-17% growth going ahead, helped by GMLR tunnels. Order inflow range of INR5,000-6,000 crores is tentative; could be more if projects like Virar-Uttan come on time. We are diversified across multiple geographies and verticals; bidding INR20,000-25,000 crores. Retention INR389 crores, unbilled INR695 crores, mobilization INR900 crores. TBM depreciation will start from Q2 FY27 on pro rata basis; finance cost run rate ~INR45 crores/quarter should continue.

  9. 9. Versova-Dahisar Coastal Road status

    Nishit Jain, SNJ Investments

    Question. What is the current status of the Versova-Dahisar Coastal Road of BMC? Has the department received the high court NOC? Has the casting yard setup started?

    Answer, Kamal Gupta, Managing Director. We have received Stage 1 clearance; Stage 2 is at final verge. We have MPCB and CRZ permissions; tree cutting permissions are awaited. We have completed six foundations in the roadside stretch. IIT has suggested an additional ramp, which has been submitted. Casting yard land is identified, preliminary works have started, and we have BMC approval for it.

  10. 10. Non-fund based limits

    Saurabh, Banyan Capital

    Question. What is the current non-fund based limits and the utilisation?

    Answer, Kamal Gupta, Managing Director. Non-fund based limit is around INR5,000 crores right now and utilisation is about 75%.

What was said

Topic by topic, in the order it was spoken

Opening Welcome and Strategic Framing · Kamal Gupta (MD)

  • Welcomed participants to Q2 and H1 FY26 earnings call, introduced co-MD Nalin Gupta, CFO Vasant Savla and IR partner Marathon Capital
  • Framed H1 FY26 as a period of balanced performance and resilience despite heavy and early monsoon
  • Emphasised J. Kumar's positioning in technically demanding, first-of-their-kind projects as a competitive differentiator

H1 FY26 Financial Performance · Kamal Gupta (MD)

  • Consolidated revenue from operations for H1 FY26 at INR2,826 crores, up 10% from INR2,574 crores in H1 FY25
  • Operating profit for H1 FY26 at INR411 crores, up 10% YoY; EBITDA margin at 14.6% vs 14.5% in H1 FY25
  • PAT for H1 FY26 at INR195 crores, up 10% YoY, with PAT margin of 6.9%
  • Total order book as of 30 September 2025 at INR20,160 crores; mix 53% elevated corridors/flyovers, 17% roads and tunnels, 17% buildings and other civil, 13% metro

In their words

Where others see complexity, we see opportunity. Technically demanding, first-of-their-kind projects are not obstacles, they are catalysts that push us to innovate, adapt and lead.
Kamal Gupta (Managing Director, J. Kumar Infraprojects)
H2 2026 will be a period of building momentum, scaling up execution and moving ahead with greater speed and focus.
Kamal Gupta (Managing Director, J. Kumar Infraprojects)

To check next time

What management committed to on this call, or the dates they gave.

  • Award of L1 ₹1,200 cr Lucknow conventional centre project and outcome of ₹2,000 cr financial bids already submitted
  • CIDCO ₹1,020 cr project execution commencement after environmental clearance expected in November 2025
  • Closure of Stage 2 forest clearance and tree cutting permissions for Versova-Dahisar Coastal Road
  • GMLR TBM assembly completion, capitalisation of ₹292 cr CWIP and execution ramp-up
  • H2 FY26 execution catch-up to bridge monsoon-driven Q2 shortfall; revenue trajectory toward ₹6,200-6,300 cr FY26 target
  • FY26 capex actuals against ~₹500 cr guidance; confirmation of TBM depreciation commencement timing

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Fri 7 Nov 2025₹619.60−5.43%−0.07%
5 sessions Thu 13 Nov 2025₹614.40−6.22%+1.45%
20 sessions Thu 4 Dec 2025₹555.60−15.19%+2.05%

From the close of Thu 6 Nov 2025, ₹655.15: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.