In brief

RVNL posts record FY24 top line ₹21,732 cr, PAT ₹1,463 cr; targets ₹23,000 cr turnover and ₹20,000-25,000 cr order inflow in FY25.

Management's tone
Confident
What was said
Leaned positive
Guidance
First guidance issued
Analyst pushback
Low
Stock, next session
+3.76% (Nifty 50 +0.28%)
  • FY24 top line ₹21,732 cr (record, +7.15% YoY) and PAT ₹1,463 cr (+17.94% YoY); all-time high.
  • Order book ~₹85,000 cr; FY25 plan ₹23,000 cr turnover and ₹20,000-25,000 cr order inflow via 150+ bids costing ₹75,000+ cr.
  • First bidding projects delivered strong margins: Indore Metro 10.66%, Maldives 11%; combined turnover ₹986 cr (~45% of bidding turnover of ₹2,255 cr).
  • Vande Bharat: 120 trainsets at Latur, RVNL 25% SPV stake, ₹151.7 cr equity injected; production from Nov-Dec 24, prototype by Sep 25.
  • SPV/JV investments ~₹1,600+ cr; net worth ~₹7,867 cr; can infuse up to ₹2,200 cr (30% of net worth) without further approvals.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q4 FY24

This quarterA year agoLast quarterMargin
Revenue₹6,714 cr+17.4%+43.2%
EBITDA (excl. other income)₹456 cr+21.9%+83.2%6.8% (6.5% a year ago)
Net profit₹479 cr+33.2%+33.5%7.1% (6.3% a year ago)
EPS (₹)₹2.29+33.1%+33.1%

From the company's filed results for the quarter ended 31 Mar 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

What moved the numbers, as management explained it

  • FY24 top line +7.15% to ₹21,732 cr (record) on increased project execution and 243 km commissioned in March 2024 (100 km on a single day).
  • FY24 bottom line +17.94% to ₹1,463 cr on shift to higher-margin bidding projects (Indore 10.66%, Maldives 11%) vs 8.5% nomination margin.
  • Indore Metro and Maldives (combined turnover ₹986 cr, ~45% of bidding turnover) delivered margins above 10%, lifting overall profitability.
  • 12 projects completed in FY24 with cumulative 152 as on 31-03-2024; contributed to turnover recognition.
  • Vande Bharat production not yet started (begins Nov-Dec 2024); FY24 numbers do not include any trainset revenue.

The numbers management led with

  • Current order book: Rs 85,000 crores
  • Aspirational order book target: Rs 1,00,000 crores (3-4x annual revenue)
  • Vande Bharat equity infused: Rs 151.7 crores (25% SPV stake; 120 trainsets; Latur workshop)
  • Equity infusion ceiling: ~Rs 2,200 crores (30% of Rs 7,867 crores net worth) without ministry approval

Guidance

Guidance on this call

WhatForWhat management saidFiled
FY25 turnoverFY25If our turnover this year was INR21,700 and next year we plan for INR23,000 crores₹19,923 cr, below the figure guided
FY25 order inflowFY25we would like to have the inflow of approximately INR20,000, INR25,000 crores in a year—
Top line growth (next 5 years)FY25-FY30We want to grow the top line at a rate of around 5% to 7%—
Bottom line growth (next 5 years)FY25-FY30The bottom line growth, which is roughly 15%, should continue over the next five years—
Order book target—we want to maintain an order book of around ₹75,000 crores to INR1 lakh crores—
Vande Bharat production startQ3 FY25we have to start from the November, December 24—
Vande Bharat first prototypeQ2 FY26the first prototype supply is likely to be completed by September 25—
SPV equity infusion capacity—up to INR2,200 crores, we can infuse the equity—

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

By business

Nomination Projects

Legacy business from Ministry of Railways; margin fixed at 8.5% per revenue stream; nomination has been totally stopped for new inflow.

Nomination project margin 8.5% · Cumulative completed projects 152 as on 31-03-2024

Outlook: Nomination has totally stopped; all new inflow will be through bidding only.

Bidding Projects

New vertical started FY22; 286 cumulative bids costing >₹1,50,000 cr; FY24 participated in 142 bids costing ₹65,000 cr with >20% success rate; Indore Metro and Maldives delivered 10%+ margins.

FY24 bids 142 costing ₹65,000 cr · Cumulative bids 286 · Success rate 23.24% civil, 35.78% electrical, 14.27% S&T · Bidding project turnover FY24 ₹2,255 cr · Indore Metro margin 10.66% · Maldives margin 11% · Indore + Maldives turnover ₹986 cr · Signalling orders >₹700 cr

Outlook: Plan ₹20,000-25,000 cr order inflow in FY25 via 150+ bids costing ₹75,000+ cr.

Vande Bharat Trainsets

Contract for 120 trainsets manufactured at Latur; RVNL 25% SPV stake, agreement signed Sep 2023; ₹151.7 cr equity injected; Latur workshop ready; mock-up in advanced stage.

120 trainsets · RVNL SPV share 25% · Equity injection ₹151.7 cr · Year 1 output 12 trainsets · Year 2 output 18 trainsets · Year 3+ output 25 trainsets

Outlook: Production starts Nov-Dec 2024; first prototype by Sep 2025; further equity may be infused as project progresses.

SPVs and JVs

Investments in 5 railway SPVs, 4 MMLPs (Chennai, Bangalore, Indore, Pune), Chatra Expressway (50%), Chandikhole-Paradip (100%); Krishnapatnam turnaround with traffic loading +25% YoY.

Total SPV investment ₹1,600+ cr · Krishnapatnam debt ₹663 cr · Krishnapatnam traffic loading +25% YoY · Net worth ₹7,867 cr · Equity infusion ceiling ₹2,200 cr

Outlook: Up to ₹2,200 cr equity infusion allowed (30% of net worth); further investment subject to opportunity viability.

International Operations

Expanding footprint in Bangladesh, Maldives, Sri Lanka, UAE, Oman, Nepal and others; offices in South Africa, Oman, UAE, Maldives; Kyrgyzstan MoU for 4 projects with DPR done.

Kyrgyzstan MoU: 4 projects

Outlook: Management keen to increase international footprint; India-Middle East corridor seen as big opportunity.

Balance sheet, capex and funding

  • Net worth ~₹7,867 cr; equity infusion capacity up to ₹2,200 cr (30% of net worth) without further Ministry approvals.
  • Cumulative SPV/JV investments ~₹1,600+ cr across 5 railway SPVs, 4 MMLPs, Chatra Expressway (50%), Chandikhole-Paradip (100%).
  • Vande Bharat equity injection ₹151.7 cr; further infusion may be required as project progresses.
  • Krishnapatnam SPV debt ₹663 cr (from financial institutions), down from previous levels.
  • Trade receivables improving per management; arbitration award awaited.

The industry, as management sees it

Management sees strong pipeline under Viksit Bharat 2047 — particularly high-speed rail corridors and the IMEEEC — alongside capacity augmentation projects (rail traffic projected to grow from 1,500 mt now to 3,000 mt); domestic railway electrification is essentially over but doubling/third line, S&T and station development remain.

Risks management named

  • Railway electrification opportunity nearly exhausted in India (~98% done); value-per-km too low
  • Margin variability across bid projects; no uniform margin guidance possible
  • Equity infusion ceiling of ~Rs 2,200 cr (30% of net worth) limits incremental SPV investment without ministry approval

Q&A

Q&A was dominated by growth and bidding-model questions rather than competitive pressure; analysts probed Kyrgyzstan, IMEEEC, Vande Bharat and the bidding pivot. Two repeated audio-clearance issues (Shreyans Mehta) caused moderator relay of questions but did not affect content. Management gave direct quantitative guidance on FY25 revenue (~Rs 23,000 cr) and order inflow (Rs 20,000-25,000 cr) but deflected on exact order book composition and project-level sizes.

Not answered directly

  • Specific project-level sizes within Rs 85,000 cr order book
  • Exact FY24 order inflow figure
  • Incremental equity quantum in existing SPVs over next 1-2 years

Asked for a number, answered without one

  • Incremental SPV investment over 1-2 years: depending upon the requirement, we may have to invest... it depends upon the situation and the conditions. And we cannot foresee at this very moment
  • Vande Bharat total equity commitment: As the project keeps on moving forward, we may have to infuse more
  • High-speed rail margin range: We do not have any order for the high-speed... nomination margin is 8.5% and bidding margins vary project to project

Every question, with its answer

  1. 1. Kyrgyzstan project

    Ranodeep, MAS Capital

    Question. Any update on the Kyrgyzstan INR 18,000 cr deal?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Earlier MOU was signed. RVNL was assigned DPR preparation and financial tie-up — both done. Now the Government of Kyrgyzstan is working on it. The project life cycle is in early stage: concept, alignment and DPR are ready; financing discussions with institutions are complete. Project is viable; we signed MoUs for four projects and are awaiting DPR approval and implementation clearance.

  2. 2. 5-year growth trajectory

    Ranodeep, MAS Capital

    Question. Sales have gone from Rs 10,000 cr (2019) to Rs 21,000 cr and profits from Rs 680-700 cr to almost Rs 1,500 cr — can this doubling continue over the next 5 years given the Rs 85,000 cr order book?

    Answer, Rajesh Prasad, Director of Operations, RVNL. PAT has gone 2.4x in six years (from Rs 600 cr to Rs 1,463 cr). Top line trajectory: Rs 15,710 cr (FY21) → Rs 19,381 cr → Rs 20,281 cr → Rs 21,732 cr (FY24) — ~7% YoY. Management is more focused on bottom-line growth; the tradition of ~5% top line and ~15% bottom line growth should continue over the next 5 years.

  3. 3. Margins (bid vs nomination)

    Ranodeep, MAS Capital

    Question. For nominated railway projects we work at an 8.5% model — combined with market-bid projects, what margin aspiration do we have for the coming years?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Bid projects will have varying margins — some less, some very good. Indore Metro (FY24) gave 10.66% margin; Maldives gave 11%; combined turnover ~Rs 1,000 cr at 10%+ margin. Margin depends on execution capability, value engineering, planning, procurement and timely delivery. We have demonstrated market-based projects can earn 10%+ margins.

    Partly answered.

  4. 4. Vande Bharat trainset capex & advances

    Shreyans Mehta, Equirus Securities

    Question. On the Vande Bharat trainset order we won: (1) do we need to invest capex, (2) do we get mobilisation advances, (3) will we keep building under the JV for this project?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Contract is for 120 trainsets, manufactured at Latur. RVNL has 25% shareholding in the SPV; agreement signed September 2023. Equity injection by RVNL to date: Rs 151.7 cr. Layout and colour scheme under approval with the Ministry; mock-up contract awarded to M/s Kineco (Goa) and is in advanced stage. Manufacturing schedule: start Nov-Dec 2024; first prototype by Sept 2025; 12 units in year 1, 18 in year 2, 25 thereafter. Three maintenance depots at Jodhpur, Delhi and Bangalore; Latur workshop is fully ready.

    Follow-up. How much more equity will we need to invest?

    Answer. As the project keeps moving forward, we may have to infuse more.

  5. 5. Vande Bharat future bidding

    Shreyans Mehta, Equirus Securities

    Question. Once the Vande Bharat design is approved and first trains delivered, can we bid on our own for further Vande Bharat opportunities, or are we dependent until full delivery to railways?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Depends on the client's eligibility criteria. RVNL is a Navratna company with all kinds of exposure and experience. Policy: if credentials fit, we go alone — we will not tie up. Policy applies to Vande Bharat too: if client eligibility can be satisfied, RVNL will bid alone.

    Partly answered.

  6. 6. SPV/JV investment

    Shreyans Mehta, Equirus Securities

    Question. How much have we invested in different JVs till date and how much more do we need to invest?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Total ~Rs 1,600+ cr invested in various SPVs/JVs/companies — five railway SPVs, MMLPs at Chennai/Bangalore/Indore/Pune, Chatra Expressway (50%), Chandikhole-Paradip (100% subsidiary). Equity infusion ceiling: 30% of net worth, which with current Rs 7,867 cr net worth means up to ~Rs 2,200 cr without Ministry approval.

    Follow-up. Is this Rs 1,600 cr the full amount or do we need to invest more in these SPVs over next 1-2 years?

    Answer. Yes — depending on requirement, we may have to invest. If financially viable and in the interest of RVNL, we will invest even in existing companies; if it leads to losses, we will not.

    Partly answered.

  7. 7. High-speed rail order book

    Tushar Raghatate, Kamayakya Wealth Management

    Question. What percentage of our order book is high-speed railway?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Currently zero — we have no high-speed rail work order. We are executing metros in seven cities; metro is our preferred segment. Under the Viksit Bharat 2047 vision, large plans exist for high-speed corridors. RVNL is technically competent and interested in bidding for high-speed work.

    Follow-up. Can you give a margin range for high-speed rail orders?

    Answer. We have no high-speed orders. Nomination margin is fixed at 8.5%; margins for bid projects vary by project nature and risk profile. Indore Metro and Maldives bid projects delivered 10%+ margins.

  8. 8. Order book nomination/bidding split

    Vishal Periwal, IDBI Capital

    Question. Of the current Rs 85,000+ cr order book, can you give a split between nomination and bidding?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Around Rs 36,000 cr exact number not available — 40-45% kind of split. Remaining is bidding-based. Going forward, nomination has totally stopped and all inflow will be through bidding.

    Partly answered.

  9. 9. Key orders in order book

    Vishal Periwal, IDBI Capital

    Question. Can you share the key 4-5 orders in the Rs 85,000 cr order book with sizes?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Highlighted new signaling vertical — orders worth >Rs 700 cr, including a Southern Railway ABS project at Jolarpatti Road Junction (Salem Division) of ~Rs 239-250 cr. Also flagged large electrical works portfolio across state government projects, metros and railways, plus full metro vertical (depot, track, electrical, S&T, civil, station, underground packages). Detailed project-by-project breakdown not provided.

    Not answered directly.

  10. 10. FY24 order inflow

    Vishal Periwal, IDBI Capital

    Question. With 20%+ success rate, what was the order inflow in FY24 in Rs cr?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Exact number not available. Bids participated in FY24: 142 costing ~Rs 65,000 cr (76 civil, 36 electrical, 29 S&T). Success rates: civil 23.24%, electrical 35.78%, S&T 14.27%. Applying ~20% to the bid value gives an approximate inflow figure.

    Not answered directly.

  11. 11. IMEEEC corridor opportunity

    Ranodeep, MAS Capital

    Question. Have you quantified the opportunity from the India-Middle East-Europe Economic Corridor (IMEEEC)?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Announced in G20 — big opportunity covering rail and marine segments. RVNL has marine experience from Maldives and bridges; commissioned >16,000 km of railway infrastructure. Rated 'excellent' by Department of Public Enterprises for 13 years. Once DPR/tenders are out, RVNL will be keen to bid — 100% confident of delivering with quality and safety.

    Partly answered.

  12. 12. Railway electrification opportunity

    Ranodeep, MAS Capital

    Question. Railway electrification used to be a major component of order book but ~95% of India is electrified — are we still looking at this opportunity?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Electrification in km looks big but value-wise is small — doubling/third line costs Rs 15-20 cr/km while electrification costs ~Rs 1 cr/km. More than 99% of RVNL's electrification assignment is done. Not pursuing electrification in India. Future focus: capacity augmentation (rail traffic projected 1,500 mt now to 2,000 mt by 2030 and 3,000 mt), turnkey projects, manufacturing, S&T, station development.

  13. 13. Solar / non-rail diversification

    Ranodeep, MAS Capital

    Question. On the South African Jackson Green solar JV — what are our aspirations in solar?

    Answer, Rajesh Prasad, Director of Operations, RVNL. Looking at all kinds of opportunities — not limited to railway infrastructure anymore. Tagline: 'from local rail infra to global all infra.' International push covers all infra. 100% confident of delivering these projects with good margins going forward.

    Partly answered.

  14. 14. FY25 guidance (order inflow & revenue)

    Ketan Jain, Avendus Spark

    Question. What is the FY25 order inflow guidance and revenue guidance?

    Answer, Rajesh Prasad, Director of Operations, RVNL. FY24: 142 bids participated costing ~Rs 65,000 cr. FY25: 150+ bids costing >Rs 75,000 cr; success rate ~20% — so inflow ~Rs 20,000 cr. Target order book always 3-4x revenue; FY25 revenue planned ~Rs 23,000 cr, so order book target Rs 92,000 cr to Rs 1,00,000 cr. Expected annual inflow: Rs 20,000-25,000 cr (all from bidding — nomination stopped).

What was said

Topic by topic, in the order it was spoken

FY24 Financial Performance & Growth · Rajesh Prasad (Director of Operations, RVNL)

  • Top line Rs 21,732 cr in FY24, up 7.15% YoY — all-time high; bottom line Rs 1,463 cr, growth cited between 15.38% (later in call) and 17.94% (opening).
  • Top line growth paced at 5-7% annually; bottom line focus is the stated priority, targeted at ~15% growth.
  • Prior guidance of Rs 21,000 cr+ top line and Rs 1,400 cr+ bottom line delivered; targets met on both counts.
  • Cumulative project expenditure scaled from Rs 15,600 cr (FY14) to Rs 1.55 lakh cr (FY24).
  • Decade PAT CAGR: PAT grew 2.4x over six years from Rs 600 cr to Rs 1,463 cr.

First Bidding Wins: Indore Metro and Maldives · Rajesh Prasad (Director of Operations, RVNL)

  • Indore Metro — first Indian project won through competitive bidding — delivered 10.66% margin in FY24.
  • Maldives — first overseas project — delivered 11% margin in FY24.
  • Combined turnover from these two bid projects was Rs 986 cr, ~45% of the Rs 2,255 cr bidding-project turnover in FY24.
  • Margins from market-priced projects exceed the 8.5% margin earned on nomination-based railway projects, validating the bidding pivot.

Project Execution & Commissioning Records · Rajesh Prasad (Director of Operations, RVNL)

  • 152 cumulative projects completed as on 31 March 2024; 12 projects completed during FY24.
  • 243 km of railway track commissioned in March 2024 alone; 100 km commissioned on a single day — a record.
  • First-of-its-kind rail-over-rail bridge commissioned at Indore Yard; first-of-its-kind metro station at Majerhat.
  • Bohe workshop completed and commissioned during FY24 — described as state-of-the-art.
  • Rishikesh-Karnaprayag: 60 km of tunnelling executed in one year; Kolkata metro saw three new sections inaugurated by the PM.

Business Development & Bidding Pipeline · Rajesh Prasad (Director of Operations, RVNL)

  • 142 bids participated in FY24 costing ~Rs 65,000 cr (76 civil, 36 electrical, 29 S&T); cumulative 286 bids to date costing >Rs 1.5 lakh cr.
  • Win rate >20% overall: Civil 23.24%, Electrical 35.78%, S&T 14.27%.
  • FY25 plan: 150+ bids costing >Rs 75,000 cr; expected inflow Rs 20,000-25,000 cr.
  • Nomination has totally stopped — all future order book inflow will be through bidding only.

International Footprint Expansion · Rajesh Prasad (Director of Operations, RVNL)

  • International bids pursued in Bangladesh, Maldives, Sri Lanka, UAE, Oman, Rwanda, Uzbekistan, Saudi Arabia, Nepal; EOIs in Botswana Railways and Namibia Trans-Kalahari.
  • International offices opened in South Africa, Oman, UAE, Maldives.
  • Tagline articulated: 'from local rail infra to global all infra.'
  • Kyrgyzstan: MOU signed for four projects; DPR prepared and financial tie-up done; awaiting government approval for implementation.

SPV / Subsidiary Turnaround · Rajesh Prasad (Director of Operations, RVNL)

  • Krishnapatnam Rail Co: traffic loading and rakes up 25% YoY; >100% over two years; debt reduced to Rs 663 cr.
  • Trade receivables improving; arbitration award awaited.
  • Total SPV/JV investment to date ~Rs 1,600+ cr across five railway SPVs, MMLPs (Chennai, Bangalore, Indore, Pune), Chatra Expressway (50%), Chandikhole-Paradip (100% subsidiary).
  • Equity infusion ceiling: 30% of net worth (~Rs 2,200 cr of Rs 7,867 cr net worth) without ministry approval.

In their words

nomination has been totally stopped. So, whatever order book inflow will be there, it will be through the bidding only. So, we would like to have the inflow of approximately INR20,000, INR25,000 crores in a year.
Rajesh Prasad (Director of Operations, RVNL)
We want to grow the top line at a rate of around 5% to 7%. And in order to grow like this, all the time we want to maintain an order book of around INR75,000 crores to INR1 lakh crores. INR1 lakh crore is an aspirational target.
Rajesh Prasad (Director of Operations, RVNL)
We have got a very beautiful tagline from local rail infra to global all infra. So, earlier we were executing we used to have only one client, that is the Ministry of Railways and we are executing all the railway infrastructure.
Rajesh Prasad (Director of Operations, RVNL)

To check next time

What management committed to on this call, or the dates they gave.

  • Vande Bharat mock-up completion and colour scheme approval by Ministry of Railways.
  • Vande Bharat production start (Nov-Dec 2024) and first prototype delivery (Sep 2025).
  • FY25 order inflow progress vs ₹20,000-25,000 cr target via 150+ bids.
  • FY25 turnover progress vs ₹23,000 cr plan.
  • International order wins: Kyrgyzstan DPR approval, India-Middle East corridor.
  • Order book maintenance at ₹75,000-1,00,000 cr range.

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Fri 17 May 2024₹290.80+3.76%+0.28%
5 sessions Thu 23 May 2024₹372.25+32.83%+2.52%
20 sessions Thu 13 Jun 2024₹390.15+39.21%+4.44%

From the close of Thu 16 May 2024, ₹280.25: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.