Godawari Pow & Isp Q2 FY25 earnings call

Mon 28 Oct 2024GPIL

In brief

Management's tone
Mixed
What was said
Mixed
Guidance
Guidance cut
Analyst pushback
Medium
Stock, next session
−0.20% (Nifty 50 +0.65%)
  • Iron ore production guidance cut to 2.35 MT for FY25 (from 3 MT) after state-government EC for mining expansion slipped; mining approval now expected only Q4 FY25.
  • Pellet plant capacity expansion (2.7→4.7 MT) remains on schedule for June/July 2025; FY26 volumes guided +1 MT, full +2 MT by FY27 with no merchant iron-ore sales.
  • Q2 hit by 50-day annual pellet-plant shutdown — INR 65 cr revenue impact, EBITDA INR 247 cr at ~20% margin vs ~28% YoY; shutdown not repeated for ~10 years.
  • Balance sheet robust with INR 998 cr net cash; capex of ~INR 800 cr FY25 and ~INR 1,000 cr FY26 to fund pellet + integrated steel plant + solar.
  • Pellet Q3 realization expected better than Q2 on iron-ore price rise; spot INR 10,000/t (63% Fe) and INR 11,500/t (66% Fe), mix to shift to 2/3 high-grade once new plant ramps.

An AI read of the company's transcript · the filing

The numbers

The quarter, Q2 FY25

This quarterA year agoLast quarterMargin
Revenue₹1,268 cr−1.8%−5.6%
EBITDA (excl. other income)₹247 cr−31.6%−39.3%19.5% (28% a year ago)
Net profit₹159 cr−38.1%−44.5%12.6% (19.9% a year ago)
EPS (₹)₹12.98−37.0%−43.5%

From the company's filed results for the quarter ended 30 Sept 2024 (consolidated), not from the call. EBITDA here excludes other income, so it can differ from the figure management quotes.

The numbers management led with

  • Iron ore production FY25 guidance: 2.35 MT (revised down from 3 MT)
  • Net cash position H1 FY25: INR 998 crore
  • Iron ore mining capacity target: 6 MT (up from 2.35 MT); EC by Q4 FY25
  • Pellet plant capacity expansion: 2.7 to 4.7 MT; commissioning June/July 2025
  • Capex FY25: ~INR 800 crore

Guidance

Guidance on this call

WhatForWhat management said
Iron ore production (FY25)FY25Revised to 2.35 MT for FY25 (from 3 MT earlier) due to state government environmental clearance slipping to Q4 FY25. (cut)
Iron ore mining capacity (commissioning)FY26Approval expected Q4 FY25; ramping from Q1 FY26 with full 6 MT by end of Q1 or Q2 FY26.
Beneficiation plant commissioningQ4 FY25 + 6 monthsWithin 6 months of mining EC, since preparatory work is already substantially complete.
Pellet plant capacity (2.7→4.7 MT) commissioningQ1 FY26On schedule for June/July 2025 commissioning. (held)
Greenfield integrated steel plant (2 MT) — MOEF approvalQ3 FY25Approval expected December 2024; construction only after regulatory approvals.
Pellet volumes incrementalFY26 and FY27FY26: +1 MT incremental; FY27: full +2 MT (captive consumption stays 0.9 MT).
Capex FY25FY25~INR 800 cr. (held)
Capex FY26FY26~INR 1,000 cr; pellet plant plus balance on beneficiation/steel post EC. (held)
Solar power capacityFY25/FY26165 MW already operational; additional 70 MW planned for the upcoming 2 MT pellet plant.
Net Zero targetby 20502050; CCU pilot with IIT Bombay in lab-scale; larger unit subject to pilot success. (held)
Pellet Q3 realizationQ3 FY25Expected at ~INR 10,000/t average (vs Q2 ~INR 10,000); spot INR 10,000/t (63 Fe) and INR 11,500/t (66 Fe).
Pellet grade mix (post new plant)FY26 onwardShifts to ~2/3 high-grade (66 Fe) and 1/3 normal (63 Fe), vs 50:50 currently.

Guided on earlier calls, and what was filed

WhatForGuidedFiled
FY25 EBITDA marginFY2524–25% (on the Q4 FY24 call)22.2%, below the range

Filed figures are summed from the company's own quarterly results for the whole period (EBITDA excludes other income); where one sits against what was guided is arithmetic, not a judgement.

The business

The industry, as management sees it

Global iron-ore prices have corrected sharply from January 2024 highs (~$144) to sub-$100 on China slowdown concerns, with brief China-stimulus rallies fading; large Guinea mine adding supply from 2027 is a medium-term headwind. However, India is one of the brightest spots globally — the Steel Association forecasts domestic steel demand to grow 8% in FY24 and 5% in calendar 2025 (to 143 MT and 153 MT respectively), and domestic iron-ore prices have held firm on the back of auction floor and merchant-supply tightening.

Risks management named

  • State-government environmental approval for mining expansion slipped from earlier timeline; may not land before new pellet plant commissioning
  • If mining EC slips, market iron-ore purchases could rise from ~25% to 30–35% of requirements, raising landed cost
  • Global iron-ore price has fallen from $144 (Jan 2024) to sub-$100 on China slowdown; Guinea Simandou mine adds supply from 2027
  • Sponge iron and billet realizations dropped YoY in H1; heavy rains hit iron-ore mining output in Q2
  • Pellet exports not viable — domestic demand and pricing stronger; pellet price lag of 1–2 months vs iron-ore moves

Q&A

Q&A focused heavily on three themes: (i) the pellet plant 50-day shutdown impact on Q2 margins and the trajectory of pellet Q3 realization, which management confidently pegged at INR 10,000–11,500/t spot; (ii) the state-government EC delay for iron-ore mining expansion and its cascading impact on iron-ore market purchases and FY26 ramp — Jinesh Shah pushed hard on the timeline and pushed back on whether 6 months is realistic, drawing a partial/evasive response that EC should come 'by end of FY25'; (iii) capex, solar economics and ferro-alloy/galvanized-products outlook. Pushback was highest on the EC-approval timing and pellet realization step-up, with management deferring precise guidance on the beneficiary ramp and EC landing date to 'before the new pellet plant commissions'. Pleasantries dominated otherwise — the call was technically substantive but light on hard analyst contention past the EC question.

Not answered directly

  • Mining EC approval precise date — deferred to 'before new pellet plant starts'
  • Iron ore purchases proportion if EC slips beyond Q1 FY26 — partially deflected
  • Post-beneficiation grade at Boria Tibu — answered with range but timing '2–3 years' only
  • EC vs mining-clearance distinction — partial clarification, not crisp

Every question, with its answer

  1. 1. Pellet prices & demand outlook

    Sahil Rohit Sanghvi, Monarch Networth Capital

    Question. On pellet prices — given 1–2 month contracts, how have prices not corrected more in Q2 and what's the Q3 trajectory? Also, were there iron-ore market purchases in Q2? Is the 7 MW waste-heat power for self-consumption or export? Finally, how is ground demand in Q3 post monsoon?

    Answer, Abhishek Agrawal, Executive Director. For Q3, pellet prices have resumed positively and are currently ~INR 10,000/t; Q3 number will be on the higher side vs Q2. Company is buying ~25% of iron ore from the market (at ~INR 3,500/t) and will continue for ~6 months until new mining EC lands. The 7 MW waste-heat plant is fully for self-consumption — not for export to grid; helps reduce coal burn and carbon emissions. Q2 is normally a lean season; Q3 post-Diwali they expect demand to come back, margins to recover, and prices to rise further.

  2. 2. Coal costs & pellet pricing

    Manav Gogia, YES Securities India Limited

    Question. What was the blended landed coal cost for Q2? Any domestic sourcing split? Are Q3 pellet prices expected higher than Q2 — can you qualify? With mining EC expected by Q4, when are mines operational (you mentioned 6 months from Q4) and what's the landed cost per ton outlook vs INR 2,800–2,900/t?

    Answer, Abhishek Agrawal, Executive Director. Blended imported RB1 coal cost for DRI was ~INR 12,000/t vs ~INR 11,500/t last quarter. Domestic coal linkages from Coal India for power and gasifier were ~INR 4,000/t in Q2 and Q3 — stable through 5-year linkage. Q2 pellet average ~INR 10,000/t; Q3 expected at same level (prices dipped late Q2 but recovered on OMC auction rise in iron-ore fines). Mines are expected to start from Q1 FY26; landed cost will remain similar to current mining cost, plus ~INR 3,500/t paid on the 20% market volumes.

    Follow-up. Does this mean pellet prices for Q3 are expected to be a little up as compared to Q2? And the EC approval slipping — what's a realistic timeline for iron-ore mining to be operational?

    Answer. Dinesh Gandhi clarified that 6 months refers to beneficiation-plant commissioning; mining itself expected from Q1 FY26, right when the pellet plant comes on stream. Pellet Q3 prices expected at ~INR 10,000/t average, similar to Q2.

    Partly answered.

  3. 3. Mining & pellet ramp-up timeline

    Aditya Welekar, Axis Securities

    Question. Will pellet plant, crushing & beneficiation, and iron-ore mining all start in tandem from Q1 FY26? Any ramp-up timeline and what incremental volumes can we expect in FY26? On international iron-ore (e.g., Guinea mine coming online), how do domestic pellet prices hold up?

    Answer, Abhishek Agrawal, Executive Director. Yes, all three will start in tandem from Q1 FY26. Once approval lands, mining ramp begins; expect to mine desired volumes by end of Q1 or Q2 FY26, reaching full 6 MT. Pellet prices are insulated from global moves because India's steel production growth is strong; domestic iron-ore pricing has been firm and pellet prices should stay at similar levels.

  4. 4. Solar capex intensity & capex split

    Akhilesh Kumar, Emkay Global Financial Services

    Question. On capex intensity — solar typically takes INR 50–55 m/MW but GPIL targets 70 MW at INR 35–36 m/MW. Why the lower cost? Given iron-ore guidance cut, is there a risk of scale-back on 6 MTPA by FY26? Of the ~INR 1,000 cr balance capex, what's the split between FY25 and FY26?

    Answer, Abhishek Agrawal, Executive Director. Module prices have collapsed from INR 2–2.5 cr/MW earlier to INR 1.5 cr/MW; EPC contractor finalized — confident 70 MW doable in INR 200–225 cr. No scale-back on 6 MTPA target — approval should land and then there's no issue reaching full capacity. All capex (FY25 + FY26) will be consumed across the two years — major spend is pellet plant (already underway), with the balance on beneficiation/steel once mining approval lands.

    Follow-up. Can we assume 50:50 between FY25 and FY26?

    Answer. Major is the pellet plant already being consumed; remainder depends on mining approval and will fall in FY26.

  5. 5. Pellet grade mix & mining approval risk

    Jatin Damania, Swan Investments

    Question. Pellet prices fell QoQ in Q1 but realization improved sequentially in Q2 — can you explain the grade mix and whether 50:50 high-grade (Fe 63/66) continues? New pellet plant commission timing? If the EC doesn't come by Q4 FY25, do market iron-ore purchases go from 25% to 30–35%? Why has the mining EC been delayed? What's the capex already spent on beneficiation?

    Answer, Abhishek Agrawal, Executive Director. 50:50 high-grade (66 Fe) and normal (63 Fe) will continue until the new plant commissions in Q1 FY26 (production Q2 FY26). If EC doesn't come, market purchases will rise — confident EC will arrive before pellet plant starts. Delay is procedural, not contentious — state government taking more time. Pellet plant now fully operational since September (smaller iron-ore plant was the one shut); both will be fully operational.

    Follow-up. And in Q2 the pellet plant — was it fully operational in October?

    Answer. Yes, both pellet plants fully operational since September; confident FY25 guidance will be achieved at the start of the year.

    Partly answered.

  6. 6. Q2 margin & sponge-iron realization

    Rakesh Roy, Boring AMC Omkara Capital

    Question. Margin declined from ~28% YoY to ~20% — is there any reason beyond rain/pellet? Is the 50-day shutdown one-time? Will margins normalize from Q3? Why is your sponge-iron realization lower than that of a competitor who recently declared results? Coal cost INR 12,000/t — is that for imported DRI coal?

    Answer, Abhishek Agrawal, Executive Director. Major reason was the 50-day annual pellet-plant shutdown — last time this was done was ~10 years back, so it's not a recurring event. Q3 production normalizes; margins will remain intact subject to market. In Q2, sponge-iron was sold to market as surplus from running at capacity; from Q3 onward they will only sell surplus to internal steel production. Yes, DRI coal is imported.

  7. 7. Boria Tibu mine & export opportunity

    Vikash Singh, PhillipCapital

    Question. With iron-ore prices inching up, has management thought about restarting Boria Tibu Mine (low grade)? What average grade now and post-beneficiation? Is there export market opportunity for pellets given China's sintering shutdown? Q3 pellet realization outlook vs Q2?

    Answer, Abhishek Agrawal, Executive Director. Boria Tibu Mine — papers being filed for beneficiation; will only start once plant comes online as low grade (50–52% Fe) is feasible only with beneficiation to 63–65% — expected 2–3 years out. On exports — GPIL has not exported pellets in 10 months; domestic demand and prices are stronger. Some port-based plants in Odisha/Vizag may export. Q3 pellet realization should be better than Q2 — Q2 volumes were lower so pricing was maintained; Q3 demand-supply should improve. Spot ~INR 10,000/t (63 Fe) and INR 11,500/t (66 Fe).

    Follow-up. How are the spot Q3 prices?

    Answer. Normal grade ~INR 10,000/t; high grade ~INR 11,500/t at the moment.

  8. 8. Iron-ore market & ferro alloys

    Aman, Augmenta Asset Manager LLP

    Question. For FY25 overall, are you buying ~60,000 tons iron-ore from outside for internal operations? NMDC raised prices 2x in last 20 days — what's your view on the domestic iron-ore market? What's happening in the ferro alloys market currently?

    Answer, Abhishek Agrawal, Executive Director. Currently buying ~1,500 tons iron-ore from the market (corrected the '60,000' figure). Domestic iron-ore market strong — recent OMC auction prices up ~INR 1,000/t. With post-monsoon global steel demand, expect prices to remain elevated. Ferro alloys market is stagnant — raw material prices (manganese) have come down; domestic silico-manganese stable after Q2 rise on production outage + China demand.

  9. 9. Galvanized products demand & margins

    Tushar Chaudhari, Prabhudas Lilladher Private Limited

    Question. Galvanized fabricated products — volumes have fallen over last 2 quarters yet capacity is being increased. What's the deal — was it higher zinc prices pressuring margins? How is demand currently?

    Answer, Abhishek Agrawal, Executive Director. Q2 volumes were lower because the zinc bath was under major maintenance/repair. Demand is strong — also commissioned a new rolling mill to support profitability. Expect major uptick in Q3 and Q4 volumes. Margins will remain intact — business is more PSU work (transmission towers, railways) with robust demand.

    Follow-up. But margins?

    Answer. Margins will remain intact; once desired volumes achieved, profitability sustained.

  10. 10. Ferro alloys buyback & economics

    Pradeep Rawat, Yogya Capital

    Question. What's the consideration for the Alok Ferro Alloys buyback from promoters? Why are both ferro-alloy subsidiaries doing badly year-on-year? What EBITDA margins are you expecting from ferro alloys? What's the cost per ton of converting mined iron-ore into iron-ore pellets?

    Answer, Dinesh Gandhi, Executive Director. Buyback was at ~INR 10 per share. Both ferro-alloy plants operating fully; current-year volumes considerably higher — last year's subdued performance was due to plant modification and shutdown at Alok's power plant, not now. Consolidated ferro alloys EBITDA ~INR 40–45 cr; ~INR 8,000–10,000/t margin. Pellet conversion cost ~INR 1,800/t (vs mining cost ~INR 3,000/t).

  11. 11. Pellet capacity ramp & iron-ore offtake

    Wayne D'Mello, Badrinath Holding

    Question. On the 2 MT new pellet capacity in FY26 — is the FY26 ramp ~50% (1 MT) and full 2 MT in FY27? Does captive pellet consumption stay at 0.9 MT throughout? Iron ore from new mining will not be sold externally given royalty cost? What will be the high-grade mix (Fe 63 vs 66) in FY27?

    Answer, Abhishek Agrawal, Executive Director. Correct — FY26 adds ~1 MT pellet volume, FY27 adds full 2 MT. Captive consumption stays at 0.9 MT, so incremental volume goes to market. No intention to sell iron-ore externally — whatever is mined is consumed in the pellet plant. On grade mix — currently 50:50; new pellet plant will also produce high-grade, so mix shifts to ~2/3 high-grade (66 Fe) and 1/3 normal (63 Fe).

  12. 12. Pellet export share & CCU/Net Zero

    Vaibhav Dubey, BigMint Technologies Private Limited

    Question. What was the domestic vs export split last quarter and what's the Q3 outlook? Can you share more detail on the CCU/Net Zero plans mentioned in the investor presentation?

    Answer, Abhishek Agrawal, Executive Director. GPIL has not exported pellets in 10 months; all domestic sales. Outlook remains domestic-only for Q3 and likely Q4. On Net Zero — target 2050. Working with IIT Bombay on CCU; pilot done in lab; larger unit to be installed at GPIL. Still R&D stage — only major investment once pilot is operationally and economically proven.

  13. 13. Net cash composition & inter-corporate loans

    Sahil Rohit Sanghvi, Monarch Networth Capital

    Question. On the net cash figure of INR 970–990 cr — there appears to be INR 170–180 cr of loans being shown as cash equivalent. Who are these loans given to, and what's the interest rate?

    Answer, Sanjay Bothra, Chief Financial Officer. Interest rate is largely between 12%–16%; loans are repayable on demand (hence treated as cash equivalent). Counterparty — GMR Enterprises and other corporates. Abhishek Agrawal added: GMR is one party; rest are other corporates.

  14. 14. Capex guidance & other expenses

    Manav Gogia, YES Securities India Limited

    Question. Capex guidance for this year INR 800 cr and next INR 1,000 cr — is that still intact? Total capex spend in H1 FY25? Other expenses jumped ~14% QoQ — what drove that?

    Answer, Abhishek Agrawal, Executive Director. Capex guidance intact at INR 800 cr (FY25) and INR 1,000 cr (FY26). H1 capex number is in the investor presentation. On other expenses — INR 25 cr was one-time maintenance cost during pellet-plant shutdown; not repeated. Dinesh Gandhi noted that the presentation has the H1 capex numbers.

    Partly answered.

  15. 15. Mining EC delay & public hearing timeline

    Jinesh Shah, HNI Investments

    Question. In Q1 presentation, beneficiation was 15 months from EC; in Q2 it's 6 months — what changed in 3 months? With EC continuously delayed, isn't the team under-pressing for clearance given the pellet plant starts in Q1 next year? Which state-government approvals are still pending beyond EC? When will you submit response to revised ToR, and when does the public hearing happen?

    Answer, Abhishek Agrawal, Executive Director. On 15→6 month timeline: 0.6 MT has been approved and most work already done; the remaining 6 months covers incremental work for the additional capacity after the 6 MT EC. Environment team is putting required effort — it's just that the state-government (not central) approval is taking longer than expected; expect mining permission by end of FY25. State-government approvals under MMDR Act include EC and related clearances — all at state level, now in last stage (private hearing / public hearing to happen); response to revised ToR already submitted; public hearing expected December, approval by end of November.

    Follow-up. By when will public hearing happen — getting approval in next 6 months seems tough?

    Answer. GPIL is at the last stage of permission route; fully by November-end they expect approval, and public hearing in December, which puts them on track for EC by end of financial year.

    Partly answered.

What was said

Topic by topic, in the order it was spoken

Q2 & H1 FY25 Financial Performance · Dinesh Gandhi (Executive Director)

  • Q2 consolidated revenue INR 1,268 cr, EBITDA INR 247 cr, PAT INR 158 cr (adjusted, ex-exceptional items)
  • Q2 impact of INR 65 cr from pellet plant shutdown: ~INR 50 cr on lower sponge-iron/billet realization, INR 25 cr on additional maintenance cost
  • H1 FY25 revenue flat YoY at ~INR 2,600 cr; higher value-added product volume offset by lower realization
  • H1 EBITDA INR 654 cr (-2% YoY); H1 PAT INR 445 cr (-5% YoY); EBITDA margin 25%, PAT margin 17%
  • H1 cash flow from operations INR 564 cr; net cash position INR 998 cr — strongest balance sheet in peers

Operational Performance & Volumes · Dinesh Gandhi (Executive Director)

  • Pellet volume loss of ~150,000 tons in Q2 from 50-day shutdown of 0.9 MT pellet plant; second pellet plant unaffected
  • H1 sponge iron sales volumes +56% YoY; steel billet +20% YoY; HB wires +39% YoY; value-added products ramped
  • Iron-ore mining production down in Q2 on heavy rains; H1 mining & pellet output flat YoY
  • Pellet realization +5% YoY to INR 10,569/t in H1; other product realizations fell
  • Iron-ore sourcing: ~25% bought from market at ~INR 3,500/t; balance captive; market share stays high until new mining EC received

Capex Update — Mining, Pellet & Steel Plant · Dinesh Gandhi (Executive Director)

  • Mining capacity expansion (2.35→6 MT): EC delayed; approval now expected Q4 FY25; FY25 production guidance cut from 3 MT to 2.35 MT accordingly
  • Beneficiation plant (6 months from EC) — preparatory work already executed; will commission quickly post-EC
  • Pellet expansion (2.7→4.7 MT) — on schedule for June/July 2025; orders placed; construction >50% complete; equipment shipments begin in a month
  • Greenfield 2 MT integrated steel plant — public hearing completed earlier; MOEF presentation done in Q2; approval expected December 2024
  • Construction of new pellet/sinter/beneficiation plants to begin only post all regulatory clearances

Solar, Decarbonization & Sustainability · Dinesh Gandhi (Executive Director)

  • 165 MW solar commissioned and operational; additional 70 MW in process (land acquisition) to feed 2 MT new pellet plant
  • Stage-1 decarbonization capex INR 75 cr to add 11 MW power without extra fuel; payback ~3 years
  • Waste-heat recovery with Siemens: 7 MW additional clean power, INR 73 cr capex from internal accruals, 50,000 t/yr carbon reduction, 18-month build
  • Net Zero commitment reaffirmed for 2050; collaborating with IIT Bombay on CCU; pilot in lab, larger unit planned

Group Structure & Subsidiaries · Dinesh Gandhi (Executive Director)

  • Alok Ferro Alloys buyback → 100% subsidiary; HFAL stake raised to 96%
  • Chhattisgarh Captive Coal mining: partial buyback done; GPIL's stake reduced correspondingly
  • Alok Ferro Alloys and HFAL operating at full capacity; FY25 volumes considerably higher YoY after plant modification shutdown

Industry Outlook — Iron Ore & Steel · Dinesh Gandhi (Executive Director)

  • Global iron-ore prices: dropped from $144 (Jan 2024) to sub-$90 on China slowdown; brief China-stimulus rally to $115 faded; back below $100
  • Guinea Simandou large mine to add supply from 2027 — could cap prices medium-term
  • China housing demand recovery could push global prices back to $110–$115 in the interim
  • Domestic iron-ore: NMDC follows global but auction prices + merchant-supply tightening floor domestic prices
  • India steel demand: Steel Association forecasts +8% in FY24 and +5% in CY25 (143 MT and 153 MT)

In their words

GPIL is developing a waste heat recovery based power plant harnessing heat from the company's existing Ferro Alloys furnaces and pellet plant cooler exhaust to generate additional power of 7 megawatt of clean energy, which will reduce carbon emission by 50,000 tons annually.
Dinesh Gandhi (Executive Director, GPIL)
whatever we mine will be consumed in the [pellet] plant. So we have no intention selling that [iron ore] on the market.
Abhishek Agrawal (Executive Director, GPIL)
as the generation increases, we will reduce our coal, fossil fuel burn, and we'll reduce the carbon emission. That's the whole idea.
Abhishek Agrawal (Executive Director, GPIL)

Transcript

We have not transcribed this call's recording. Read the company's transcript (PDF).

The stock after the call

After the callCloseStockNifty 50
Next session Mon 28 Oct 2024₹173.10−0.20%+0.65%
5 sessions Fri 1 Nov 2024₹198.12+14.22%+0.51%
20 sessions Tue 26 Nov 2024₹187.34+8.01%+0.06%

From the close of Fri 25 Oct 2024, ₹173.45: the close before the call day (the call's time is not on file). Adjusted daily closes; the move includes everything else that happened in those sessions.

Godawari Pow & Isp's other calls